This document is a Questions and Answers (Q&A) document related to the federal contract opportunity for the OSP Fiber Optic Cable Upgrade project.

The key details are:

  • This is a new requirement, not an incumbent contract.
  • The contractor must have an existing Facility Clearance Level (FCL) to be rated technically acceptable and eligible for award, as the period of performance does not allow time to obtain a new clearance.
  • The government is not providing sponsorship for an FCL.
  • The Solicitation Number is FA251724Q00591, and the contract is for the Department of the Air Force Space Command to engineer, furnish, install and test single mode Fiber Optic Cables to multiple Critical End Buildings on Cheyenne Mountain Space Force Station.

View the file

Other files for this federal contract opportunity

Other files attached to OSP Fiber Optic Cable Upgrade, newest first.
File Type Posted
Combo CO signed.pdf PDF
Attachment 1 - SOW.pdf PDF
Attachment 2 - CLIN Price Sheet.xlsx XLSX spreadsheet
Attachment 3 - Clauses and Provisions (additional).docx DOCX document
Attachment 10 - QA from Previous Solicitation.docx DOCX document
Combo .pdf PDF
Attachment 5 - DD Form 254.pdf PDF
Attachment 7 - Complex 1st Floor Map.pdf PDF
Attachment 8 - Complex 2nd floor Map.pdf PDF
Attachment 9 - Complex 3rd Floor Map.pdf PDF
Attachment 4 - Wage Determination.txt TXT text file
Attachment 6 - Raytheon Lead Results.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A

PROJECT: OSP FOC UPGRADE CMSFS

PROJECT NUMBER: FA2517-24-Q-0059

CONTRACTOR QUESTION
GOVERNMENT RESPONSE
1.
Do we have time to obtain Secret Clearances?
No, due to the period of performance the contractor must have an existing FCL to be rated technically acceptable and be eligible for award.
2.
Can we apply after award?
No, due to the period of performance the contractor must have an existing FCL to be rated technically acceptable and be eligible for award.
3.
Is the Government providing the Prime so we can get a clearance?
The government is not providing sponsorship for an FCL.
4.
Is this a brand-new requirement? If not, who was the incumbent/previous contract number?
This is a new requirement.