Attachment 1 - DEL 7 Carpet Replacement SOW - 19 May 23.docx

DOCX document 389 KB Posted

Attached to
Delta 7 Bldg 361 Carpet Replacement Federal contract opportunity
Solicitation number
FA251723Q0120
Issued by
Department of the Air Force Space Command

About this file

This statement of work outlines requirements for a carpet replacement project at Building 361 at Peterson Space Force Base. The contractor will remove existing carpet and install new carpet and wall base in various rooms totaling approximately 5,967 square feet, as detailed in appendices providing floor plans and room-specific requirements. The project will be managed according to terms specifying initiation requirements, material delivery and installation procedures, inspections, closeout procedures, security access, and general information regarding warranties, facility information, and operational hours and holidays. The related federal contract opportunity is a solicitation from the Air Force seeking to fulfill the carpet replacement project at Delta 7 Building 361 as described in the statement of work.

View the file

Other files for this federal contract opportunity

Other files attached to Delta 7 Bldg 361 Carpet Replacement, newest first.
File Type Posted
RFQ_DEL 7 Bldg 361 Carpet - Amendment 3.pdf PDF
RFQ_DEL 7 Bldg 361 Carpet - Amendment 2.pdf PDF
Amendment 1 - RFQ_DEL 7 Bldg 361 Carpet.pdf PDF
DEL 7 Carpet Replacement PWS- Final v2.pdf PDF
RFQ_DEL 7 Bldg 361 Carpet.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

CARPET REPLACEMENT OF

SPACE DELTA 7

BLDG 361

AT

150 DOVER STREET

PETERSON SFB, CO 80917-1129

19 May 2023

TABLE OF CONTENTS

Section
Title
Page
1.0
DESCRIPTION OF SERVICES
3
1.1
Specific Requirements
3
1.1.1
Removal of Existing Carpet and Wall Base
3
1.1.2
Installation Of New Carpet And Wall Base
3
1.1.3
Government Directed Vendors
3
1.1.4
Site Clean-Up
3
1.2
Initiation Requirements
4
1.3
Material Delivery, Installation And Inspection
4
1.4
Post Installation Inspection
4
1.5
Close-Out Requirements
4
1.5.1
Punch List/Close Out
4
1.5.2
Task Verification/Acceptance
4
2.0
PROJECT MANAGER & POC
4
3.0
SECURITY & ACCESSES
4
3.1
Access to PSFB
4
3.2
Access to B361
5
4.0
GENERAL INFORMATION
5
4.1
Mission Black-Out Times
5
4.2
Warranty
5
4.3
Project Location
5
4.4
Licenses and Permits
5
4.5
Personal Property
5
4.6
Safety Requirements
5
4.7
Availability of Utility Services
6
4.8
Hours of Operation
6
4.9
Federal Holidays
6
APPENDIX A:
BUILDING 361 FLOOR PLAN

BUILDING 361 FLOOR PLAN

APPENDIX B:
SQUARE FOOTAGE WORK REQUIREMENTS BY ROOM
APPENDIX C:
MANDATORY USE CARPET COLORS
1.0DESCRIPTION OF SERVICES: (1) Removal and disposal of existing carpet and wall base in the rooms listed throughout Building 361 (B361) Space Delta 7 Headquarters (DEL 7 HQ) (specific rooms listed in Appendix B). (2) All labor, material, equipment, transportation and storage required to install new carpet and wall base for the rooms listed in Appendix B. This equates to about 5,967.5 sq-ft of area.
1.1SPECIFIC REQUIREMENTS: The contractor shall provide the above detailed in accordance with Appendix A and Appendix B, which illustrates the B361 floor plan and lists approximate square footage of carpet areas per room; contractor is responsible for all field measurements prior to ordering the materials; Appendix C shows carpet colors from each vendor on the Air Force Mandatory Use list. The DEL 7 Project Manager (PM) will review any refinements or changes to the package.
1.1.1REMOVAL OF EXISTING CARPET AND WALL BASE: The contractor is responsible for removal and disposal of existing carpet in the same rooms detailed in Appendix B. The contractor is responsible for preparing the flooring for receiving new adhesive, as needed. The contractor will carefully remove all existing wall base in the same rooms detailed in Appendix B, taking care not to damage the wall finish or paint above the area where the base is being removed. Should the paint or wall become damaged during the removal process, the contractor will be responsible for repairing the damages, ensuring that the repairs match the existing finish and color.
1.1.2.INSTALLATION OF NEW CARPET AND WALL BASE: B361 has very little internal storage room due to the critical shortfall of DEL 7 workspace and high numbers of personnel. Therefore, if the contractor cannot safely store materials outside the facility (there is a concreate, walled pad near the Mechanical Room entrance; see Appendix A) the contractor will need to find other storage solutions. The carpet will be tiled. Modular furniture, or other furniture, exists in most rooms, and the contractor must use minimally invasive techniques to install carpet tiles under furniture. Care must be taken not to damage existing furniture, cabling, and especially fiber optic cables (which are often strung near the floor). Any damages by the contractor will be the responsibility of the contractor to fix or pay for (government’s choice). The building occupant will receive a schedule of rooms to service in advance, and will remove computers, roller chairs, and other easily relocatable items (does not include medium/large cabinets, refrigerators, safes, sofas, and desks), from off the floor, and will make a good-faith effort to lift cabling from off the floor (though this may be difficult or unnecessary in some cases; this will be coordinated between the PM and contractor in advance). The occupant is responsible for removing all personal items prior to work. Three server racks in the LAN Room are bolted to the concrete and it is permissible that existing carpet be left in place in a rectangular box surrounding the rack. Carpet must be of commercial grade, heavy foot traffic with equal or greater than ten years expected life, and minimum five thousand (5,000) pile density and must contain stain resistant/release characteristics. Color and pattern reference is posted in Appendix C. Carpet adhesive must contain minimal to no volatile organic compounds (VOC) to accommodate the quickest resumption of operations by DEL 7 personnel. There is no requirement for cushion. All wall base will be of long-duration/durability, at a height of at least 4” throughout (from the top of the carpet), and in a color complimentary to existing wall color and future carpet.
1.1.3.GOVERNMENT DIRECTED VENDORS: The Mandatory Carpet Initiative dictates that carpet will be purchase from one of the following vendors at Government Deviated Pricing and that pricing will be passed on. The color selected shall be from one of the manufactures J&J Flooring, Mowhawk Inc., or Shaw Inc. (See Appendix C for color options)
1.1.4.SITE CLEAN-UP: The Contractor will be responsible for site clean-up daily and upon work completion. This includes but is not limited to removal and proper disposal of debris, as well as restoration of furniture to its proper/specified and uniform position in locations after the work is complete. The Government will designate a location for a contractor provided dumpster, if necessary. Contractor is responsible for off-site disposal of removed carpet/rubber flooring.
1.2INITIATION REQUIREMENTS: Prior to commencement of work, the Contractor and Government will agree upon a schedule for installation. The Government maintains the right to refuse any particular requested dates and the Contractor is not guaranteed consecutive installation dates. The Contractor shall not begin any work until they are 100% materials in-hand.
1.3MATERIAL DELIVERY, INSTALLATION and INSPECTION: The Contractor will be allowed to use either the front (Room 101), sides (Rooms 110 and 131) and back door entry (Room 125) for the removal or loading of carpet and materials. Due to concurrent use and operations within B361, there will be very limited pre-staging of materials within the facility. The Contractor will protect all landscape, site work, and building façade during this process.
1.4POST INSTALLATION INSPECTION: The PM will conduct a Post-Installation Inspection after all carpet and wall base is in place. All project spaces will be inspected for completion and damage. All new damages will be the responsibility of the Contractor to repair or replace at no additional cost to the government. A single punch list will be compiled for submittal to all parties by the Contracting Officer. Post-Installation Inspection will be attended by Contractor and Government personnel.
1.5CLOSE-OUT REQUIREMENTS:
1.5.1PUNCH LIST/CLOSE OUT: All punch lists and punch list items will be completed within 14 days of final inspection. Any items that cannot be completed in that period of time will be addressed in writing by the Contractor. This correspondence will indicate the agreed to completion date.
1.5.2TASK VERIFICATION/ACCEPTANCE: A Government Representative will be on site to verify all steps of installation. Contractor will provide written documents to the Government Representative for record keeping. The building occupant and Government Representative will perform acceptance inspections upon completion of all stated work.

2.0 PROJECT MANAGER & POC: The DEL 7 PM will be available throughout this project to provide direction. The PM will provide all necessary construction documents and resources at the Contractor’s request. PAFB DEL 7 Primary POC is Mr. David Smith, 719-556-0917, david.smith.451@spaceforce.mil; the alternate POC is Sgt Cory Winston, 719-556-5278, cory.winston@spaceforce.mil.

3.0SECURITY & ACCESSES:
3.1ACCESS TO PSFB: Obtain all necessary cards, passes, decals, or other items required for access to PSFB, with Government Representative support as needed. The contractor will be allowed non-escorted access to specific Government buildings on Peterson AFB consistent with Task requirements. Submit a Visit Request Letter on company letterhead through the Government Representative at least (14) duty days prior to the scheduled visit. Letters must specify location of work being performed at PSFB. The Security POC of the company must sign the request. Letters for entry should be 31 days or more in the event of delayed entry. It will be the Contractor’s responsibility to update the list as personnel changes occur. Background checks will be accomplished on all listed personnel. The following information for all Contractor employees must be on file with the 21st Security Forces before entry is approved:

Full Name:

D.O.B.

Social Security Number:

Reason for the Visit:

Date and Duration of the Visit:

Name and Address Company:

Point of Contact, Telephone No:

Required information of vehicle operator and vehicle for access to base.

Full Name:

Current Driver’s License:

Make/ Model, Year of Vehicle:

Color:

License Plate # and state of issue:

Current Insurance:

Current Vehicle Registration:

3.2 ACCESS TO B361: The contractor must be escorted into B361 at all times during work within the B361. The building users will provide escorts. Pre-coordination will be required with the PM to ensure the proper number of escorts are provided during work hours. Pre-coordination must be finalized at least six business days (M-F) before any entry into B361.

4.0GENERAL INFORMATION
4.1MISSION BLACK-OUT TIMES: Due to real-world mission requirements performed by DEL 7, the building user reserves the right to deny contractors entry to the facility with little or no prior notice. Although every effort will be made by the PM to provide as advanced notice as possible, due to mission needs it is possible entry could be denied the contractor the day of, or that the escorted personnel must be removed during work hours. This is not expected or common.
4.2WARRANTY: Warranty shall be provided for all products against all defects in materials and workmanship, for a one year period based on manufacturer’s warranty from the acceptance date. The Contractor shall provide a point of contact to interface with the Government Purchase Card holder and/or Government Representative on issues concerning installation and warranty service.
4.3PROJECT LOCATION: The Project Site is the Space Delta 7 HQ, Bldg. 361, 150 Dover Street, Peterson SFB, Colorado 80914. Use East Gate, off Marksheffel Road, for truck deliveries.
4.4LICENSES AND PERMITS: The Contractor shall be responsible for obtaining all necessary licenses and permits, complying with all federal, state, and municipal laws, codes and regulations applicable to the performance of the work It is the responsibility of the Contractor to determine if permits and licenses are required by federal, state or local agencies and submit copies of any required permit to the Government.
4.5PERSONAL PROPERTY: The building users will be responsible to relocate all personal property and office files from their current workstations.
4.6SAFETY REQIREMENTS: Safety requirement shall be the applicable sections of EM 385-1-1, Oct 1992 and Occupational Safety and Health Administration (OSHA) Regulations. The contractor shall ensure that any lifting devices or ladders meet any and all applicable safety standards. The contractor shall be required to use those lifting devices that will allow for the existing furniture to be raised for the installation of the new materials requested.
4.7AVAILABILITY OF UTILITY SERVICES: All reasonable quantities of utilities will be made available to the contractor. The Government shall not be held responsible for interruptions of utility services, and will not be liable for contractor delays, damages, or increased costs incurred by any such interruption of service.
4.8HOURS OF OPERATION: Perform work under this contract during normal hours of operation, Monday – Friday, 7:00am – 4:00pm. Pre-approval must be obtained from the CO (Contracting Officer) for changes in work hours or to schedule weekend/holiday work.
4.9FEDERAL HOLIDAYS: The following are recognized Federal Holidays. The Contractor will not be required to work on these days.

New Year’s Day

President’s DayLabor Day
Memorial DayColumbus Day
Juneteenth DayMartin Luther King
Independence DayVeteran’s Day
Thanksgiving DayChristmas Day

APPENDIX A

BUILDING 361 FLOOR PLAN

MENS

JANITOR

CCC

CV 105

TD

FRONT

VESTIBULE 101

WOMENS 134

71 CC

ENTRY

EXEC. SECRETARY 103

CC

NURSING

OPEN OFFICE 131

CC CONFERENCE

72 VEST.

72 CC

72 DO

SECURITY

LAN OFFICE 121

COMM 128

TRAINING ROOM

ELEC 129

72 SEL

72 OPEN OFFICE

72 S6

MECH 130

CORNER OFFICE 122

APPENDIX B

SQUARE FOOTAGE WORK REQUIREMENTS BY ROOM

Room
Square Feet
Dimensions

(per blueprint)

Wall Base
Floor Type
102 – Entrance
99.7
10’ 6 ½” x 9’ 5 ½”
Yes
Carpet
131 – Open Office
1,577.1
51’ 8 ½” x 30’ 6”
Yes
Carpet
114 – 71 CC
165.8
17’ 4 ½” x 9’ 6 ½”
Yes
Carpet
103 – Exec Secretary
274.1
17’ 6 ½” x 15’ 7 ½”
Yes
Carpet
104 – TD
100.5
10’ 10 ½” x 9’ 2 ½”
Yes
Carpet
105 – CV
97.1
10’ 6 ½” x 9’ 2 ½”
Yes
Carpet
106 – CCC
175.7
17’ 6” X 10’ ½”
Yes
Carpet
107 – CC
284.8
20’ ½” x 14’ 2 ½”
Yes
Carpet
109 - Nursing
116.9
17’ 2 ½” x 6’ 9 ½”
Yes
Carpet
110 – CC Conf
670.1
37’ 8 ½” X 17’ 9 ½”
Yes
Carpet
124 – 72 Vestibule
59.5
10’ 1 ½” x 5’ 10 ½”
Yes
Carpet
125 – 72 Open Off
1,117.4
49’ 2 ½” x 22’ 8 ½”
Yes
Carpet
123 – Security
142.1
14’ 2 ½” x 10’
Yes
Carpet
117 – 72 DO
138.8
13’ 10 ½” x 10’
Yes
Carpet
126 – 72 CC
139.8
14’ 11” x 9’ 4 ½”
Yes
Carpet
127 – 72 SEL
84.0
8’ 11 ½” x 9’ 4 ½”
Yes
Carpet
122 – Corner Office
84.0
8’ 11 ½” x 9’ 4 ½”
Yes
Carpet
121 – LAN Office
126.7 (does not include server areas)
14’ 10 ½” x 10’
Yes
Carpet
119 – Training Room
359.7
22’ 6 ½” x 15’ 11 ½”
Yes
Carpet
118 – 72 S6
153.7
17’ x 9’ ½”
Yes
Carpet

APPENDIX C

MANDATORY USE CARPET COLORS

Room
J&J Flooring
Mohawk
Shaw
103 – Exec Secretary
1993 Ingrain embossed with

10 ½” accent border along walls of 1978 Vibrant 593 Navy Gray with 10 ½” accent border along walls of 353 Tango 00570 Flying Saucer with 10 ½” accent border along walls of 00851 Regal Red

107 – CC
1993 Ingrain embossed with

10 ½” accent border along walls of 1978 Vibrant 593 Navy Gray with 10 ½” accent border along walls of 353 Tango 00570 Flying Saucer with 10 ½” accent border along walls of 00851 Regal Red

110 – CC Conf
1993 Ingrain embossed with

18” accent border along walls of 1978 Vibrant 593 Navy Gray with 18” accent border along walls of 353 Tango 00570 Flying Saucer with 18” accent border along walls of 00851 Regal Red

ALL OTHER ROOMS
1993 Ingrain embossed
593 Navy Gray
00570 Flying Saucer

* Carpet tile pattern desired is one that provides the least visual break in between tiles (possibly vertical ashlar, but subject to change based on specific tile pattern properties and aesthetics).

image1.png image2.png image3.png image4.png image5.png

File details come from the government source that posted it. Updated .