Dark Fiber QA.xlsx
XLSX spreadsheet 17 KB Posted
- Attached to
- Dark Fiber
- Solicitation number
- F2B0BB0164AW0100000
View the file
Other files
| File | Type | Posted |
|---|---|---|
| v2 Combined Synopsis Solicitation Dark Fiber.docx | DOCX document | |
| v1 Combined Synopsis Solicitation Dark Fiber.docx | DOCX document | |
| FY20_Dark Fiber SOW Mitre and Hanscom Revised 15 Jul 20.pdf | ||
| v0 Combined Synopsis Solicitation Dark Fiber.docx | DOCX document | |
| Dark Fiber Bid Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Q&A Dark Fiber F2B0BB0164AW0100000 3 Aug 2020 | ||
| Contractor Question | Government Answer | |
| 1 | The PoP is to begin 1 Sept 2020, which gives Crown Castle 13 business days to complete construction and turn up the services. The standard time for installation for fiber construction is 45 business days, can the Government either shorten the RFP due date or push out the PoP to allow for installation? | The dedicated fiber is installed and in service to date, this acquisition is for leasing the fiber from Crown Castle and to perform maintenance/emergency services as defined in the SOW. The RFP due date and PoP dates will not change. |
| 2 | Does Crown Castle have splicing that needs to be completed? | No splicing is required. |