Exhibit H - Special Provisions Summary
This document comprises the Special Provisions for the Abernathy Greenway Southside Improvement Project administered by the City of Sandy Springs in coordination with AtkinsRealis, the Georgia Department of Transportation, the City of Atlanta Department of Watershed Management, Fulton County Department of Public Works, and Georgia EPD. The Special Provisions establish mandatory compliance requirements across 24 specification sections addressing traffic control, unit pricing, product substitutions, project management, construction schedules, photography, submittal procedures, shop drawings, quality control, and erosion/pollution control. The traffic control specification (Section 150-0000) requires the contractor to submit a phased traffic control plan to the city for approval prior to construction commencement, maintain two-way traffic throughout the project, provide pedestrian safety measures 24 hours daily seven days weekly, maintain existing traffic signals and detection systems with replacements within 24 hours, and ensure all work conforms to the Manual on Uniform Traffic Control Devices (MUTCD) current edition. All traffic control costs, including signing, pavement markings, barricades, and flagging, are included in the lump sum bid. The contractor must maintain coordination with utility companies operating within project limits and comply with applicable state and local traffic safety requirements.
Contractors must submit construction schedules using Critical Path Method (CPM) format within 10 days of the Notice to Proceed, including Overall Project Schedules (OPS), Near Term Schedules (NTS), and Schedule of Values (SOV), with updates submitted monthly alongside progress payment requests. Product substitutions require submission using the designated form with supporting documentation including performance data, manufacturer information, cost analysis, and evidence of similar installations, subject to Engineer's written approval prior to installation. All submittals, including shop drawings and product data, must be prepared to scale showing field-verified dimensions and coordination requirements, submitted in PDF electronic format via e-Builder or approved project management software, and marked with the contractor's approval stamp prior to design team review. Quality control services must be provided by prequalified independent testing agencies complying with American Council of Independent Laboratories standards, with certified written reports submitted monthly to the owner's representative, contractor, and owner. Material certifications must warrant that all products are free of asbestos, PCBs, and other hazardous materials, with written certification required from manufacturers for any suspected materials. Construction photographs, including daily progress photos and monthly aerial imagery, must be submitted electronically in .jpg format with date and time markings and uploaded with monthly payment applications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB_27_004_Abernathy Greenway Southside Impro.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A b e r n a t h y G r e e n w a y S o u t h s i d e P a g e | 17
EXHIBIT H-
SPECIAL PROVISIONS
TABLE OF CONTENTS
As part of this contract, the Contractor is required to comply with AtkinsRéalis construction documents, and Special Provisions, City of Sandy Springs codes, Georgia Department of Transportation Standard Specifications, Construction of Transportation Systems (current edition), Georgia EPD grant requirements, Fulton County, Department of Public Works Specifications and Standards for Sanitary Sewer Improvements, and the City of Atlanta Department of Watershed Management Specifications ,Water Distribution Systems Details and Specifications. The Special Provisions associated with this project include:
Section Description 105-0000 Traffic Control 01-2200 Unit Prices 01-2500 Product Substitutions 01-2500.01 Product Substitutions Request Form 01-3100 Project Management and Coordination 01-3216 Construction Schedules 01-3233 Construction Photographs 01-3300 Submittal Procedures 01-3310 Shop Drawings, Product Data and Samples 01-4500 Quality Control Services 01-5100 Erosion Control and Pollution Control 01-7123 Construction Staking 01-7400 Cleaning 01-7839 Closeout Submittals 02-2200 Geotechnical Information 02-4113 Selective Site Demolition 31-2301 Excavating, Backfilling and Compacting for Structures 31-2319 Dewatering 31-1313 Concrete Paving 32-1373 Concrete Paving Joints Sealants 32-9000 Lawns and Grasses 32-9113 Mulching 32-9300 Trees Plants and Ground Covers 33-0000 Utilities 40-0000 Masonry 705–0000 Two-Year Maintenance Services 900-0000 Paver Installation 992-0000 Stone Masonry
P a g e | 18
SPECIAL PROVISION
Section 150-0000– Traffic Control
Add the following to GDOT Specification, Section 150.01 and Section 150.06:
150.01 General Description:
1. This section as supplemented by the Plans, Specifications, and Manual on Uniform Traffic Control Devices (MUTCD) shall be considered the Temporary Traffic Control (TTC) Plan in accordance with Work Zone Safety and Mobility Policy and a Traffic Control Plan submitted by the contractor.
Activities shall consist of furnishing, installing, maintaining, and removing necessary traffic signs, pedestrian signs, barricades, lights, signals, cones, pavement markings and other traffic control devices and include flagging and other means for guidance and protection of vehicular and pedestrian traffic through the Work Zone. This Work shall include both maintaining existing devices and installing additional devices as necessary in construction work zones.
2. When any provisions of this Specification or the Plans do not meet the minimum requirements of the MUTCD, the MUTCD shall control. The current Edition of the MUTCD shall be in effect for the duration of the project.
3. All traffic control devices used during the construction of the project shall meet the standards utilized in the MUTCD, and shall comply with the requirements of these Specifications, Georgia Construction Standards and Details, Project Plans, Design Manuals, and Special Provisions.
4. The Contractor’s attention is directed to articles 104.05 and 107.07 of the GDOT Standard Specifications and the special provisions for traffic control and sequence of operations regarding maintenance of traffic during construction, for additional traffic control notes see GDOT std. drawing no. 9100.
5. The price bid for Traffic Control is Lump Sum - shall include, but is not limited to, construction, maintenance, and removal of temporary signing and pavement markings, barricades, channelizing devices, etc. required for maintenance of traffic during construction. All temporary signing and pavement marking shall be in accordance with the "Manual on Uniform Traffic Control Devices", current edition and/or as directed by the representative of the city.
6. All work must conform to applicable state and local requirements for traffic control and safety. Prior to construction the contractor shall submit a traffic control plan to the owner for review and approval. Such a plan at a minimum shall address safety and traffic management for residents, pedestrians, bicyclists and motorists, maintenance of 2-way traffic, advanced notice of construction activities affecting traffic, construction staging, proposed detours, signing and marking, warning devices, the use of flaggers and similar traffic control measures.
7. Utilities included in the contract are bound by Special Provision 150 and shall meet its requirements. For utilities not included in the contract but working within the project limits, they shall, at a minimum, follow the MUTCD. Moreover, in accordance with the Utility Accommodation Policy and Standards Manual dated 2016, the Engineer reserves the right to require additional certified flaggers, signs, warning lights, channelization devices, and other safety devices as may be necessary to properly protect, warn, and safeguard the traveling public. In addition, the Department reserves the right to place time restrictions or moratoriums on all utility work covered under a permit when, in the opinion of the city, the continuance of the Work would seriously hinder traffic flow, be needlessly disruptive, or would unnecessarily inconvenience the traveling public. In case of emergencies, Utilities shall be provided access in accordance with Utility Accommodation Policy and Standard Manual.
The Worksite Traffic Control Supervisor (WTCS) shall have a copy of Part VI of the MUTCD and the Contract on the job site. Copies of the current MUTCD may be obtained from the FHWA web page at http://mutcd.fhwa.dot.gov.
P a g e | 19
150.06 Special Conditions
A. Traffic Control Plan:
All work must conform to applicable state and local requirements for traffic control and safety. Prior to construction, the Contractor shall submit their Phased Traffic Control Plan to complete all work to the city for their review and approval. Such Plan at a minimum shall address safety and traffic management for residents, pedestrians, bicyclist and motorist, maintenance of 2 -way traffic, advance notice of construction activities affecting traffic, construction staging, proposed detours, signing and marking, warning devices, the use of flaggers and similar traffic control devices. The proposed Traffic Control Plan shall include the Contractors’ proposed schedule for the completion of all work. The Contractor attention is directed to Articles 104.5 and 107.7 of the GDOT Standard Specifications.
B. Lane closures:
No proposed Lane Closures are anticipated. Should the Contractor propose Lane Closers construct the project for any of the intersecting and perpendicular streets within or adjacent to the project limits, the Contractor shall be submitted to the city for approval at least 7 days prior to implementation of the temporary lane closures. These temporary lane closures shall be furnished, installed and maintained in accordance with Georgia Standard Specifications, applicable City of Sandy Springs Standards and the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD). Cost for furnishing, installing and maintaining the lane closures shall be included in the price bid for Traffic Control.
C. Crosswalk and Pedestrian Circulation:
The Contractor shall always maintain pedestrian access around the perimeter of the construction area.
For all crosswalk locations, the Contractor shall provide a pedestrian safety plan. The pedestrian safety plan shall maintain safe crossing for 24 hours a day and seven days a week. While completing the project, the contractor cannot interfere with school vehicle and pedestrian traffic crossings.
D. Maintaining Traffic Signals:
The contractor shall be responsible for the maintenance of traffic signals and Advanced Traffic Management system (ATMs) devices from the time that the system is modified until final acceptance.
The contractor is responsible for damages to all devices that he or their subcontractors cause, in accordance with Section 107 and other specifications.
The Contractor shall always maintain detection for traffic signals. This applies to existing traffic signals.
This may require temporary detection either by loops or video detection. Failure to maintain the detection of the traffic signals will result in assessment of non-refundable deductions as noted in Section 150.7.01. All Traffic Loops that shall be replaced in 24 hours
The Contractor shall always maintain interconnect to the traffic signals. This may require temporary devices and other items. Failure to maintain interconnect to the traffic signals will result in assessment of non-refundable deductions as noted in Section 150.7.01.
E. Warning Devices:
Warning devices shall be placed prior to commencement of any road improvement work and shall remain in place until the conclusion of all construction.
END OF SECTION 150-0000
Traffic Control 150-0000-3
P a g e | 20
SECTION 01 2200
UNIT PRICES
PART 1 GENERAL
1.01 SCOPE
A. Section Includes:
1. Unit price work.
2. List of unit prices required.
3. Procedures for unit price work.
B. Related Sections
1. Applications for payment: As outlined in General Conditions and Bid Schedule
2. Procedures for modifications to the Contract: As outlined in General Conditions.
3. Procedures for utilization of testing and inspection: As outlined in Specifications.
4. Contract closeout procedures: As outlined in Specifications.
1.02 SUBMITTALS
Supporting Data: With applications for payment covering unit price work submit substantiated measurement of quantity installed or executed.
A. Unit Prices
1. Indicate unit price for each item on Bid Form.
2. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
SECTION 01 2200 -1
P a g e | 21
3. Quantities:
a. Including in the contract base bid an amount equal to the unit price times the estimated quantities.
b. Contractors are required to determine and verify all quantities prior to their bid.
c. Unit Prices are for future additions and deductions that may be requested by the city. The Contractor Lump-Sum bid is a total of all Unit Prices.
4. Accepted unit prices will be included in the agreement and may be used for future project additions and deductions to the contract.
B. Procedures for Modifications to the Contract: Procedures for submitting and handling modifications due to changes are specified elsewhere.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
END OF SECTION 01 2200
SECTION 01 2200 -2
P a g e | 22
SECTION 01 2500
PRODUCT SUBSTITUTIONS
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this section
1.02 SUMMARY
A. This section specifies administrative and procedural requirements for handling requests for substitution, made after award of the Contract.
B. Standards: Refer to Section “Codes and Standards” for applicability of industry standards to products specified.
1.03 DEFINITIONS
A. Definitions used in this Article are not intended to change or modify the meaning of other terms used in the Contract Documents.
B. Substitutions: Requests for changes in products, materials, equipment, and methods of construction required by Contract Documents proposed by the Contractor after award of the Contract are considered requests for “substitutions.” The following are not considered substitutions:
1. Revisions to Contract Documents requested by the Owner or Designer.
2. Specified options of products and construction methods included in Contract
Documents.
3. The Contractor’s determination of and compliance with governing regulations and order issued by governing authorities.
1.04 MATERIAL
A. Use materials and equipment that are new and of quality suited to use intended, suitable for function intended, and plainly labeled and delivered to Project site in original unopened containers when nature of materials is suitable for containers.
B. The Engineer has endeavored to specify materials, products and assemblies which are totally free of asbestos, polychlorinated biphenyl (PCB) or other similar materials believed to endanger the health and safety of construction workers and future building occupants.
However, manufacturers' information and other data normally furnished to the Engineer by producers of building material products and systems do not always contain accurate, complete, or appropriate information for the Engineer to properly evaluate each product.
01 2500-1
P a g e | 23
C. It shall therefore be a requirement of these Contract Documents that neither the Contractor, nor their material suppliers, nor their Subcontractors install or otherwise incorporate any materials containing asbestos, PCB or other hazardous materials within the boundaries of the Project. No soil found on site, or transported to the site from remote locations, which is contaminated with material containing asbestos, PCB, Radon, gasoline, fuel oil, diesel fuel or other similar fossil fuels shall be used to fill backfill or landscape topsoil.
D. The Contractor shall require that each of their Subcontractors and material suppliers warrants to City and Engineer, that all materials, products, and assemblies incorporated, or submitted for incorporation into this Project, are totally free of asbestos, PCB, or other such hazardous materials. This warranty shall include all materials, products and assemblies specified and otherwise required in the Contract Documents. This warranty shall also include all materials, components and accessories not specifically enumerated or detailed in these Contract Documents, but which are required by performance specifications or recommended by manufacturers for complete installation of materials, products, and assemblies. If the Contractor or their Subcontractors or material suppliers have knowledge that, or believe that an item, component, material or accessory within a product or assembly may contain asbestos, PCB or other such hazardous material, it is the Contractor's sole responsibility to secure a written certification from the manufacturer of any suspected material stating this material is totally free of asbestos, PCB or other hazardous materials.
E. A copy of the Products that are specified by reference standards or in descriptive manner without a manufacturer's name, model number or trade name, shall be selected by the Contractor, shall comply with all specified requirements, and shall not contain asbestos, PCB or other hazardous materials in any form. The Contractor shall be responsible for determining that materials requested for substitution are totally free of asbestos, PCB or other similar materials known to endanger the health and safety of construction workers and future building occupants written certification shall be submitted to the Owner and Engineer.
1.05 WORKMANSHIP
A. Follow the manufacturer’s instructions. When instructions conflict with Contract
Documents, make request for clarification before proceeding. Maintain a copy of manufacturer's instructions at Project site.
B. Comply with industry standards except when specified tolerances indicate more rigid standards or more precise workmanship. Perform work by qualified people to produce workmanship of specified quality.
C. Join materials to uniform, accurate fit to meet with straight lines free of smears and overlaps. Install exposed materials appropriately level, plumb, and at accurate right angles or flush with adjoining materials. Attach materials with sufficient strength, number, and spacing of attachments that will not fail until materials joined are broken or permanently deformed.
1.06 CONTRACTOR'S OPTIONS
A. For products specified only by reference standard or description, provide any product meeting specifications.
B. For products specified by naming one or more products or manufacturers, request for substitution for any product not named is required
01 2500-2
P a g e | 24
C. For products specified by naming one or more products or manufacturers with no substitutions permitted, provide one of named products.
D. Where items of methods, materials, systems, and equipment are specified as products of certain named manufacturers, products of those named manufacturers, or approved equivalents, are acceptable. Certain specified construction and equipment details may not be regularly included as part of the named manufacturer's standard catalog equipment but shall be provided by the manufacturer as required for the proper functioning of the equipment. The Contractor shall assume full responsibility to assure that the manufacturer provides materials and equipment conforming to indicated and specified requirements. Reasonable minor variations in equipment due to manufacturing methods are expected and will be acceptable;
however, indicated, and specified performance and material requirements are minimum. The Engineer reserves the right to determine equality of equipment that deviates from any of the indicated and specified requirements.
E. Naming any manufacturer does not imply approval of that manufacturer's noncom- forming products.
F. The Contractor shall include in the Work; the materials, products and equipment named in the Contract Documents by trade name, proprietary name or manufacturer's catalog numbers, including any specified modifications thereto unless proposed substitutions are approved in writing by the Design Team.
1.07 SUBSTITUTIONS
A. The Engineer will consider formal requests from Contractor and Vendor for product substitutions.
1. The contractor shall submit written requests using Section 01 2500.01 Substitution Form to Engineer for review and consideration of proposed substitution.
2. Each proposed substitution shall require Engineer's written approval prior to inclusion in Work.
3. Any request not to use a complete Substitution Form will not be considered.
B. Submit separate requests for each substitution in compliance with Section 01 2500. Support each request with:
1. Complete data substantiating compliance of proposed substitution with requirements of Contract Documents.
2. Product identification including manufacturer's name and address.
3. Manufacturer's product data including product description, reference standards, and performance and test data.
4. Samples as applicable.
5. Name and address of similar projects on which product has been installed and date of each installation.
6. Itemized comparison of proposed substitution with product specified. List significant variations including costs.
01 2500-3
P a g e | 25
7. Data relating to changes in construction schedule.
8. List of changes required in other Work or products.
9. Designation of required license fees or royalties.
10. Designation of availability of maintenance service and source of replacement materials.
C. Substitutions will not be considered for acceptance when they are indicated or implied on Shop Drawings or Product Data Submittals without formal requests from the Contractor or when acceptance will require substantial revision of Contract Documents.
D. When a request for substitution is denied, the General Contractor shall provide specified Product.
E. Substitute products shall not be installed without an Engineer’s written acceptance or prior approval.
F. Where the shop drawings, product data and/or samples as submitted by Contractor indicate a departure from the Contract which Engineer deems to be a minor adjustment in the interest of Owner, not involving a change in the Contract Price or Contract Time, Engineer will approve the data/drawing, but the approval will contain, in substance, the following notation:
"The modification shown on the attached data/drawings is approved in the interest of Owner to effect an improvement for the Project and is accepted with the understanding that it does not involve any change in the Contract Price or Contract Time; that it is subject generally to all Contract stipulations and covenants; and that it is without prejudice to any and all rights of Owner under the Contract and Bond or Bonds."
Approval by Engineer of shop drawings, product data and/or samples will be general and shall not relieve Contractor from the responsibility of adherence to the Contract, nor shall it relieve him of the responsibility for any error which may exist or result.
1.08 CONTRACTOR'S REPRESENTATIVE
A. In making formal request for substitution, Contractor/Subcontractor represents:
1. He has investigated proposed product and has determined it is equal to or superior to specified product.
2. He will provide the same warranties and bonds for substitutions as for specified product.
3. He certifies cost data presented is complete and includes all related costs under this
Contract but excludes any Engineer's redesign costs and waives all claims for additional costs related to substitution which subsequently becomes apparent. Any redesign costs from use of substitution are the responsibility of the contractor.
4. He will coordinate installation of accepted substitute, making such changes as may be required for Work to be complete in all respects.
01 2500-4
P a g e | 26
5. He waives claims for additional costs caused by substitution which may subsequently become apparent or unforeseen at the time of approval.
1.09 ENGINEER'S DUTIES
1.09.1 Review Contractor's requests for substitutions with reasonable promptness.
1.09.2 Notify Contractor, in writing, of decision for acceptance or rejection of requests for substitution.
END OF SECTION 01 2500
01 2500-5
P a g e | 27
AtkinsRéalis - Baseline / Référence
TO:
SECTION 01 2500.01
PRODUCT SUBSTITUTION REQUEST FORM
FROM:
Name of Company _ _ _
Street Address
City and State
Phone Number and Name of Person to Contact
PROJECT:
1. Specification Section and Paragraph Numbers of product specified: _
2. Proposed Substitution:
a. Name and Model No. _
b. Manufacturer:
Name Address Phone
c. Description:
d. Attach applicable performance and test data.
e. Numbers of applicable reference standards.
f. Attach a color chart, if applicable.
g. Attach installation instructions.
3. Manufacturer's Reputation: Attach the following:
a. Evidence of reputation for prompt delivery.
b. Evidence of reputation for efficiency in servicing products.
01 2500.01-1
P a g e | 28
4. Comparison: Attach an itemized comparison of the proposed substitution with product specified, including all reference standards related to the product.
5. Previous Installation: Provide the following information on similar projects on which proposed substitution was used, list projects in both the locale of the project and the Atlanta metro area:
Name and Address of Project Date of Installation Name, address, and phone number of Design Team a.
b.
c.
d.
6. Changes in Work: Attach data relating to changes required in other work to permit use of proposed substitution and changes required in the construction schedule.
7. In making request for substitution, petitioner represents that he has examined the Drawings and has determined that, to the best of their knowledge, the proposed substitution is appropriate for the use intended in the Drawings and Specifications.
Signature of Petitioner/Bidder Date
END OF SECTION 01 2500.01
01 2500.01-2
P a g e | 29
SECTION 01 3100
PROJECT MANAGEMENT AND COORDINATION
Provisions and other Division 1 Specification Sections, apply to this section.
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. Requests for Information (RFIs).
4. Project meetings.
B. Related Requirements:
1. Section 01 7839 "Closeout Submittals" for coordinating closeout of the
Contract.
A. RFI: Request from Contractor seeking information required by or clarifications of the Contract Documents.
1.04 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, and telephone number of entities performing subcontractor supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
01 3100-01
P a g e | 30
Post copies of list in project meeting room, in temporary field office, and by each temporary telephone. Always keep list current.
1.05 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence are required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work.
Each contractor shall coordinate its operations with operations, included in different Sections, that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence are required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their
Work is required.
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
01 3100-02
P a g e | 31
6. Preinstallation conferences.
7. Project closeout activities.
E. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.
1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.
1.06 COORDINATION DRAWINGS
A. Coordination Drawings: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applicable Drawings as a basis for preparation of coordination drawings.
Prepare sections, elevations, and details as needed to describe relationships of various systems and components.
b. Coordinate the addition of trade-specific information to the coordination drawings by multiple contractors in a sequence that best provides coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
e. Indicate required installation sequences.
f. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Design Team indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
2. Review: Design Team will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If the Design Team determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Design Team will inform Contractor, who shall make changes as directed and resubmit.
01 3100-03
P a g e | 32
1.07 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Design Team/Owner’s Representative will return RFIs submitted to Design Team/ Owner’s Representative by other entities controlled by Contractor with no response.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Design Team’s Prime Consultant/Owner’s Representative.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: AIA Document G716 or software-generated form with substantially the same content as indicated above, acceptable to Design Team/Owner’s Representative.
1. Attachments shall be electronic files in Adobe Acrobat PDF format.
D. Design Team's Action: Design Team will review each RFI, determine action required, and respond. Allow seven working days for the Design Team's response for each RFI. RFIs received by Engineer after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
01 3100-04
P a g e | 33
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the
Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Design Team's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Design Team's action may include a request for additional information, in which case
Design Team's time for response will date from time of receipt of additional information.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit logs monthly. Use CSI Log Form 13.2B. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Design Team’s Prime Consultant.
4. RFI numbers, including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date Design Team's response was received.
F. On receipt of the Design Team's action, update the RFI log and immediately distribute the
RFI response to affected parties. Review response and notify Design Team within seven days if Contractor disagrees with response.
1.08 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify the Owner and Design Team of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Contractor will record significant discussions and agreements achieved.
Distribute the meeting minutes to everyone concerned, including the Owner and Design Team, within three days of the meeting.
B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Design Team, but no later than 15 days after execution of the Agreement.
1. Conduct the conference to review responsibilities and personnel assignments.
01 3100-05
P a g e | 34
2. Attendees: Authorized representatives of the Owner, Design Team, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other parties concerned shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect progress including, but not limited to, the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Lines of communications.
f. Procedures for processing field decisions and Change Orders.
g. Procedures for RFIs.
h. Procedures for testing and inspecting.
i. Procedures for processing Applications for Payment.
j. Distribution of the Contract Documents.
k. Submittal procedures.
l. Preparation of recorded documents.
m. Use of the premises.
n. Work restrictions.
o. Working hours.
p. Owner's occupancy requirements.
q. Responsibility for temporary facilities and controls.
r. Construction waste management and recycling.
s. Office, work, and storage areas.
t. Security.
4. Minutes: Contractor will record and distribute meeting minutes.
C. Pre-installation Conferences: Contractor shall conduct a pre-installation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Design Team/Owner’s Representative of scheduled meeting dates.
2. Agenda: Review of the progress of other construction activities and preparations for the activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Review of mockups.
i. Possible conflicts.
01 3100-06
P a g e | 35
j. Compatibility requirements.
k. Time schedules.
l. Weather limitations.
m. Manufacturer's written instructions.
n. Warranty requirements.
o. Compatibility of materials.
p. Acceptability of substrates.
q. Temporary facilities and controls.
r. Space and access limitations.
s. Regulations of authorities having jurisdiction.
t. Testing and inspecting requirements.
u. Installation procedures.
v. Coordination with other work.
w. Required performance results.
x. Protection of adjacent work.
y. Protection of construction and personnel.
3. Contractors shall record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requesting information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to the performance of the Work and reconvene the conference at the earliest feasible date.
D. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Owner and Design Team/Owner’s Representative, but no later than 30 days prior to the scheduled date of Substantial Completion.
1. The contractor shall conduct the conference to review requirements and responsibilities related to Project closeout.
2. Attendees: Authorized representatives of the Owner, Design Team, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of recorded documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Submittal of written warranties.
d. Requirements for preparing operations and maintenance data.
e. Requirements for delivery of material samples, attic stock, and spare parts.
f. Requirements for demonstration and training.
g. Preparation of Contractor's punch list.
h. Procedures for processing Applications for Payment at Substantial
Completion and for final payment.
01 3100-07
P a g e | 36
i. Submittal procedures.
j. Coordination of separate contracts.
k. Owner's partial occupancy requirements.
l. Installation of Owner's furniture, fixtures, and equipment.
m. Responsibility for removing temporary facilities and controls.
4. Minutes: Contractor shall record and distribute meeting minutes.
E. Progress Meetings: Contractor shall conduct progress meetings at monthly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representatives of the Owner and Design Team, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review the present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Progress cleaning.
10) Quality and work standards.
11) Status of correction of deficient items.
12) Field observations.
13) Status of RFIs.
14) Status of shop drawing reviews.
15) Pending changes.
16) Status of Change Orders.
17) Pending claims and disputes.
1 3100-08
P a g e | 37
18) Documentation of information for payment requests.
4. Minutes: Contractor shall record and distribute the meeting minutes to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized.
Issue revised schedule concurrently with the report of each meeting.
END OF SECTION 01 3100
01 3100-09
CONSTRUCTION SCHEDULES
01 3216-38
P a g e | 38
SECTION 01 3216
A. The work under this Section includes preparing, furnishing, distributing, and periodic updating of the construction schedules as specified herein.
B. The purpose of the schedule is to demonstrate that the Contractor can complete the overall
Project within the Contract Time and meet all required interim milestones.
1.02 QUALITY ASSURANCE
A. The development of the Overall Project Schedule (OPS) shall be by a party who has experience performing CPM scheduling utilizing the scheduling software on projects of similar type, size, and complexity.
1.03 SUBMITTALS
A. Overall Project Schedule (OPS)
1. Submit the OPS within 10 days after the date of the Notice to Proceed.
2. The Owner’s Representative will review the schedule and return it within 5 days after receiving receipt.
3. If required, resubmit corrected schedule within 5 days after receipt of a returned copy.
B. Near Term Schedule (NTS)
1. Submit the first Near Term Schedule within 10 days of the Notice to Proceed.
2. The Owner’s Representative will review the schedule and return it within 5 days after receiving receipt.
C. Schedule of Values (SOV)
1. Submit the SOV within 10 days after the date of Notice to Proceed.
2. The Owner’s Representative will review the SOV and return a reviewed copy within
5 days after receipt.
3. If required, resubmit corrected SOV within 5 days after receipt of a returned copy, or before submittal of first Application for Payment.
D. Submit an update of the OPS, NTS, and narrative with each progress payment request. Provide each update on a CD or flash drive, and an 11-inch x 17-inch copy.
01 3216-39
P a g e | 39
1.04 APPROVAL
A. Approval of the Contractor's construction schedule and revisions thereto shall in no way relieve the Contractor of any of Contractor's duties and obligations under the Contract. Approval is limited to the format of the schedule and does not in any way indicate approval of, or concurrence with, the Contractor's means, methods, and ability to carry out the work.
1.05 OVERALL PROJECT SCHEDULE (OPS)
A. The Contractor shall submit to the Owner for approval a detailed OPS of the Contractor's proposed operations for the duration of the Project. The OPS shall be in the form of a Critical Path Method bar chart.
B. Critical Path Method Schedule
1. Each activity shall be identified by a separate bar. Activities with a duration of more than 30 days shall be sub-divided into separate activities. Activities shall be grouped into separate areas of construction of the entire Project.
2. The schedule shall include activities for shop drawing preparation and review, fabrication, delivery, and installation of major or critical path materials and equipment items.
3. The schedule shall show the proposed start and completion date for each activity. A separate list of activity start and stop dates and working day requirements shall be provided.
4. The schedule shall identify the Notice to Proceed date, the Contract Completion date, major milestone dates, and a critical path.
5. The schedule shall be printed on a maximum 11-inch x 17-inch size paper. If the OPS needs to be shown on multiple sheets, a simplified, one-page summary bar chart showing the entire Project shall be provided.
6. The schedule shall have a horizontal time scale based on calendar days and shall identify the Monday of each week.
7. The schedule shall show the precedence for each activity.
8. Activities shall show relationships to other activities using arrows.
1.06 NEAR TERM SCHEDULE (NTS)
A. The Contractor shall develop and refine a detailed NTS showing the day-to-day activities with committed completion dates that must be performed during the upcoming 30-day period. The detailed schedule shall represent the Contractor's best approach to the work that must be accomplished to maintain progress consistent with the OPS.
B. The NTS shall be in the form of a Critical Path method bar chart and shall include a written narrative description of all activities to be performed and describe corrective action to be taken for items that are behind schedule.
1.07 UPDATING
A. Show all changes occurring since the previous submission of the updated schedule.
B. Indicate progress of each activity and show actual completion dates.
01 3216-40
P a g e | 40
C. The Contractor shall be prepared to provide a narrative report at the Project
Coordination Meetings. The report shall include the following:
1. A description of the overall Project status and comparison to the OPS.
2. Identify activities that are behind schedule and describe corrective action to be taken.
3. A description of changes or revisions to the Project and their effect on the OPS.
4. A description of the NTS of the activities to be completed during the next 30 days. The report shall include a description of all activities requiring participation by the Owner’s Representative and/or Owner.
END OF SECTION 01 3216
CONSTRUCTION PHOTOGRAPHS
01 3233-41
P a g e | 41
SECTION 01 3233
1.01 SUMMARY
A. Provisions in this Section are mandatory procedures for preparing and submitting construction photographs.
B. The Contractor shall furnish all equipment, labor, and materials required to provide the City with digital construction videos and photographs of the Project.
1.02 PHOTOGRAPHS
A. Progress Photographs
1. Prior to the beginning of any work, the Contractor shall take Project videos of the work area to record existing conditions.
2. Take progress photographs daily. Schedule photography to allow submittal of photos with monthly Application for Payment.
3. Take photographs beginning the first month of construction activity and terminating at Date of Final Acceptance.
4. Take photographs on the same day each month, weather permitting, and at same time of day.
5. Standard locations of which photos will be taken will be selected by the Owner’s Representative. Take photos of the same standard location each month, unless otherwise directed by Owner’s Representative. Assign a number to each of the standard photo locations, in comparison with previous and future submittals.
6. In addition to photographs of standard locations, take photographs which best show significant elements of the work. Locations for these photos shall be selected by the Contractor. Assign a number to each of the non- standard photograph locations, for comparison with previous and future submittals.
B. Color Aerial Photographs
1. Contractor to provide aerial photography at the following intervals:
a. Before construction starts.
b. Monthly with pay requests.
c. Upon completion of construction at Final Acceptance.
1.03 SUBMITTAL OF PHOTOGRAPHS
A. Progress Photographs
1. Submit electronic photographs with Contractor’s Application for Payment.
01 3233-42
P a g e | 42
2. Format and progress photographs: Provide electronic file in .jpg format. Photographs shall include the date and time marking of the recording.
3. Identify each photograph with photograph number, location, and element of work.
Provide written description of photograph number, project name, date, and Contractor’s name.
B. Color Aerial Photographs
1. Smith Aerial Service: 404/531-6448 or approved equal.
a. Size:
i. 8 by 10-inches for submittal with pay requests.
ii. 8 by 10-inches of 4 viewpoints, selected by Owner, of approved, finished work.
b. Print on glossy, photo quality paper.
c. Provide a high resolution “.jpg” file of each and all images.
d. Mounting:
i. Identify each print on the back with:
1. Name of Project.
2. Name of Owner’s Representative.
3. Name of Contractor.
4. Name and address of photographer.
5. Date photograph was taken.
6. Description of vantage point.
ii. Enclose back-to-back in clear plastic sleeves that are punched for a standard 3-ring binder.
END OF SECTION 01 3233
SUBMITTAL PROCEDURES
01 3300 - 43
P a g e | 43
SECTION 01 3300
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
B. Related Requirements:
1. Division 02 through 33 Sections for specific requirements for submittals in those
Sections.
A. Action Submittals: Written and graphic information and physical samples that require Design Team’s and Construction Manager's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require the Design Team's and Construction Manager's responsive action.