Attachment_1_-_Statement_of_Work.pdf

PDF 91 KB Posted

Attached to
HVAC Modification Federal contract opportunity
Solicitation number
F2MRAA6015AW01
Issued by
Department of the Air Force Air Education and Training Command

About this file

Attachment 1 - Statement of Work

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA3016-16-R-0079 Attachment 1

SCOPE OF WORK

17 August 2016

1. PROJECT NUMBER: JBSF140047

2. TITLE: RENV-Modify HVAC Sys to Increase Room Ventilation, B3260

3. PROJECT LOCATION: JBSA Fort Sam Houston

4. GENERAL DESCRIPTION OF WORK

Building 3260, the Tri Services Research Laboratory is a medical research facility with admin, laboratory, vivarium, surgery and warehouse areas and chamber rooms with a gross square footage of appx. 150,000 square feet.

The facility HVAC system consists of two 700 ton water cooled chillers and associated cooling towers, various hot water and steam boilers, 7 air handling units with supply air flow rates ranging from 17,000 to 46,000

CFM, numerous small air handlers and fan coil units and approximately 350 supply, return and exhaust terminal units.

Work under this contract is limited to relocating the exhaust grille and duct work to finished floor level and for modifying the HVAC system as necessary to provide a minimum ventilation rate of 15 total air changes per hour (ACH) in the following rooms: 3059, 3061, 3063, 3066, 3065, 3173, 3177, 3202, 3198, 3199, 3203 and 3160, and for increasing the ventilation rate to 15 ACH only in rooms 3057 and 3015 (no relocation of exhaust components in these rooms).

All rooms have 100% outside air. Rooms are served either by AHU 7 or by

AHUs 5&6. These rooms will be converted to operating rooms, similar to existing operating rooms 3060, 3062 and 3064.

4.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

DoD Unified Facilities Criteria (UFC)

UFC 4-510-01 (1 November 2012 Change 1, May

2014)DESIGN: MILITARY MEDICAL FACILITIES

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2008; Errata 2011) Safety and Health

Requirements Manual

5. APPLICABLE DETAILED SPECIFICATIONS: DIVISION 1 THROUGH 32

DIVISION 01 GENERAL REQUIREMENTS

01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 13.20 00 SPECIAL PROJECT PROCEDURES- CAD

01 35 29 OCCUPATIONAL SAFETY AND HEALTH

01 35 30 SAFETY, HEALTH AND EMERGENCY RESPONSE

01 35 35 ENVIRONMENTAL PROTECTION

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 20 CONTRACTOR QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 54 23.00 SCAFFOLDING TUBULAR STEEL

01 56 00.00 44 DUST CONTROL

01 71 23.16 CUTTING AND PATCHING

01 72 00.00 44 ALTERATIONS TO EXISTING FACILITIES

01 74 19.00 CONSTRUCTION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 36.00 WARRANTY OF CONSTRUCTION

01 91 13.00 23 GENERAL COMMISSIONING REQUIREMENTS

DIVISION 09 - FINISHES

09 57 13 GFRP CEILINGS

09 96 00 HIGH-PERFORMANCE COATINGS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

6. PERFORMANCE SPECIFICATIONS/DETAILED SCOPE OF WORK:

6.1 DEMOLITION

Contractor shall use means and methods to minimize excessive dust and noise. If excessive noise during demolition/construction is unavoidable contractor shall notify the contracting officer or designated government representative within a minimum of 7 (seven) working days in advance to allow for coordination with building manager.

6.1.1 Architectural/Interior

See Attachment 5, Design Drawings.

6.1.2 Mechanical

See Attachment 5, Design Drawings.

6.1.3 Existing Devices

Existing devices shall remain in place during renovation work. Contractor shall protect devices to prevent damage.

AIR SUPPLY, DISTRIBUTION, VENTILATION, AND

EXHAUST SYSTEMS

COMMON PIPING FOR HVAC

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING

AND EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 08 00.00 23 COMMISSIONING OF HVAC SYSTEMS

23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC

6.2 NEW WORK

Contractor shall supply labor and new materials unless otherwise specified to provide a complete and usable system.

6.2.1 Architectural

6.2.1.1 GFRP Ceilings

The Glass Reinforced Ceilings that are modified as part of this work shall be repaired/installed IAW section 09 57 13 GFRP CEILINGS.

6.2.1.2 Aqua-Tough Ceilings

Existing ceilings that have Aqua-Tough gypsum board will be patched and repaired using like material and construction method as existing.

6.2.1.3 Painting

New masonry exhaust returns shall be painted in accordance with section

09 96 00 HIGH PERFORMANCE COATINGS.

6.2.2 Mechanical

The mechanical systems shall be installed in accordance with project requirements drawings, specification and equipment manufacturer recommendations.

6.2.3 Electrical

Equipment designated to have an electrical disconnect shall be provided with a factory installed and wired disconnect switch sized for the electrical characteristics of that piece of equipment. Equipment not designated to have an electrical disconnect switch shall have a field installed disconnect provided and installed by the electrical contractor.

6.2.4 Environmental

Contractor personnel will be required to show proof of most recent tuberculosis test prior to being allowed access to the facility to perform the work.

7. PERFORMANCE PERIOD/LIQUIDATED DAMAGES

Project schedule shall be submitted IAW section 01 32 16.00 10 PROJECT

SCHEDULE. Liquidated damages will be assessed as provided in the contract for failure to complete the work within the specified time.

8. PHASING REQUIREMENTS AND HOURS OF OPERATION/DAILY WORK HOURS

There will be phasing requirements for demo and installation of new work per the SOW/specifications. The project will require the Contractor to submit a preliminary schedule after award which should outline the entire project proposed timeline to complete the project including the design phase. In addition, during the construction phase, the contractor needs to include the proposed method of how they will “phase” each of the relocating the exhaust grille, ductwork, and HVAC Systems. Construction Efforts will require phasing due to only two rooms can be under construction at a time.

Consideration needs to be given to the operation of the facility and how the work will impact the Government. The facility will be occupied during this period. The Facility Manager and or his representative will provide escort personnel for personnel assigned to this project. Normal work hours are 0730-1700 Monday-Friday. Work days and hours other than indicated must be approved prior by Contracting Officer.

9. GOVERNMENT FURNISHED ITEMS

As built drawings for building 3260 upon contractor request.

10. NOTED CONTRACTOR REQUIREMENTS

10.1 Prior to Contract Award

10.1.1 Pre Bid Site Visit

Attend a Pre-Bid site visit to verify measurements, quantities and investigation of existing site conditions.

10.2 After Contract Award

10.2.1 Contractor Quality Control Reports

Contractor shall submit daily (or more often, as applicable) Contractor

Quality Control Report (CQC) IAW section 01 45 00.00 20 CONTRACTOR QUALITY

CONTROL.

10.2.2 Lay Down Area

Contractor shall coordinate with government representative to determine the location for the project lay down/storage area.

10.3 Debris and Cleanup

Upon completion of the workday, the contractor shall leave the work area in a clean manner. All project generated debris and waste shall be removed from the site and disposed of at an appropriate location off post.

10.4 Toilet Facilities

Are available for normal use. Contractor shall have a designated area for cleaning tools and debris disposal, the use of building restroom facilities are not to be used for cleaning of tools or dumping of hazardous material.

10.5 As Built Record Drawings

As Built CADD documents IAW section 01 35 13.20 00

SPECIAL PROJECT PROCEDURES-CAD

11. ATTACHMENTS

Attachment 1 - Division 01

Attachment 2 - Division 09

Attachment 3 - Division 23

Attachment 4 - Design drawings 1 through 24.

-- End of Section --