Black Canyon Archeological District Trail Statement of Work

Statement of Work

Design - Build

United States Fish and Wildlife Service Pahranagat National Wildlife Refuge – Alamo, NV

May 9, 2017

1.0 Background:

Surrounded by Nevada desert, the Pahranagat National Wildlife Refuge (PNWR) in Lincoln County, Nevada is a 5,380 acre ecological oasis of lakes, marshes, wet meadows and desert uplands. In 1963, the U.S. Fish and Wildlife Service (FWS) recognized the value of the Pahranagat Valley and designated 3,916 acres of lakes, marshes, meadows and desert uplands as Pahranagat NWR. Later land acquisitions expanded the refuge to its present size of 5,382 acres. The Refuge was established for the purpose of “…for use as an inviolate sanctuary, or for any other management purpose, for migratory birds…” (16 USC 715d).

Pahranagat NWR is located on the Pacific Flyway, a major north-south migratory route along the western coast of the United States. Designated by The Nature Conservancy as one of the nation's prime biological "hotspots", the Refuge is an essential stopover for hundreds of different species of waterfowl, raptors and songbirds. The refuge also provides habitat for fish and mammals including several endangered and threatened species. Many species also breed and overwinter here. Hunting and fishing are popular activities, and for those interested in experiencing this desert oasis at night, camping is available at the Upper Lake.

2.0 General Information:

2.1 Provide design and construction services for the Black Canyon Archeological District Trail project at Pahranagat NWR.

2.2 Bid Schedule will include Base Bid and Option Bid items. Option items may be awarded at any reasonable period within the Performance Period of the awarded contract and are subject to availability of project funds.

2.3 Period of Performance: The anticipated and desired construction start date is September 1, 2017, with a project completion date of November 30, 2017. The time required to secure all required permits could affect start and completion dates. The anticipated performance period for the design requirement of the contract will be 45 – 60 days from issuance of the Notice to Proceed. Pahranagat NWR will begin to turn water into the Black Canyon channel on or

Statement of WorkC:\Users\jeffrose\Desktop\Pahranagat Black Cyn\2017.05.02.SOW.BlackCanyonTrail.docx about September 30, 2017. Work items that would be affected by channel flows would need to be scheduled and completed as much as possible, so as to not have negative impacts on Refuge operations. The Refuge staff shall be advised of all anticipated deviations from the project schedule and will provide input to the C.O.R regarding the approval of any deviations to the schedule.

2.4 The resulting contract is to be Firm Fixed Price (FFP) or lump sum.

3.0 Scope:

Design and Construct install the Black Canyon Archeological District Trail and all associated project elements as described in this Statement of Work.

All work will comply with any applicable Architectural Barriers Act (ABA) standards and requirements, or any other applicable accessibility codes or requirements. The design will include an analysis and certification that any applicable accessibility requirements have been considered and provided for.

3.1 Trail: Design and construct an approximate 7400 foot trail. The location is shown on the

Project Map (Figure 1.). The trail location will be clearly marked in the field at the time of the pre – bid meeting at the site. The proposed trail width is 6’, but the designer will follow any pertinent accessibility requirements regarding trail width, cross – slope, longitudinal – slope and passing/resting pull outs requirements. The trail will require clearing and grubbing and final grading to establish a uniform surface free of any organic materials prior to surfacing. The trail surfacing will consist of a 6” (in place) compacted base material, with a 2” (in place) compacted top course. The final depths will be measured after satisfactory compaction efforts, with lifts not to exceed 2” at the proper moisture content. Provide compaction plan to include anticipated equipment and methods to the C.O.R for approval.

The base course will consist of crusher fines in the approximate ¼” (-) gradation. The top course will also be crusher fines material, but will be pinkish – red in color, so as to blend in with the natural canyon landscape. Representative materials can be inspected at the Rainbow Canyon Pit in Caliente, NV. The colored top course material has more fines than the base course material. USFWS will accept any aggregate material that meets the general properties of the described material as it is not a requirement that the materials come from the pit mentioned. The color requirement of the top course is important and subject to USFWS approval. Portions of the trail will likely require some sort of hard edging (rock, wood or other natural material) and it is anticipated that this requirement will be further defined at the conclusion of the pre – bid meeting on site. The goal is that whatever material is selected will appear natural and serve to protect the trail from unraveling in certain areas. As it is difficult to define this work requirement at this time, the bid schedule will contain a line item with an allowance of $7,500 for this work. After award of the contract, the final trail edging requirement will be further defined and approved. The bid schedule allowance will be adjusted at the time to reflect an agreed upon material, quantity and price. The Project Map shows four rest areas, a trailhead, two viewing areas and the Solitude Area. These areas will all have the same construction and surfacing requirements as the trail. It is anticipated that

Cyn\2017.05.02.SOW.BlackCanyonTrail.docx the rest areas and viewing areas will be tied to future interpretive displays which are not a part of this contract. The final locations may shift from what is shown on the Project Map.

The rest areas shall be approximately 6’ x 10’ and adjacent to the trail. The two viewing areas will be approximate 30’ diameter circular shapes. The trailhead is a gathering area and will be approximately 30’ x 40’ in size. The Solitude Area will be an approximate 16’ diameter circle. FWS may decide to add an additional 12’ diameter Prayer Circle adjacent to the larger circle. Since this has not been resolved, that work (the Prayer Circle) may be added via modification after contract award, if necessary.

3.2 Bridges: Design and Construct two bridges at the locations shown on the Project Map. The anticipated span length is approximately 25’, but the final length will be determined at the conclusion of the pre – bid meeting. The bridge decking material and handrails will be composite material, such as TREX®, or approved equal. Decking color samples shall be submitted and USFWS will approve material and color selection prior to ordering. There will be no discernable elevation difference from the finished trail surface and the bridge decking. Photos are attached in this Work Statement of the bridge at the nearby Pahranagat NWR visitor contact station. These photos are for reference and depict the character and preferred materials and railing system for the two trail bridges (although the trail bridges are on a smaller scale). Design drawings of the bridge shown are available as an attachment to the solicitation (or contact C.O.R. Jeff Rose).

3.3 Parking Areas: Two parking lots are shown on the Project Map. The northern most lot is for cars only. The lot will be sized for 6 cars and an additional 2 parking spots for disabled parking needs, for 8 total parking stalls. Adhere to all accessibility requirements, to include concrete surfacing for the disabled parking spots if that is a code requirement. The parking lot to the south will be designed to accommodate 2 RV’s or 2 buses (for a total of 2 parking spots in any combination). The surfacing will consist of 10” (compacted depth) of Type II crushed aggregate for the base course of the RV/Bus lot. The car lot will require 8” of this material. The surface course for both lots shall be three inches (compacted depth) of 1” (-) crushed driveway material. Representative materials can be inspected at the Rainbow Canyon Pit in Caliente, NV. USFWS will accept any aggregate material that meets the general properties of the described material as it is not a requirement that the materials come from the pit mentioned. Aggregate color is not a consideration for the parking lots. Provide concrete parking stop blocks and any signage required by code.

3.4 Boardwalk: The boardwalk will be an Option bid item and the approximate locations are shown on the Project Map in Figure 1. Boardwalks will be 6 foot in width, unless any governing accessibility requirements specify a wider dimension. Two potential sections of boardwalk are being considered and the total length of both sections is approximately 255 feet. The boardwalk decking material will be composite material, such as TREX®, or approved equal. There will be no discernable elevation difference from the finished trail surface and the boardwalk decking. Decking color samples shall be submitted and USFWS will approve material and color selection prior to ordering. No handrails are required for the boardwalk sections.

Cyn\2017.05.02.SOW.BlackCanyonTrail.docx

3.5 Permits: The contractor is responsible for obtaining all permits that are required for any work pertaining to this contract.

4.0 Tasks:

Task 1: Pre – Bid Meeting

This task is not a requirement and any bidders who choose to participate in this meeting at the project site will not be reimbursed for their expenses. This site visit will include meeting with the USFWS Design and Construction Branch Representative and the Refuge Manager to tour the site and discuss the project objectives and requirements.

Some work requirements may be further refined on this project tour. All meeting notes, questions and answers will be posted as an amendment to the solicitation prior to the bid date.

Task 2 – Engineering Design

This task includes preparation and submission of 65/95 and final construction documents, technical specifications, attendance of design review meetings, preparation of a tentative design schedule, incorporation of agency review comments, development of calculations, execution of accessibility checklists, and preparation of an estimated cost of construction. All drawing will meet USFWS CAD standards (available from C.O.R., Jeff Rose).

Engineering Design shall include all work elements defined under Scope.

2.1 Prepare and submit tentative design schedule.

2.2 Prepare and submit 65% construction documents (drawings and technical specifications).

2.3 Attend face-to-face design review meeting.

2.4 Incorporate agency review comments.

2.5 Prepare and submit 95% construction documents by developing the 65% construction documents in sub-task 2.2.

2.6 Execute and submit accessibility checklists.

2.7 Attend face-to-face design review meeting.

2.8 Incorporate agency review comments.

2.9 Prepare and submit final construction documents.

Cyn\2017.05.02.SOW.BlackCanyonTrail.docx

2.10 Prepare and submit construction schedule.

Task 3 – Construction

After receiving approval of Task 2, the contractor shall perform all construction requirements according to the approved design documents and requirements of this Statement of Work.

3.1 Following construction completion submit final as – built drawings in compliance with

USFWS CAD standards.

5.0 General Requirements:

5.1 Quality Assurance:

a. Implement a Quality Assurance/Quality Control (QA/QC) Plan to verify products and services are free of errors or omissions. Use of internal QA/QC plans and procedures is permitted; however, the plan shall be adapted to the specifics of this contract.

5.2 Submittal Reviews:

a. Provide electronic submittals indicating engineer of record and contractor approval.

Distribute the response via email to the Engineering POC for approval.

5.3 Communications:

a. Direct all contracting related inquiries in writing or electronically to the Contracting Officer. The Contracting Officer’s contact information will be listed in the solicitation.

Direct all technical-related inquiries in writing or electronically to the COR.

5.4 Diligence: Contractor shall perform all construction activities efficiently and with the requisite expertise, skill and competence to satisfy the requirements of the contract documents. Contractor shall at all times exercise complete and exclusive control over the means, methods, sequences and techniques of construction. Refer to FAR Clause 52.236-5 for additional information.

5.5 Supervision: Contractor shall provide a Project Manager or Project Superintendent on site at all times while work is underway. Manager or Superintendent shall have a good working knowledge of the project work. Refer to FAR Clause 52.236-6 for additional information.

5.6 USFWS Operations: USFWS operations have precedence over construction activities.

Contractor shall schedule and coordinate all construction and demolition activities so as not to unduly impact ongoing facility operations. Refer to FAR Clause 52.236-8 for additional information.

Cyn\2017.05.02.SOW.BlackCanyonTrail.docx

5.7 Security: Contractor shall effectively secure the worksite, staging areas and materials storage areas. The Government shall be held harmless from any liability resulting from the contractor’s negligence to provide effective security.

5.8 Construction Safety:

a. Contractor shall be ultimately responsible for health and safety on the worksite at all times. Refer to FAR Clause 52.236-13 for additional information.

b. Contractor shall ensure that all onsite activities, equipment and facilities constructed by the contractor, subcontractor or supplier conform fully to the safety standards in Section

7.0 of the SOW.

c. Contractor shall provide barricades and warning devices as necessary to safeguard the public, workers and Government personnel. Where project work affects public roads, contractor shall provide signage in accordance with the current edition of the Manual on Uniform Traffic Control Devices (MUTCD), as published by the U.S. Department of Transportation (USDOT) Federal Highway Administration (FHWA).

5.9 Site Cleanup: Contractor shall remove construction debris from the worksite daily, including debris within temporary facilities and storage areas. Before completing the work, contractor shall remove from the worksite any rubbish, tools, scaffolding, equipment and materials that are not the property of the Government. Upon completion of work, contractor shall leave the work area in a clean, neat and orderly condition. Refer to FAR Clause 52.236-12 for additional information.

5.10 Material, Equipment, Transportation, Handling and Storage:

a. Government-owned equipment will not be made available to the contractor for use within this contract. Government buildings and other facilities are not available for storage of the contractor’s materials, equipment and tools.

b. Contractor shall have a representative onsite to receive material deliveries. Contractor shall be responsible for all material deliveries, whether or not their representative is onsite at the time of delivery or not.

c. Contractor shall transport, handle and store materials and equipment in a secure manner and in accordance with the manufacturer’s written instructions.

d. Contractor shall promptly remove from the worksite any material(s) and equipment which are damaged or are otherwise unsuitable. Refer to FAR Clause 52.236-5 for additional information.

http://mutcd.fhwa.dot.gov/ http://mutcd.fhwa.dot.gov/

6.0 Deliverables:

6.1 Submit the following items in .pdf and/or .dwg format, where applicable.

Submittal Item Number of Copies

Field Visit Notes One (1) Electronic Copy (.pdf)

Tentative Design Schedule One (1) Electronic Copy (.pdf)

65% Construction Documents Two (2) Electronic Copies (.pdf / .dwg) Two (2) Full-size Hardcopy Sets;

One (1) Full-size, Reproducible Hardcopy

95% Construction Documents Two (2) Electronic Copies (.pdf / .dwg) Two (2) Full-size Hardcopy Sets;

One (1) Full-size, Reproducible Hardcopy

Accessibility Checklists One (1) Electronic Copy (.pdf)

Final Construction Documents Two (2) Electronic Copies (.pdf / .dwg) Two (2) Full-size Hardcopy Sets;

One (1) Full-size, Reproducible Hardcopy

Calculations One (1) Electronic Copy (.pdf)

Construction Schedule One (1) Electronic Copy (.pdf)

7.0 Codes and Standards:

Safety Standards: Contractor shall adhere to Occupational Safety and Health Administration

(OSHA) 29 CFR 1910 and 1926, as well as other applicable DOI, USFWS, State, or local regulations. In the event of a conflict, the most stringent code requirement shall apply.

8.0 Warranty of Construction:

8.1 Provide a warranty of construction. Warranty shall continue for a period of one-year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of one-year from the date the Government takes possession.

Cyn\2017.05.02.SOW.BlackCanyonTrail.docx

8.2 Restore any work damaged in fulfilling the terms and conditions of the contract.

Contractor’s warranty with respect to work repaired or replaced shall run for one-year from the date of repair or replacement.

9.0 Inspection and Acceptance:

9.1 Inspection and acceptance will be determined by the COR. Refer to Paragraph (a) of FAR

Clause 52.212-4 for additional information.

9.2 Provide copies of submittals with approvals from the engineer of record and contractor.

9.3 Receipt of QC inspection and testing reports from contractor showing contract compliance.

9.4 Comply with serving utility company and state/county electrical authorities.

10.0 Invoice and Payment:

10.1 Progress Payments: Monthly progress payments shall be invoiced and submitted in accordance with Clause 52.232-70. Invoices shall reflect the actual work performed at the time of submission. Prior to submitting invoices, they shall be sent to the COR for review and approval / disapproval.

10.2 Final Payment: Final payment shall be invoiced and submitted in accordance with Clause

52.232-70. Prior to submitting the final invoice, contractor shall have submitted all closeout submittals. In addition, contractor shall have been provided an approval by the COR stating all deficiencies have been corrected.

11.0 Place of Performance:

Pahranagat National Wildlife Refuge P.O. Box 510 Alamo, NV 89001

12.0 Government Availability:

12.1 Government is available Monday thru Friday from 7:00 AM to 5:00 PM (Pacific Daylight

Time), excluding federal holidays. Availability outside the dates / hours shall be coordinated with the Refuge Manager at least two business days in advance.

13.0 Points of Contact:

a. Engineering POC / COR:

Jeff Rose, P.E.

U.S. Fish and Wildlife Service Division of Engineering 911 NE 11th Avenue Portland, Oregon 97232-4181 jeff_rose@fws.gov

(503) 231-2287 (Desk)

b. Refuge POC:

Rob Vinson Refuge Manager U.S. Fish and Wildlife Service Pahranagat and Moapa National Wildlife Refuges P.O. Box 510 Alamo, NV 89001 james_vinson@fws.gov

(775) 725-3417 ext. 102 (Desk)

BID SCHEDULE:

ITEM UNIT QUANTITY PRICE

BASE BID

Design L.S. 1 Construction L.S. 1 Trail Edging Allowance (to be adjusted post award) L.S. 1 $7,500.00 Total

OPTION BID

Boardwalks L.S. 1

Figure 1 – Project Map

Black Canyon Project Area

Desired Bridge Concept – near Pahranagat NWR Visitor Contact Station

END

5.4 Diligence: Contractor shall perform all construction activities efficiently and with the requisite expertise, skill and competence to satisfy the requirements of the contract documents. Contractor shall at all times exercise complete and exclusi...
5.5 Supervision: Contractor shall provide a Project Manager or Project Superintendent on site at all times while work is underway. Manager or Superintendent shall have a good working knowledge of the project work. Refer to FAR Clause 52.236-6 for a...
5.6 USFWS Operations: USFWS operations have precedence over construction activities. Contractor shall schedule and coordinate all construction and demolition activities so as not to unduly impact ongoing facility operations. Refer to FAR Clause 52....
5.7 Security: Contractor shall effectively secure the worksite, staging areas and materials storage areas. The Government shall be held harmless from any liability resulting from the contractor’s negligence to provide effective security.
5.8 Construction Safety:
a. Contractor shall be ultimately responsible for health and safety on the worksite at all times. Refer to FAR Clause 52.236-13 for additional information.
b. Contractor shall ensure that all onsite activities, equipment and facilities constructed by the contractor, subcontractor or supplier conform fully to the safety standards in Section 7.0 of the SOW.
c. Contractor shall provide barricades and warning devices as necessary to safeguard the public, workers and Government personnel. Where project work affects public roads, contractor shall provide signage in accordance with the current edition of the...
5.9 Site Cleanup: Contractor shall remove construction debris from the worksite daily, including debris within temporary facilities and storage areas. Before completing the work, contractor shall remove from the worksite any rubbish, tools, scaffold...
5.10 Material, Equipment, Transportation, Handling and Storage:
a. Government-owned equipment will not be made available to the contractor for use within this contract. Government buildings and other facilities are not available for storage of the contractor’s materials, equipment and tools.
b. Contractor shall have a representative onsite to receive material deliveries. Contractor shall be responsible for all material deliveries, whether or not their representative is onsite at the time of delivery or not.
c. Contractor shall transport, handle and store materials and equipment in a secure manner and in accordance with the manufacturer’s written instructions.
d. Contractor shall promptly remove from the worksite any material(s) and equipment which are damaged or are otherwise unsuitable. Refer to FAR Clause 52.236-5 for additional information.