This file is a technical drawing exhibit prepared by KCI Technologies Inc. for the Florida Keys Electric Cooperative Association (FKEC) depicting the standard specifications for a typical underground electrical vault used in the Q Feeder project. The drawing shows a 90" x 60" x 60" pullbox design with detailed plan and elevation views across four walls (A, B, C, and D), illustrating the placement of conduit entries, stainless steel flush-mount pulling irons, galvanized hook lifters, and fiber optic bracket specifications. The design includes specific dimensional callouts for conductor and fiber placement, slack fiber bracket configurations, and top slab details. The vault serves as a standard component for the 3.5 miles of underground feeder installation extending from Crawl Key to Marathon Substation along US 1/Overseas Highway, with the drawing indicating provisions for both primary conductor installation and secondary fiber optic cable management.
This technical exhibit directly supports the broader Q Feeder construction project, which requires contractors to comply with FKEC-approved equipment specifications and underground installation standards. The drawing reflects the engineering standards and material specifications that selected contractors must implement as part of the overall distribution feeder rebuild project. By providing this typical vault design as a standardized exhibit, FKEC establishes consistent construction requirements across the underground portion of the feeder, reducing ambiguity in bidding and ensuring that all underground installations meet uniform specifications for structural integrity, equipment accommodation, and operational accessibility.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S U
R V
E Y
D A
T A
C ou nt y/
S ta te
Q ua dr an gl e:
S ec
T
R
S P
C
H or z D at um
V er t D at um
K C
I T
EC
H N
O
LO
G
IE
S
IN
C
R
IO
V
IS
TA
D
R
IV
E C
LE
AR
W
AT
ER
, F
L
TE
L
3-
0-
FA
X
3-
0-w w w .k ci .c om
FK
EK
W
AR
N
IN
G
HI
GH
V O
LT
AG
E
TOP SLAB DETAIL
SEE FKEC ASSEMBLY UNIT:
UG-PBC FOR LID DETAILS
PLAN DETAIL
WALL "A" ELEVATION WALL "B" ELEVATION
A
D B
C
A
D B
C
7'-6"
5'-0"
7'-6" 6"
6'-6" 6"
1'-1"
5"
6"
4'-0"
6"
8" STAINLESS STEEL FLUSH
MOUNT PULLING IRONS
5.5" GALVANIZED
HOOK LIFTERS
5" (TYP.)
5"
2"
2"3'-2"
2"
2"
6"
5'-0"
2"
2"
2"
6"
5"
6"
3'-0"
NOTES:
Fiber bracket and extra fiber to wrapped on wall opposite to primary conductor.
SLACK FIBER
BRACKET
WALL "C" ELEVATION WALL "D" ELEVATION
5" (TYP.)
5"
2"
2"3'-2"
2"
2"
6"
5'-0"
2"
2"
2"
6"
5"
6"
3'-0"
90" X 60" X 60" PULLBOX SPECIFICATIONS
Reverse the conduit shown in green for fiber