This document is a set of Questions and Answers related to a federal contract opportunity for a K9 Turfpad requirement at Maxwell AFB. The solicitation is a competitive best value acquisition utilizing Simplified Acquisition Procedures, where offers will be evaluated on Technical Acceptability and Price. Key details include: there is no existing turf system currently in place, the product needs to be green and cover approximately 7,000 sq ft, with storm drains and a crushed gravel base to assist with water drainage. The period of performance is preferably 30 days, and the work can be completed on weekends with materials shipped to the job site in advance. The solicitation does not specify a design-build requirement, but indicates the contracting company should provide the turf specification. The turf will be installed outdoors and should include rubber balls.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

Question

1. Could you provide a make and model of the system you have in place currently?

Answer: We do not have a turf system in place currently.

Question

2. Could you provide pictures of the existing conditions?

Answer: Yes

Question

3. Does the end user have a preference as to what system they would like installed.

Answer: The product needs to be green and by 7000 sqft.

Question

4. What is the existing drainage system?

Answer: Two storm drains are in our break yard currently

Question

5. Can the work be completed on weekends?

Answer: Yes

Question

6. Can materials be shipped to the job site in advance?

Answer: Yes

Question

7. What is the period of performance for this contract?

Answer: Preferably 30 days

Question

8. Will a spec on the turf be provided?

Answer: This should be provided by the contracting company

Question

9. Is the turf Inside or outside?

Answer: It will be outside

Question

10.Is this a design build?

Answer: No

Question

11. Are there rubber balls in the turf?

Answer: There should be.

Question

12. Is there a crushed gravel base?

Answer: There needs to be to assist with water drainage

Question

13. Are there French Drains under that?

Answer: There needs to be to assist with water drainage.