About this file
This document is an Addendum (No. 1) issued by the Florida Department of Transportation (FDOT) for Project F2037, Financial Project Number 44997665201, concerning the design and construction of a 44' x 176' Equipment Canopy at the District 2 - Gainesville Operations facility. The addendum provides clarifications to prospective bidders, confirming that the project involves a metal building with an open bay design, a minimum 16' side height, and 20' eaves, and will connect to an existing shop. The document specifies that no new electrical or plumbing installations are required, though existing utilities conflicting with the project may need to be protected or replaced, and potential modifications to the existing concrete slab might be necessary to accommodate building support footers.
The addendum does not detail specific pricing terms or funding sources, but it indicates that the project will be completed in accordance with the 2023 Florida Building Code and all applicable regulations. Bidders are required to sign and return the addendum to acknowledge receipt, and the document suggests that interested contractors must be Certified General Contractors with experience in similar commercial projects. The bid documents will be available until June 3, 2025, with a public bid opening scheduled for June 4, 2025, at the Lake City District Office. The FDOT encourages minority business enterprise participation and provides opportunities for both certified and non-certified minority businesses to compete for the contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| F2037 Invitation to Bid.pdf | ||
| d2-fax-order-form.pdf | ||
| d2-fax-order-form.pdf | ||
| F2037 Invitation to Bid.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Transportation
RON DESANTIS
GOVERNOR
1109 S. Marion Avenue
Lake City, FL 32025-5874
JARED W. PERDUE, P.E.
SECRETARY
www.fdot.gov | www.nflroads.com
May 23, 2025
To: Prospective Bidders
Addendum No.: 1, F2037, FIN# 44997665201 Provide sufficient design, work force, equipment, safety, materials, permitting, and all incidentals necessary to design and build a 44’ X 176’ Equipment Canopy. All work will be in accordance with this scope, specifications, local building codes, and contract terms. It will be the Contractors responsibility to acquire and comply with all necessary regulations and guidelines that apply to the design and construction work required to complete the project. All work will be in accordance with the Department of Transportation’s Construction Plans, the 2023 Florida Building Code, and all applicable laws, rules, and codes shall be followed for this project.
In response to Bid Questions and Answers:
1. Question: Will this be a metal building, similar to the one shown in the image below?
Answer: Yes
2. Question: What is the height that you need for this structure?
Answer: As per the scope: Contactor shall design and construct 44’ X 176‘ Equipment Canopy with a minimum 16’ side height designed to connect to existing shop with 20’ eaves.
3. Question: Will the building be an enclosed structure or an open-bay design?
Answer: Open Bay
4. Question: Concerning the building's utilities and infrastructure:
Answer: As per the scope: No electrical installation required but you will be required to remove any electrical in the way of building the building.
Addendum 1, F2037
44997665201 www.fdot.gov | www.nflroads.com
5. Question: Will the project require basic plumbing and electrical work, including lighting, outlets, fans, and any necessary rough ins?
Answer: No new or additional plumbing and electrical will be required, however, any existing utilities that conflict with this project will need to be protected or replaced if necessary.
6. Question: Is the inclusion of a concrete slab within our scope of work a requirement for this project?
Answer: No, however, modifications to the slab may need to be made to accommodate any footers for the metal building supports.
7. Question: Would you happen to have the plans for the building it is butting up to?
Answer: Plans have been attached.
Please sign this addendum and return a signed copy to me to indicate receipt.
Company Name
Signature
Date
Thank you, Brittany Whiddon District Contracts Administrator Phone: 386-758-3798 Fax: 386-758-3791