f Sanctuary Timeline Milestones.pdf

PDF 140 KB Posted

Attached to
RFP20240906 Debt and Equity Sanctuary on Potomac
Solicitation number
RFP20240906
Issued by
Alamosa County, Colorado

About this file

This document is a detailed project timeline for the Sanctuary on Potomac Permanent Supportive Housing (PSH) development, prepared by the Aurora Housing Authority (AHA) on September 24th, 2024. The timeline outlines critical development and financing milestones, including submitting a Low-Income Housing Tax Credit (LIHTC) application to the Colorado Housing Finance Authority (CHFA), soliciting investor/lender proposals, and key project stages from initial application through construction completion and occupancy. The project timeline spans from September 2024 to July 2027, with significant milestones including posting final Request for Proposals (RFPs) for investors/lenders on October 15, 2024, selecting LIHTC investors/lenders by November 18, 2024, and starting construction on May 1, 2025.

The project's financial structure involves multiple phases of financing, including LIHTC applications, construction loan closing, and conversion to a permanent loan. Construction is projected to take approximately 15 months, with the project anticipated to reach 100% qualified occupancy by March 1, 2027, and complete 90 days of stabilized occupancy by June 1, 2027. The timeline indicates a comprehensive approach to financing and development, involving careful coordination of construction milestones, investor selections, and regulatory compliance, with the ultimate goal of creating a permanent supportive housing development that meets community housing needs.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sanctuary on Potomac PSH Projected development and financing milestones are as follows: PREPARED September 24th 2024

Submit application to CHFA for LIHTC

Award of LIHTC initial determination letter

Posting of final RFPs for investor/lenders

BFOs due from investors/lenders

Selection of LIHTC investor/lenders

Completion of CDs

GC GMP pricing finalized

Close LLLP

Close Construction Loan

Start Construction (NTP)

Construction Completion-TCO (15 mo.)

Placed in Service

100% Qualified Occupancy

90 days of Stabilized Occupancy

Conversion to Permanent Loan

Completed

Completed

Sept 24, 2024 Oct 15, 2024 Nov 18, 2024 Dec 6, 2024 March 1, 2025 May 1, 2025 May 1, 2025 May 1, 2025 Sept 1, 2026 Sept 1, 2026 March 1, 2027 June 1, 2027 July 1, 2027