This document consists of Questions and Answers related to a federal contract opportunity for the 57 MXG AGE Nitro Cart Power Install project. The key details are:

The project does not have a provided cost estimate or budget. The start date will be determined after drawings and paperwork are approved, with a 30-day period of performance from the notice to proceed. The appropriate size conduit will be used for the required wiring, with work hours from 0630 to 2300. Outages can occur during normal work hours if advance notice is provided. The conduit should be surface-mounted where possible, otherwise suspended or passing through walls.

The related federal contract opportunity is a solicitation for commercial services, with the goal of awarding to the responsible offeror who submits a conforming quote rated "Acceptable" on technical capability and the lowest total evaluated price. A site visit is scheduled for July 11, 2024, with questions due by July 17, 2024 and offers due by July 31, 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

1 - Is there a cost estimate, budget or ballpark figure for the project listed?

A - An estimated budget will not be provided for this requirement.

2 - Is there an actual start date for the project?

A - Start date will be determined after all drawings and paperwork is approved. Period of Performance will be 30 days from notice to proceed.

3- Confirming the size of conduit for new run?

Whatever appropriate size conduit is for the required wiring.

4- Confirming work hours for construction?

0630 – 2300

5- If outages are required, what are the work hours for the outages?

Outages can occur during normal work hours assuming you can give us some advanced warning before these outages occur

6- Confirming we are to surface mount the conduit?

Surface mount where possible, otherwise will be suspended or in some cases passing through walls