STATEMENT OF WORK.docx
DOCX document 15 KB Posted
- Attached to
- Repair Fuel Cell Vapor Extraction System Federal contract opportunity
- Solicitation number
- FA2521-11-R-0030
About this file
Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA2521-11-R-0030 0002 New DBA WD.pdf | ||
| DBA WD FL100017 dated 22 Jul 11.pdf | ||
| 11-R-0030 SF 30 Final.pdf | ||
| 11-R-0030 SF 30.pdf | ||
| FA2521-11-R-0030.pdf | ||
| GPP.pdf | ||
| DBA Wages.PDF | ||
| SXHT08-1113 Haz Waste Form.doc | DOC document | |
| 11-R-0030 PERFORMANCE QUESTIONNAIRE.docx | DOCX document | |
| SXHT 08-1113 Repair Fuel Cell Vapor Extraction System 920th | — | |
| SXHT08-1113 REPAIR FUEL CELL Plans.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PROJECT SXHT08-1113, Repair Fuel Cell Vapor Extraction System, Bldg 647
The work to be performed under this project is located at Patrick Air Force Base. The contractor shall provide all labor, materials, equipment, transportation, and supervision to accomplish the following statement of work. All work shall be done in accordance with all local building codes, and the requirements contained in the J2 plans and specifications, dated February 2011.
Contractor work hours shall be 0730 to 1630, Monday through Friday, excluding federal holidays. Should it become necessary for work to be accomplished during weekends and holidays, the contractor is to provide written notification 72 hours prior to the desired days.
Scope:
The work to be performed under this project consists of providing the labor, equipment and materials to repair the fuel vapor extraction system at the fuel cell, Bldg 647.
Mechanical: Demolition and replacement of existing ventilation system for the modified fuel cell dock located in hanger 647 to include exhaust fans, controls, ductwork, hangers, supports and wiring.
Electrical: Demolish power and controllers for existing exhaust fans. Provide power and new controllers for new exhaust fans and HVAV equipment. Remove existing panel MPA and replace with new. Demolish existing fire alarm fan shutdown relays. Install new fire alarm fan shutdown relays that are activated by the fire alarm system.