QA_-_F17PS00266_-_Relocate_Fish_Passage_Bridge_at_Red_Rock_Lakes_NWR.pdf

PDF 17 KB Posted

Attached to
RELOCATE FISH PASSAGE BRIDGE AT RED ROCK LAKES NAT
Solicitation number
F17PS00266
Issued by

About this file

Questions & Answers - F17PS00266

View the file

Other files

File Type Posted
Sol_F17PS00266_Amd_000001.pdf PDF
16-008_Combined_Drawings.pdf PDF
16-008_Geotech_Report.pdf PDF
16-008_Submittals.pdf PDF
16-008_Drawings.pdf PDF
Sol_F17PS00266.pdf PDF
F17PS00266-__Instruction_to_Offerors.pdf PDF
16-008_SOW_Rev_2.pdf PDF
Wage_Determination_-_MT170080_-_6_Jan_2017.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RELOCATE FISH PASSAGE BRIDGE

RED ROCK LAKES NATIONAL WILDLIFE REFUGE

F17PS00266

PRE-PROPOSAL QUESTIONS & ANSWERS

1. QUESTION: Does the contractor have to attain a stream alteration permit or will they provide it?

ANSWER: Permit is already attained. Stream has already been restored by another party.

Bridge placement without creek disturbance is the goal now.

2. QUESTION: Does the contractor have to provide engineering?

ANSWER: No, engineering is complete.

3. QUESTION: Will the contractor be allowed to create a de-watering pond?

ANSWER: No, not in the creek. It was restored in October 2016. Old photos no longer apply.

4. QUESTION: Will there be access to both sides?

ANSWER: Yes.

5. QUESTION: Any special approvals for pit materials?

ANSWER: No special approvals are required. The rock fill must meet the requirements of Statement of Work section 2.6.

6. QUESTION: The contractor would like to use option 2 on the soils report. Is that OK?

ANSWER: Yes.

7. QUESTION: What does the bridge weigh?

ANSWER: The bridge will be in 2 sections weighing approximately 12 tons each. The concrete sill weighs approximately 3 tons each.

8. QUESTION: What is the current state of the bridge? Are there pictures available?

ANSWER: Yes, photos are available. 25 MB in 27 photos: Red Rock Lakes Bridge Relocation

If the above hyperlink does not work, try coping and pasting the following into the browser:

https://drive.google.com/drive/folders/0B2z17o8jxNhDeXg5TUktV3pqYVU?usp=sharing_eil&t s=58a4c73e https://drive.google.com/drive/folders/0B2z17o8jxNhDeXg5TUktV3pqYVU?usp=sharing_eil&ts=58a4c73e

9. QUESTION: Can the contractor proceed mid-summer JULY/AUG 2017 when the stream level has dropped?

ANSWER: This is a spring creek so same 22 CFS year-round. No high flows. Project must be completed before July 15, 2017 when this road must be usable as a detour route for Federal Highways project on nearby Elk Lake Road.

10. QUESTION: Are there any re-seeding requirements?

ANSWER: No.

11. QUESTION: Are there additional drawings depicting the approaches and approach railing?

ANSWER: All available drawings have been posted.

12. QUESTION: Is the bridge currently at the project site?

ANSWER: YES

File details come from the government source that posted it. Updated .