KELL 15-0014
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Purpose: To change the Period of Performance.
Changing Period of Performance from 185 Calendar Days to 290 Calendar Days.
Contracting Officer: Dorothy Ann Coleman, 210-671-6083, dorothy.coleman@us.af.mil
Contracting Administrator: SrA Casey McCracken, 210-925-1842, casey.mccracken@us.af.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Sep-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA3047-15-R-0057
X 9B. DATED (SEE ITEM 11)
20-Aug-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Sep-2015
CODE
502D CONTRACTING SQUADRON
1655 SELFRIDGE AVE
JBSA LACKLAND TX 78236-5253
FA3047 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA3047-15-R-0057
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The contractor period of performance end date has increased by 105 days from 185 days to 290 days.
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0001
The CLIN extended description has changed from 60% Design Renovate Building 200830 Calendar days after NTPIAW Statement of Work, dated 06 July 2015 to 60% Design Renovate Building 200845 Calendar days after NTPIAW Statement of Work, dated 06 July 2015.
CLIN 0002
The CLIN extended description has changed from 95% Design Renovate Building 200830 Calendar days after NTPIAW Statement of Work, 06 July 2015 to 95% Design Renovate Building 200845 Calendar days after
NTPIAW Statement of Work, 06 July 2015.
CLIN 0003
The CLIN extended description has changed from 100% Design Renovate Building 2008.15 Calendar days after NTPIAW Statement of Work, dated 06 July 2015 to 100% Design Renovate Building 2008.30 Calendar days after NTPIAW Statement of Work, dated 06 July 2015.
CLIN 0004
The CLIN extended description has changed from Extended Description: Provide all supervision, labor, materials, equipment, supplies, and transportation necessary for construction efforts to renovate Bldg 2008 at JBSA
Lackland, TX IAW SOW dated 06 July 2015110 Calendar days after NTP. The 110 calendar days is the total Period of Performance for CLINS 0004 and 0005.Minor Cost LOA to Extended Description: Provide all supervision, labor, materials, equipment, supplies, and transportation necessary for construction efforts to renovate Bldg 2008 at
JBSA Lackland, TX IAW SOW dated 06 July 2015170 Calendar days after NTP. The 110 calendar days is the total
Period of Performance for CLINS 0004 and 0005.Minor Cost LOA.
SECTION F - DELIVERIES OR PERFORMANCE
The following Delivery Schedule item for CLIN 0001 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
30 dys. ADC 1 AFIWC 23IOS F2MU23
STEVEN HOPKINS
404 GREIG ST BLDG 178
SAN ANTONIO TX 78226-1844
(210)925-0357
FOB: Destination
F2MU23
To:
45 dys. ADC 1 AFIWC 23IOS F2MU23
404 GREIG ST BLDG 178
SAN ANTONIO TX 78226-1844
(210)925-0357
The following Delivery Schedule item for CLIN 0002 has been changed from:
404 GREIG ST BLDG 178
SAN ANTONIO TX 78226-1844
(210)925-0357
45 dys. ADC 1 AFIWC 23IOS F2MU23
404 GREIG ST BLDG 178
SAN ANTONIO TX 78226-1844
(210)925-0357
The following Delivery Schedule item for CLIN 0003 has been changed from:
15 dys. ADC 1 AFIWC 23IOS F2MU23
404 GREIG ST BLDG 178
SAN ANTONIO TX 78226-1844
(210)925-0357
404 GREIG ST BLDG 178
SAN ANTONIO TX 78226-1844
(210)925-0357
The following Delivery Schedule item for CLIN 0004 has been changed from:
110 dys. ADC 1 AFIWC 23IOS F2MU23
404 GREIG ST BLDG 178
SAN ANTONIO TX 78226-1844
(210)925-0357
170 dys. ADC 1 AFIWC 23IOS F2MU23
404 GREIG ST BLDG 178
SAN ANTONIO TX 78226-1844
(210)925-0357
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 290. The time stated for completion shall include final cleanup of the premises.
60% Design Efforts – 45 calendar days after NTP
95% Design Efforts – 45 calendar days after NTP
100% Design Efforts – 30 calendar days after NTP
Construction Efforts for CLINS 0004 and 0005 – 170 calendar days total after NTP
(End of clause)
(End of Summary of Changes)