Exhibit G _ Project Schedule.pdf

PDF 209 KB Posted

Attached to
[2011-25 GTFI RFQP-DP] GT Zelnak Basketball Headquarters Renovation & Expansion
Solicitation number
PE-50300-RFP-2025-000000172
Issued by
Fulton County, Georgia

About this file

This is a project schedule (Exhibit G) for the GT Basketball Headquarters construction project managed by GT Infrastructure and Sustainability. The overall project spans 538 days, running from December 9, 2024, to December 30, 2026. The schedule is broken down into major phases including Contracting (63 days), Design (35 weeks), Bid & Award (12 weeks), and Construction & Closeout (245 days). Key milestones include Design Team Selection starting December 9, 2024, Construction Team Selection beginning December 16, 2024, and Phase 1 construction running from January 22, 2026, to September 16, 2026.

The schedule details specific design phases including Schematic Design (8 weeks), Design Development (7 weeks), and Construction Documents (20 weeks). The bid and award process includes a 2-week permitting period from October 30, 2025, to November 12, 2025. The construction phase is divided into Phase 1 (34 weeks) and Phase 2 (marked as 0 days on January 22, 2026). The schedule is presented in both Gantt chart format and tabular form, clearly showing task dependencies and parallel activities throughout the project lifecycle.

View the file

Other files

File Type Posted
Addendum__1 for release 01_06_2025.pdf PDF
Exhibit D _ DP Fee Proposal.doc DOC document
0251_2025 RFQP_DP_Final.pdf PDF
Exhibit A _ Certification Form.docx DOCX document
Exhibit H _ Sample Form of AIA Contract.pdf PDF
Exhibit E _ Contractor Affidavit.docx DOCX document
Exhibit B _ Certificate of Insurance _ Minori.docx DOCX document
Exhibit C _ Team Composition.docx DOCX document
Exhibit F _ Proposer_s Disclosure Statement.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish Notes

1 GT Basketball Headquarters 538 days Mon 12/9/24 Wed 12/30/26

2 Contracting 63 days Mon 12/9/24 Wed 3/5/25

3 Design Team Selection 58 days Mon 12/9/24 Wed 2/26/25

4 Construction Team Selection 58 days Mon 12/16/24 Wed 3/5/25

5 Design 35 wks Thu 2/27/25 Wed 10/29/25

6 Schematic Design 8 wks Thu 2/27/25 Wed 4/23/25

7 Design Team Released into DD's 8 wks Thu 2/27/25 Wed 4/23/25

8 Design Development 7 wks Thu 4/24/25 Wed 6/11/25

9 Design Team Released into CD's 7 wks Thu 4/24/25 Wed 6/11/25

10 Construction Documents 20 wks Thu 6/12/25 Wed 10/29/25

11 Team Production Time 20 wks Thu 6/12/25 Wed 10/29/25

12 Bid & Award 12 wks Thu 10/30/25 Wed 1/21/26

13 Permitting 2 wks Thu 10/30/25 Wed 11/12/25

14 Bid & Award 12 wks Thu 10/30/25 Wed 1/21/26

15 Construction & Closeout 245 days Thu 1/22/26 Wed 12/30/26

16 Phase 1 34 wks Thu 1/22/26 Wed 9/16/26

17 Phase 2 0 days Thu 1/22/26 Thu 1/22/26

Design Team Selection

Construction Team Selection

Design Team Released into DD's

Design Team Released into CD's

Team Production Time

Permitting

Bid & Award

Phase 1

1/22

D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026

GT Basketball Headquarters - Preliminary Schedule 12.05.2024

Exhibit G Project Schedule