STATEMENT OF WORK.docx

DOCX document 15 KB Posted

Attached to
Repair Fuel Cell Vapor Extraction System Federal contract opportunity
Solicitation number
FA2521-11-R-0030
Issued by
Department of the Air Force Space Command

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Repair Fuel Cell Vapor Extraction System, newest first.
File Type Posted
FA2521-11-R-0030 0002 New DBA WD.pdf PDF
DBA WD FL100017 dated 22 Jul 11.pdf PDF
11-R-0030 SF 30 Final.pdf PDF
11-R-0030 SF 30.pdf PDF
FA2521-11-R-0030.pdf PDF
GPP.pdf PDF
DBA Wages.PDF PDF
SXHT08-1113 Haz Waste Form.doc DOC document
11-R-0030 PERFORMANCE QUESTIONNAIRE.docx DOCX document
SXHT 08-1113 Repair Fuel Cell Vapor Extraction System 920th —
SXHT08-1113 REPAIR FUEL CELL Plans.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PROJECT SXHT08-1113, Repair Fuel Cell Vapor Extraction System, Bldg 647

The work to be performed under this project is located at Patrick Air Force Base. The contractor shall provide all labor, materials, equipment, transportation, and supervision to accomplish the following statement of work. All work shall be done in accordance with all local building codes, and the requirements contained in the J2 plans and specifications, dated February 2011.

Contractor work hours shall be 0730 to 1630, Monday through Friday, excluding federal holidays. Should it become necessary for work to be accomplished during weekends and holidays, the contractor is to provide written notification 72 hours prior to the desired days.

Scope:

The work to be performed under this project consists of providing the labor, equipment and materials to repair the fuel vapor extraction system at the fuel cell, Bldg 647.

Mechanical: Demolition and replacement of existing ventilation system for the modified fuel cell dock located in hanger 647 to include exhaust fans, controls, ductwork, hangers, supports and wiring.

Electrical: Demolish power and controllers for existing exhaust fans. Provide power and new controllers for new exhaust fans and HVAV equipment. Remove existing panel MPA and replace with new. Demolish existing fire alarm fan shutdown relays. Install new fire alarm fan shutdown relays that are activated by the fire alarm system.