Attachment_H_-_Site_Visit_-_Agenda.pdf

PDF 54 KB Posted

Attached to
NCTC - EPDM ROOF AND CLERESTORY VENTILATION
Solicitation number
F17PS00727
Issued by

About this file

Attachment H - Site Visit - Agenda

View the file

Other files

File Type Posted
Attachment_J_-_Q&A_Set_1.pdf PDF
Attachment_I_-_Site_Visit_-__Attendee_List.pdf PDF
Sol_F17PS00727_Amd_000001.pdf PDF
FedConnect File —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

U.S. FISH & WILDLIFE SERVICE

National Conservation Training Center 698 Conservation Way

Shepherdstown, WV 25443

Date: 12 July 2017

Subject: Site Visit, Roof Replacement & Clerestory Ventilation Control, National

Conservation Training Center, Shepherdstown, WV

Reference: Solicitation F17PS00727

1. SIGN IN:

Print name, company, and sign clearly on the sign in sheet.

2. INTRODUCTIONS:

a) Contracting Officer:

Alicia N. Weber (Nikki) Phone: 304-876-7359 E-mail: alicia_weber@fws.gov

b) Project Manager and Contracting Officer’s Representative:

Paul Wolford

3. COMMUNICATIONS:

All communication shall be in writing (email is acceptable). All verbal questions during the site visit shall be followed with the question in writing by the contractor. All questions and answers will be disseminated by amendment through FBO.

Please email the Contracting Officer with any questions. Emails or direct calls to the COR or the design firm are unacceptable.

Amendment items shall include but not limited to the following:

a) Site visit meeting minutes.

b) Contractor’s written questions.

Remarks and explanations at this meeting do not qualify the terms of this solicitation if it is not addressed in the amendment. The only official changes to the existing solicitation documents will be issued by amendment. Please monitor FBO http://www.fedbizopps.gov and FedConnect for amendments. The information transmitted to FBO is through the FedConnect website, www.fedconnect.net. Notification of amendments will be provided on FBO, but the actual documents/attachments are only available on FedConnect.

mailto:alicia_weber@fws.gov http://www.fedbizopps.gov/ http://www.fedconnect.net/

4. SOLICITATION INFORMATION:

a) Small Business Requirements: This acquisition is 100% Small Business Set-Aside.

Offers received from firms that are not small business concerns shall be considered nonresponsive and will be rejected. Any award resulting from this solicitation will be made to a small business concern.

b) Magnitude: The magnitude of the project is between $100,000.00 and $250,000.00.

c) Bonds: A Bid Guarantee and payment protection will be required. The bid Guarantee shall be 20% of the bid price. The penal amount of the payment protection at the time of contract award shall be 100 percent of the original contract price, and shall be provided within 10 days after contract award.

d) Bids: Please review Attachment F, Important Notice to Offerors, for a checklist prior to submitting your bid. The solicitation closes on 24 July 2017 at 2:00 pm EST; at which time a public opening of the bids will take place. Instructions for delivering the bids are provided in the solicitation. You must ensure that the bid is on site and received by the Government prior to the bid opening. Bids may be mailed, sent via courier (UPS, Federal Express, etc.), or hand delivered. If you wish to hand deliver your bid or wish to attend the bid opening, please contact the Contracting Officer

e) Award: This acquisition will result in a single fixed price construction contract. Award shall be made to the responsible bidder whose bid, conforming to the invitation, will be most advantageous to the Government, considering only price and the price-related factors included in the invitation.

5. ESTIMATED SCHEDULE:

The schedule for this project is as follows:

Solicitation Close/Bid Opening 24 July 2017 at 2:00 pm EST Contract Award 24 August 2017 (estimate)

Notice to Proceed 10 Calendar Days after Award Completion of Construction 150 Calendar Days after Notice to Proceed

6. CONSTRUCTION OVERVIEW BY PROJECT MANAGER:

a) Tour Sequence:

Physical Training Building Instructional East attic Instructional West attic

7. END OF SITE VISIT