F2QT044004AW02 - 365 ISRG Corrosion Paint Booth - Questions and Answers.pdf

PDF 140 KB Posted

Attached to
365 ISRG Corrosion Paint Booth
Solicitation number
F2QT044004AW02-1
Issued by

About this file

This document contains Questions and Answers related to the Federal Contract Opportunity for the 365 ISRG Corrosion Paint Booth project. The contract opportunity is a Request for Quote (RFQ) issued by the Department of the Air Force Air Combat Command, with the primary CLIN for a Paint Spray Booth with a paint mix room. Other CLINs include an HVAC system, sprinkler fire protection system, and an oil-free compressor. The solicitation has a 100% Small Business set-aside with a NAICS code of 332311 - Prefabricated Metal Building and Component Manufacturing. Offers are due on April 11, 2024 at 10:00 am PDT, and the Government intends to award a single Firm-Fixed Price contract to the responsible offeror with the lowest total evaluated price. The document provides clarification on the dimensions of the paint booth, mix room, and other requirements outlined in the Statement of Work and Nellis & Creech Air Force Bases Installation Facilities Standards.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F2QT044004AW02 – 365 ISRG Corrosion Paint Booth

Ques�ons & Answers

3 April 2024

1. One of the pictures is an overhead view (atachment 3) with a yellow outline which seems to carve out the area around the electrical panels and I assume to be the area in which we have to build? Is this correct?

Yes. The area in yellow is the area the installer has available for the installa�on. The area in the southeast corner (lower right) is where the electrical panels are. Per the NEC, a three (3) foot space is required between the wireway and the structure.

2. Apparently, you changed the length of the booth from approximately 43’ to a minimum of 25’. Is that the working depth or the total depth? The exhaust filter area takes up about 4’ at the rear of the booth. Would 30’ be adequate?

The minimum working depth would be 25’. A working depth of 30’ would be more than sufficient provided the other dimension is 20’ or greater.

3. You stated the mix room cannot be more than 150 square-foot. I assume that does not include the clean room, which is atached to it. The clean room was requested by your personnel, if not required please let me know.

Per the regula�ons, the mix-room cannot be more than 150 square feet. Since the clean room is a separate room, this square footage is not to be included in that calcula�on. The clean room will be eight

(8) feet by nine (9) feet (This addi�on has been added to the SOW and is highlighted in red).