Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 21-1012 PROJECT TITLE REPAIR SOUTH DEER FENCE SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALLAUGHLIN DIV 01 SPECS REFERENCESTATEMENT OF WORK REFERENCEENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFBNUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Pre-Construction Submittals
1Construction Site Plan, Laydown area12.13.2.11 DigitalNLT 30 Days after NTP 1
2Work Clearance Request, AF Form 1032.23.2.11 Digital30 Days prior to construction start
3Project Schedule Form6.1.19.71 DigitalNLT 7 Days after NTP 1
4Contract Progress Report9.71 DigitalNLT 7 Days after NTP 1
5Contractor Health and Safety Plan3.2.21 DigitalNLT 30 Days after NTP 1
6Worker/Area Protection Plan3.4.2.21 DigitalNLT 30 Days after NTP 1
7QC Plan4.2.41 DigitalNLT 30 Days after NTP 1
8QC Manager Qualifications4.2.31 DigitalNLT 30 Days after NTP 1
9Safety Data Sheets3.1.21 DigitalNLT 30 Days after NTP 1
10FOD Plan9.111 DigitalNLT 14 Days after NTP 1
11Hazardous Waste Disposal Documentation3.2.22.2, 3.1, 5.21 DigitalNLT 30 Days after NTP 1
12Solid Waste Management Plan2.2.2, 5.11 DigitalNLT 30 Days after NTP 1
13Records of Existing Conditions7.1.11 DigitalNLT 30 Days after NTP 1
14Recycling Disposal Report5.11 DigitalAt the Final Inspection
15Shop Level Drawings10.4.42.24 Paper copies, 1 DigitalNLT 30 Days after NTP 1
16Product Data10.4.52.24 Paper copies, 1 DigitalNLT 30 Days after NTP 1
16aChainlink2.21 DigitalNLT 30 Days after NTP 1
16bTies2.21 DigitalNLT 30 Days after NTP 1
16cGate Latch2.21 DigitalNLT 30 Days after NTP 1
16dFence Posts2.21 DigitalNLT 30 Days after NTP 1
16eConcrete2.21 DigitalNLT 30 Days after NTP 1
16fReinforcement Bar2.21 DigitalNLT 30 Days after NTP 1
16gMetal Tubing2.21 DigitalNLT 30 Days after NTP 1
17OPSEC Training2.41 DigitalNLT 14 Days after NTP 1
18Entry Access List (EAL)1.8.21 Digital2 Weeks prior to base access
19Phase Plan (if requested in SOO/SOW)11 DigitalNLT 30 Days after NTP 1
20FAA Form 7460-019.31 DigitalNLT 7 Days after NTP 1
Construction Submittals
21Progress Report6.1.213.21 DigitalWeekly
22Meeting Minutes6.2.19.71 DigitalNLT 3 Days after meeting
Materials
23Samples10.4.613.3.2
23aChainlink13.3.21 SampleBefore installation
23bTies13.3.21 SampleBefore installation
23cGate Latch13.3.21 SampleBefore installation
23dFence Posts13.3.21 SampleBefore installation
23eMetal Tubing13.3.21 SampleBefore installation
24Test Reports10.4.93.1.2, 3.4.2.1, Appendix E1 Digital
24aConcreteN/AN/A
25Certifications10.4.103.1.2, 3.41 DigitalElectrician License
26Manufacturer's Field Reports10.4.121 DigitalAs Needed
Close-Out
27Completion Inspection (QC Manager Punchlist)13.41 DigitalBy Pre-Final Inspection
28O&M Data (Manuals)10.41 Paper copy, 1 DigitalNLT 2 weeks after Final Inspection
29Draft DD Form 135413.314.1.11 DigitalNLT 3 weeks Prior to Pre-Final Inspection
30Final DD Form 135413.314.2.11 Paper copy, 1 DigitalAt the Final Inspection
31As Built Drawings/CAD Files10.4.141 Paper copy, 1 DigitalNLT 2 weeks after Final Inspection
32Warranty13.21 Paper copy, 1 DigitalNLT 2 weeks after Final Inspection
Schedule of Submittals Template, Feb 05 (SAF/AQCP)

Task Order # FA3099-16-D-0002-0002 SOW Atch 2

&"Times New Roman,Regular"&12Page &P of &N

File details come from the government source that posted it. Updated .