20B0020_QandAs.pdf
PDF 104 KB Posted
- Attached to
- Install Emergency Cooling Tower Makeup Water Federal contract opportunity
- Solicitation number
- FA252120B0020
About this file
This solicitation and set of questions and answers concerns an emergency cooling tower makeup water installation project. The federal contract opportunity seeks bids for a firm-fixed price construction contract valued between $500,000 and $1,000,000 to provide all materials, labor, and equipment to install emergency makeup water systems for critical facilities at Cape Canaveral Space Force Station in the event of a loss of water. The work must be completed within 215 days of the notice to proceed according to the attached technical specifications and drawings. The North American Industry Classification System code for this requirement is 237110 for water, sewer line, and related structures construction. The small business contract size standard is $39.5 million, and this solicitation is set aside entirely for small businesses. The Department of the Air Force Space Command is the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WD FL20200001 (04Sep2020).pdf | ||
| Solicitation Amendment FA252120B00200001 SF 30.pdf | ||
| 20B0020_Supplemental_Drawings.pdf | ||
| Attach_1_Tech_Specs.pdf | ||
| Attach_4_ CECC_Form_3052.xls | XLS spreadsheet | |
| Solicitation - FA252120B0020.pdf | ||
| Attach_5_GPP_Forms.pdf | ||
| Attach_7_45_SFS_Badge_Request_Form.pdf | ||
| Attach_6_DB_WD_FL20200001_(14Aug2020).pdf | ||
| Attach_3__Questions_Template.docx | DOCX document | |
| Attach_2_Drawings.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA252120B0020 – INSTALL EMERGENCY COOLING TOWER MAKEUP WATER
QUESTIONS AND ANSWERS
Q‐1. C-501 shows bringing the well water piping underground into the Mechanical Building at the EPF. At the site visit, it was discussed bringing it in above ground through the wall. Please clarify which installation is correct.
A-1. At both the EPF and TSF, the pipe should be brought out of the ground outside the facility, adjacent to the wall, and then passed through wall to the pump equipment. In both cases, the wall must be sleeved. The required location at the TSF for the well and pump equipment is the secondary location shown on Sheet C-103, Flag Note 10. Attached is a supplement drawing for the TSF provided by the User.
Q-2. There aren’t any locations shown on the drawings where to connect to power for the EPF and TSF. How are the pumps to be connected?
A-2. At both the EPF and TSF, the User will show the contractor where to install the disconnect, and the User will run power to that location.