Ciena ONT Network Bandwidth Expansion Solution- F1S0AG2221A001
Q&A’s
1. Could you please provide a detailed building list and network equipment list requested at each building?
EAFB Response:
Edwards buildings 2600, 1440, and 3812 will be for the core nodes and edge equipment. List of equipment is being reviewed and will be released Friday, 16 Sep.
2. Please provide requested network topology and government fiber routes for that topology.
EAFB Response:
Final network topology will be provided to the contractor awarded the project. Existing base fiber exists to/from each core node location.
3. Will the government provide the contractor unescorted access to installation sites?
EAFB Response:
Contractors will have escorted access to the installation sites.
4. Will the government provide a DD-254 to pass down clearances to the contractor?
EAFB Response:
No. Contractor will be required to identify installation personnel and specific information for base access.
5. Will the government provide all inter site fiber?
EAFB Response:
Yes.
6. Is the “Sole Source Justification” considered the Scope of Work (SOW) for the project? The solicitation mentions an attached SOW, however The only additional attachment is the SSJ
EAFB Response:
No. The Scope of Work will be provided.