KENAI NWR Contact Station

Building Leveling and Helical Piers

Work Statement 29 January 2015

Statement of Owners Objectives: Construction Services

Kenai National Wildlife Refuge

Visitor Contact Station Foundation Repair

Revision: January 30, 2014

1.0 SCOPE OF WORK

1.1 Background:

The Kenai National Wildlife Refuge Contact Station located at the Russian River Ferry approximately 35.5 miles East of Soldotna, AK on the Sterling Hwy. The contact station is small a log structure approximately 12’x16’ (Size to be verified by contractor) on 3, 16” steel

I-beams that are welded to 6, 6” steel piers of unknown depth. The Piers are welded directly to the I-beams. There is also an attached deck that is supported by screw-jacks to adjust the level of the deck. Frost heaving has driven several of the piers up causing the floor to be canted at an unsafe degree and render the building un-useable. The intent of this statement of objectives is to bring the building back to serviceable condition by replacing the existing steel pipe piers with drilled helical piers.

1.2 Base Proposal:

DESIGN

Provide a stamped engineered helical pier design that will support the structure in its current location. The design should accomplish the following:

1. Perform a geotechnical investigation as necessary to determine underlying soil conditions

2. Provide a pier sizing diagram from a licensed engineer that will:

a. Prevent building disruption of the building from the existing steel piers

b. Adequately support the structure

c. Provide for future adjustments to level the structure and accommodate future movement of the sub-base

3. Provide the most cost effective solution to the U.S. Fish and Wildlife Service to level the structure. .

CONSTRUCTION

1. Upon design approval by the Service, and subsequent notice to proceed (NTP) provide full construction services outlined in the design provided as the base proposal. Work will include, but is not limited to

a. Remove the structure as necessary to facilitate pier installation

b. Remove existing piers (if required by design)

c. Install helical piers

d. Replace the structure

e. Site Clean-up

1.3 PERIOD OF PERFORMANCE

See Section F

2.0 GENERAL REQUIREMENTS

2.1 LOCATION OF WORK

2.1.1 Administrative Field Station: U.S. Fish and Wildlife Service (USFWS), Kenai NWR Contact Station

Kenai National Wildlife Refuge

1 Skihill Road, Soldotna, AK

2.1.2 Physical Project Location: 35.5 Miles East of Soldotna on the Sterling Hwy.

2.2 INQUIRIES

2.2.1 Contracting Officer: Anita Baker, 907-786-3415

Division of Contracting and General Services

U.S. Fish and Wildlife Service

1011 E Tudor Rd

Anchorage, AK 99503 anita_baker@fws.gov

2.3 SITE AVAILIBILITY

2.3.1 The work site is accessible from existing roads.

2.3.2 Work Hours: Monday through Friday, 7:00 a.m. to 5:00 p.m. except federal holidays, unless approved otherwise.

2.3.3 The bunkhouse is available to the contractor for lodging

2.3.4 Work limits are a staging area (approved by the local USFWS staff) and within 30 feet of the improvements.

2.2 GOVERNMENT FURNISHED EQUIPMENT, MATERIALS, INFORMATION

2.3.1 USFWS will provide the General Engineering Requirements specification.

2.3.2 Photos

2.3.3 USFWS Kenai NWR Jim’s Landing Improvements, Kenai Peninsula Borough, Alaska Drawings, dated 04/94, 23 pages.

2.3.4 USFWS Jim’s Landing Improvements Visitor Contact Station, dated 10/95, (Marked for demolition), 3 pages.

2.4 INSPECTION AND ACCEPTANCE

2.4.1 Inspection: The Work is subject to observation and/or inspection by the USFWS and other authorities having jurisdiction.

2.4.2 Acceptance: Acceptance of the work is contingent on compliance with the requirements set forth in the specifications, drawings, and other documents awarded with (or referenced by) the contract for this project.

2.4.3 Show the overhead percentage/multiplier. Only if request by the Contracting Officer, provide an itemization for the overhead rate calculation.

2.4.4 Show the percent profit.

2.5 DELIVERABLES AND MEETING

2.5.1 See General Engineering Requirements for submission milestone descriptions and requirements for the 100%, and Construction Documents.

2.5.2 Deliverables & submittals shall be electronic; typically as Abode, Word, Excel. Final drawings Adobe and AutoCAD with CTB plot file.

2.5.3 Routine submittals shall be delivered to the USFWS at Anchorage, AK via FEDEX or electronic submission via email to the Contracting Officer and the Contracting

Officer’s Representative. Resolve routine review comments with the Contracting

Officer’s Representative by e-mail, fax, and telephone.

2.5.4 The final design documents shall meet the approval of the FWS and governing regulatory authorities.

2.5.5 Meetings

2.5.5.1 Pre-Design

2.5.5.2 100% Design Review

2.5.5.3 Preconstruction Conference

2.5.5.4 Final Walk through

2.6 SCHEDULE OF ACTIVITIES

2.6.1 A preliminary Schedule of Activities is shown below. The dates shown are “no later than” and included float time. Within the formal contract time (term), the schedule may be revised as agreed to meet the project needs without incurring delay or acceleration. The intent is to accomplish the project in the shortest time frame feasible.

2.6.2 Project Schedule (or as otherwise agreed with awarded fee proposal.)

Target Date Event (Office Entry)

TBD Finalize negotiation and contract award.

10 Days Design and product submittals due

30 Days Begin on-site construction

90 Days End Construction