Answers to Questions recieved as of 17 Feb 2012.

View the file

Other files for this federal contract opportunity

Other files attached to Environmental Support Contract (ESC III), newest first.
File Type Posted
RFP Q A 6.docx DOCX document
RFP Q A 5.docx DOCX document
RFP Q A 4.docx DOCX document
12-R-0001 ESC III Amendment 2 Mod document.pdf PDF
12-R-0001 ESC Pre-Proposal Conference Mins.pdf PDF
RFP Q A 3.docx DOCX document
12-R-0001 Pre-Proposal Min Attach 1 Attendee List.pdf PDF
FA2521-12-R-0001 U0001 ESC III Amendment 1 Conformed Doc.rtf.doc DOC document
Attachment 8-Rev 1Proposal Worksheet Bid Schedule.xlsx XLSX spreadsheet
AF Form 332.pdf PDF
2009 PAFB Biennial Report 20100324.pdf PDF
Blank Success Story Format.pdf PDF
AF-Form-813-Environmental-Impact.pdf PDF
45 SW HazWaste 25 Reduction Candidate Waste Stream Blank.pdf PDF
Existing Environmental Databases Screen Shots 20120203.pdf PDF
FINAL_Cov Ltr.PDF PDF
APP_I-1.PDF PDF
App. A-1.PDF PDF
APP_TV-6.PDF PDF
0090005-010-avf.pdf PDF
Pmt_SOB.pdf PDF
FINAL_Cov_Ltrsigned.pdf PDF
FINAL_Cov_Ltr.pdf PDF
APP_TV-6.pdf PDF
SP_CND_07.pdf PDF
APP_H-1.pdf PDF
RCRA Operating Permit PAFB 15 Nov 2007.pdf PDF
20111228 CCAFS C D Landfill Permit.pdf PDF
CCAFS Landfill asbestos monofill permit 0614.pdf PDF
2011 DW Monitoring Requirements.pdf PDF
Example State Stormwater Permits —
Tab M 45SW Final Wildland Fire Management Plan_formatted.pdf PDF
Tab G Pest Management.pdf PDF
Tab D-2 Florida Scrub-jay Manag Plan.pdf PDF
Tab B Wetland and Floodplain Mgmt.pdf PDF
Tab C Coastal and Marine Resources.pdf PDF
Tab J Lands and Grounds.pdf PDF
45SW_INRMP_MainBody_1.pdf PDF
Tab O NEPA Documents.pdf PDF
Tab A Fish and Wildlife Management Plan.pdf PDF
Tab E Agricultural Outgrants.pdf PDF
Tab D-3 Scrub Habitat Restoration Plan.pdf PDF
Tab I Conservation Law Enforcement.pdf PDF
Tab K 45SW ISMP.pdf PDF
Attachment 2-Pricing Worksheet Bid Schedule.xlsx XLSX spreadsheet
Attachment 10 Question and Answer Template.docx DOCX document
Attchment 1b-Appendix E SAM.xlsx XLSX spreadsheet
Attachment 6-ESC III Past Perf Questionnaire 2 Dec 11.docx DOCX document
FBO NOTICE.docx DOCX document
Attachment 10 Question and Answer Template.docx DOCX document
Show all 50

Environmental Support Contract (ESC III) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA2521-12-R-0001 ESC III

RFP Question and Answer 2

Q1. Attachment 4: Do we need to have a Secret Facility Clearance at the time of proposal submission?

A1. No, Attachment 4 is a planning DD254. The contractor must meet the DD254 requirements at time of award.

Q2. General Information: Who is currently performing the work?

A2. Badger Technical Services (BTS) is the incumbent contractor.

Q3. RFP Section L Paragraph IV Past Performance pg 38: Paragraph b of this section states “Provide a comprehensive list of up to ten recent and relevant contracts…” Paragraph c states “a list of questionnaire recipients to include two current POCs and phone numbers for each contract reference provided.” Does this that if you provide 10 contracts that you expect 20 questionnaires?

A3. The Government request in Volume IV Past Performance a list with up to ten (10) recent and relevant contracts be listed and described with two (2) POCs for each contract listed. The Government request at least one (1) questionnaire be sent for each contract listed in Volume IV.

Q4. RFP Section L Paragraph IV Past Performance pg 38: Section c, paragraph 4 states “Any major subcontractors Performance Evaluation Questionnaire’ will be in addition to the 10 surveys provided for the prime offeror.” Does this mean that contracts for the major subcontractor are in addition to the 10 contracts from the prime? This says 10 surveys from the prime which seems to conflict with the statement in the previous question. Please clarify exactly what you are expecting to be submitted for past performance.

A4. Past Performance Information for major Subcontractors’ contracts should be in addition to the 10 contracts and questionnaires submitted as Past Performance Information for the Prime Offeror. Volume IV should have a separate list for contracts any major Subcontractor performed for which questionnaires were sent.

Q5. RFP Section M Paragraph Factor 2, Volume III Price Proposal pg 46: Paragraph d. Affordability: States: “A proposal which exceeds the budget may be determined unaffordable and ineligible for award.” Paragraph e. Budget. Budget information includes all CLINS.

FY 12FY 13FY 14FY 15FY 16FY17
.2M7.2M6.1M3.9M3.7M3.6M

The reduced budgets don’t seem to support the quantities that are provided in Attachment 8 which appear to remain pretty much constant. Which line items will most be affected by the significant budget decrease from FY 13 to FY 17?

A5. It is up to the offeror to propose cost efficiencies that result in a decrease in price in the out years.