Questions_and_Answers_Trees.docx

DOCX document 13 KB Posted

Attached to
Tree Removal
Solicitation number
F2B3AQ9015A001
Issued by

View the file

Other files

File Type Posted
AMENDED-Statement_of_Work(SOW).docx DOCX document
(AMENDED)Combined_Synopsis-Tree_Removal.pdf PDF
Bid_Schedule.pdf PDF
67469.pdf PDF
Statement_of_Work.pdf PDF
Combined_Synopsis-Tree_Removal.pdf PDF
67470.pdf PDF
67458.pdf PDF
67471.pdf PDF
67459.pdf PDF
Wage_Determinations.pdf PDF
67468.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Question 1: Is this a new requirement or is there an incumbent vendor? If available, can you please send along the incumbent contract number?

Answer: Yes, this is a new requirement.

Question 2: Please explain the following section from the Statement of Work,“complete the “builder data inventory and assessment sheet” for newly installed assets, ensuring the bar code number is attached to the new equipment. Transfer bar codes from any removed equipment to the builder assessment ½ sheet form”. If we bring in aerial or chipper truck and chipper, are the above necessary?

Answer: This is a statement that is on all work orders. It does not pertain to tree removal

Question 3: Please explain from the Statement of work, “Provide three (3) copies of O & M manuals and warranty letter”. If we bring in aerial or chipper truck and chipper, are the above necessary?

Answer: This is a statement that is on all work orders. It does not pertain to tree removal

Question 4: Stump grinding is no longer necessary for Work Orders 67458, 67459, and 67468. Will there be an updated Statement of Work posted to FBO?

Answer: Yes, an amended Statement of Work was posted to FedBizOpps (FBO) on 13 February 2019

Question 5: How should we structure the bids that we submit?

Answer: Bids should follow the bid schedule that was posted to FedBizOpps. Each Work Order should be on a separate CLIN with a cost associated with that work order. A total cost for the entire project should also be included.