F1S0AG2221A001 Ciena OTN RFP

1. Does the Government have sufficient power available in the form of rectified/battery backup ‐ 48VDC to support new core equipment (4X60A feeds) X2 at each network location?

EAFB ANSWER:

‐Core Node‐ Building 2600: Sufficient AC Power/ Rectifier/Battery back‐up (48 VDC) at this location. DC Rectifier and backup is part of the vendor supplied HW and installation. Vendor will utilize AC supplied power to feed vendor supplied DC rectifier and battery backup.

‐Core Node‐ Building 1440‐ CR125‐ Sufficient AC Power will be installed at time of equipment receipt. DC Rectifier and backup is part of the vendor supplied HW and installation. Vendor will utilize AC supplied power to feed vendor supplied DC rectifier and battery backup.

‐Core Node‐ Building 3812/ITN 3812‐ Sufficient AC Power will be installed at time of equipment receipt.

DC Rectifier and backup is part of the vendor supplied HW and installation. Vendor will utilize AC supplied power to feed vendor supplied DC rectifier and battery backup.

2. Does the Government have sufficient AC (120/240V) power available at each location to support new edge devices (up to 48 connections total required across all sites)? Power and racking is a significant consideration and a detailed site survey is required to determine specific power, racking, and potential allied support items at each location.

EAFB ANSWER:

There will be sufficient AC (120V) power available to support new edge devices at each building at time of equipment receipt. LOM will include needed racks, UPS, and fiber patch HW.

3. Will the Government provide partial payments for equipment delivery and installation labor?

EAFB ANSWER: You can bill after all equipment is shipped. Then bill again after the installation is fully complete. Both these will be on different CLINs.

4. Will a List of Materials (LOM) be forthcoming?

EAFB ANSWER:

Yes, will need to perform final review prior to release.

5. Sections (xiv) identifies DPAS as being Not Applicable. Will the government consider issuing a DPAS‐rated order to expedite product shipping, especially on ROADM components which are heavily constrained due to commercial demand?

EAFB ANSWER:

Currently in discussions with Air Force Authorizing Agent for DPAS Rating.