This is a Statement of Objectives (SOO) for a bird netting installation project at Building 190, Nellis Air Force Base, Nevada, dated 13 April 2026.
The primary objective is to install approximately 37,800 square feet of Premium PolyNet bird netting in two hangar bays to prevent birds from roosting and nesting. The installation shall utilize 9-gauge and 11-gauge tension wire, twist lock clips, and poly clips across the entire ceiling area, including under trusses, and down three walls (excluding hangar doors) from approximately 10 feet above the floor to the ceiling with no breaks in the netting. The project is located at 5507 Tyndall Avenue, Nellis Air Force Base, Nevada 89084. Standard working hours are 7:00 a.m. to 4:00 p.m., Monday through Friday, excluding Federal Holidays and the day after Thanksgiving. The contractor must clean all job-related debris daily and upon project completion. A post-construction inspection will be conducted with the contractor, Civil Engineer, and customer present. All work must comply with applicable federal, state, local, and NAFB laws and regulations, including NAFB Management Plan 12, and conform to industry standards and manufacturer recommendations. Work must also comply with the National Electric Code (NFPA 70), Uniform Mechanical Code, NFPA 54, ASME CSD-1, International Building Code (2009 Edition), DoD Unified Facilities Criteria Standards, and Unified Plumbing Code. The government, through the 99 CES Representative, will periodically evaluate contractor performance, and the system must be 100 percent operational upon project completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| Attachment 1 - Specifications.pdf | ||
| Combo Synopsis Solicitation.pdf | ||
| Attachment 2 - Building Layout.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOO-1
STATEMENT OF OBJECTIVES
FOR
BUILDING 190
NELLIS AIR FORCE BASE, NEVADA
13 April 2026
OFFICE OF THE BASE CIVIL ENGINEER
NELLIS AIR FORCE BASE, NEVADA
SOO-2
STATEMENT OF WORK
1. OVERVIEW: Hangar 190 does not currently have bird netting on the ceiling or side walls.
This has caused issues with maintaining a clean environment in the hangar. Bird netting is required to keep birds from roast and nest in the hangar.
SCOPE: The purpose of the contract is to install approximately 37,800SF of Premium PolyNet bird netting in two hangar bays using 9ga and 11ga tension wire, twist lock clips and poly clips on the entire ceiling area to include under trusses and down three (3) walls (hangar doors will not be included) past bottom side wall girts from approximately 10ft from the floor up to the ceiling with no breaks in the netting to ensure birds do not roast or nest. At the end of each day and at the completion of the project, the contractor will clean all job-related debris from area. A post construction inspection will be conducted with contractor, CE and the customer.
1. LOCATION: The project site is located at Nellis Air Force Base, Nevada. The Main Base is located approximately 9 miles north of downtown Las Vegas on Highway US 93 (Las Vegas
Blvd.). NAFB consists of three main areas: the Main Base, Area II, and Area III. The specific project location is on 5507 Tyndall Ave, NAFB, NV, 89084. Building number 190.
2. ENVIRONMENTAL PROTECTION: All work and the contractor’s operations shall comply with the requirements imposed by all applicable federal, state, local, and NAFB laws, regulations, codes, and permits (including NAFB Management Plan 12) concerning environmental protection. If required per the task in the area where work is to be performed, an asbestos-containing material and a lead-based paint test will be done by the 99 CES.
3. CONTRACTOR PERSONNEL: The contractor’s personnel shall conduct themselves in a professional manner.
4. QUALITY ASSURANCE: The government, through the 99 CES Representative, will periodically evaluate the contractor’s performance in accordance with the specific contract performance requirements.
5. WORKING HOURS: Standard working hours are from 7:00 a.m. to 4:00 p.m. Monday through Friday excluding Federal Holidays and the day after Thanksgiving.
6. GENERAL CONDITIONS: All work must be in compliance with and conform to industry standards and applicable manufacturer’s recommendations. Any electrical wiring, connections, and structural designs shall be installed IAW latest version of the NFPA 70 National Electric Code
(NEC), Uniform Mechanical Code, and NFPA 54, ASME CSD-1 (Controls & Safety Devices).
All work must be in compliance with the International Building Code (IBC). 2009 Edition, DoD
Unified Facilities Criteria Standards (UFC) Unified Plumbing Code (UPC) and all accepted industry practices. At the completion of the project, the system should be 100% operational.