Exhibit F _ Project Cost Matrix.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- UGA_BR-10-2702 CM Oglethorpe House Renovation
- Solicitation number
- PE-47200-RFQ-2027-000000163
- Issued by
- Clarke County, Georgia
About this file
This file is a Cost Proposal Matrix for a construction project at an unnamed institution in Georgia. The matrix serves as a template guide for bidders to allocate and submit cost proposals across three primary cost categories: Construction Fee, General Conditions, and Cost of Work By Others. The document outlines approximately 100 line items organized into six major sections: Site Supervision & Management, Site Office Expense, Safety & Security, Cleaning, General Equipment, and Bonds & Insurance, with an additional Miscellaneous section containing numerous project-related expenses. The matrix indicates a projected fee of $1,231,000 based on a $46 million Guaranteed Maximum Price (GMP), providing bidders with a cost allocation framework to structure their proposals according to the owner's preferences for expense categorization.
The Cost Proposal Matrix establishes specific allocation guidelines through marked cells indicating where the owner wishes costs to be categorized, with many line items designated for inclusion in Construction Fee, General Conditions, or Cost of Work By Others. Several expense categories are marked as "NA" or "Incl." to indicate items not applicable to this project or already included in other line items. The matrix does not contain information regarding set-asides, contract term, response dates, or funding sources. This document functions as a cost accounting tool to ensure consistent bid evaluation and transparent cost breakdown across all proposal submissions for the Georgia institutional construction project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit D _ Preconstruction Cost _ Expenses B.xlsx | XLSX spreadsheet | |
| Exhibit G _ Proposer_s Disclosure Statement.doc | DOC document | |
| Egnyte Upload Instructions.pdf | ||
| _UGA_BR_10_2702_CM_RFQ_RFP.pdf | ||
| Exhibit E _ General Conditions Breakdown.xlsx | XLSX spreadsheet | |
| Exhibit A _ Certification Form.docx | DOCX document | |
| Exhibit C _ CM_GC Fee Proposal.docx | DOCX document | |
| Exhibit B _ Contractor Affidavit.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cost Proposal Matrix
| PROJECT COST MATRIX | ||||||||
| The spaces marked with an "X" below indicate where the Owner wishes to allocate costs for the project. Please follow this as a guide in preparing your cost proposal for the project. | ||||||||
| Project No., Project Name | ||||||||
| Institution Name, City, Georgia | ||||||||
| I. Site Supervision & Management: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Project Executive | X | |||||||
| Corporate Executives | X | |||||||
| Legal Services | X | |||||||
| Senior Project Mgr. | X | $0 | $0 | 0 | $0 | |||
| Project Mgr. | X | $0 | $0 | 0 | $0 | |||
| Project Supt. | X | $0 | $0 | 0 | $0 | |||
| Asst. Project Supt. | X | $0 | $0 | 0 | $0 | |||
| Area Supt. | X | NA | ||||||
| Secretary | X | $0 | $0 | 0 | $0 | |||
| Project Engineer | X | $0 | $0 | 0 | $0 | |||
| Engineer or Eng. Company | X | $0 | $0 | |||||
| Cost Control | X | $0 | $0 | |||||
| Safety Engineer | X | 0 | $30,000 | |||||
| Scheduling | X | $0 | $0 | 0 | $0 | |||
| Purchasing | X | 0 | $0 | |||||
| Project Accountant | X | Incl. | ||||||
| Rodman | X | Incl. | ||||||
| $0 | $0 | 0 | $0 |
| II. Site Office Expense: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Job Office Trailer Rent | X | NA | ||||||
| Office Jobsite Build Out | X | $0 | $0 | 0 | $0 | |||
| Office Jobsite Set-up | X | $0 | $0 | 0 | $0 | |||
| Temp. Const. Trailer/Storage | X | NA | ||||||
| Office Furniture | X | Incl. Below | ||||||
| Office Machines/Equip. | X | $0 | $0 | 0 | $0 | |||
| Copy Machines/Maintenance | X | Incl. Above | ||||||
| Office Supplies | X | $0 | $0 | 0 | $0 | |||
| Janitor/San. Supplies | X | $0 | $0 | |||||
| Postage & Shipping | X | $0 | $0 | 0 | $0 | |||
| First Aid/Med. Treat. | X | $0 | $0 | |||||
| Telephone System | X | $0 | $0 | 0 | $0 | |||
| Phone Installation | X | 0 | $0 | |||||
| Phone Charges | X | 0 | $0 | |||||
| Phone Charges-Long Dist. | X | By Arch. | ||||||
| Radio Communications | X | $0 | $0 | 0 | $0 | |||
| Radio Maintenance | X | Incl. | ||||||
| Computer-PCS | X | $0 | $0 | 0 | $0 | |||
| Computers | X | Incl. | ||||||
| Software | X | $0 | $0 | 0 | $0 | |||
| MIS Charges | X | 0 | $0 | |||||
| Temp. Electric-Office | X | |||||||
| Security-Office | X | |||||||
| Water - Field Office | X |
| 0 | $0 | |||||||
| III. Safety & Security: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Safety Incentives | X | NA | ||||||
| Watchman/Guard Ser. | X | 0 | $0 | |||||
| Traffic Control | X | $0 | $0 | 0 | $0 | |||
| Safety Equipment | X | $0 | $0 | 0 | $0 | |||
| Rainwear/Hardhats, etc. | X | 0 | $0 | |||||
| Drug Testing | X | $0 | $0 | 0 | $0 | |||
| Fences & Gates | X | 0 | $0 | |||||
| Fire Protection, Extinquishers, Barrels | X | 0 | $0 | |||||
| Covered Walkways | X | 0 | $0 | |||||
| Roadway Maintenance | X | $0 | $0 | |||||
| Sidewalk Barricades | X | $0 | $0 | |||||
| Safety Railings | X | $0 | $0 | |||||
| Opening Closures | X | |||||||
| Weather Protection | X | |||||||
| Ladders & Stailrs | X |
| IV. Cleaning: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Trash Bin Rent/Haul | X | Incl. | ||||||
| Trash Chutes/Hoppers | X | $0 | $0 | 0 | $0 | |||
| Dump Fees/Hauling | X | $0 | 0 | $0 | ||||
| Dust Barricades | X | 0 | $0 | |||||
| Daily Cleaning | X | |||||||
| Final Cleanup-Building | X | |||||||
| Window/Skylight Cleaning | X |
| $0 | 0 | $0 | ||||||
| V. General Equipment: | Construction Fee | General Conditions | Cost of Work | By Others | $0 | 0 | $0 | |
| Small Tools/Expendables | X | $0 | $0 | 0 | $0 | |||
| Survey Equipment | X | Incl. | ||||||
| Hoist/Operator | X | 0 | $0 | |||||
| Hoist Service | X | $0 | $0 | 0 | $0 | |||
| Erect/Dismantle Hoist | X | 0 | $0 | |||||
| Temp. Elev. & Operator | X | $0 | 0 | $0 | ||||
| Rapair Cab/Temp. Elev. | X | $0 | 0 | $0 | ||||
| Protect Perm. Elevator | X | |||||||
| Fuel/Oil/Grease | X | |||||||
| Forklift Rental | X | |||||||
| Contractor Equipment License | X | |||||||
| Contractor Equipment Permits | X | |||||||
| Tower Crane Service | X | |||||||
| Erect/Dismantle Crane | X | |||||||
| Crane Rental/Operator | X | |||||||
| Construction Equipment | X |
| VI. Bonds & Insurance: | Construction Fee | General Conditions | Cost of Work | By Others | |
| Perform. & Payment Bonds | X | ||||
| Workers Comp. Insurance | X | ||||
| Liability Insurance | X | ||||
| Fed. & State Unemployment | X | ||||
| FICA | X | ||||
| Builders Risk Insurance | X | ||||
| $1,231,000 |
| Projected Fee (Based on $46 Million GMP) | ERROR:#REF! | |
| Builders Risk Insurance | X |
| VII. Miscellaneous: | Construction Fee | General Conditions | Cost of Work | By Others | ||
| CM General Overhead Cost | X | |||||
| CM Profit Margin | X | |||||
| Costs Over GMP | X | |||||
| Project Staff Living Expenses | X | |||||
| Executive Travel | X | |||||
| Air Fare | X | |||||
| Car Rental | X | |||||
| Hotel | X | |||||
| Meals | X | |||||
| Project Staff Moving Expenses | X | |||||
| Warranty Work | X | |||||
| Off-Site Parking | X | |||||
| Ceremony Expense | X | |||||
| Vehicle for On-Site Project Manager | X | |||||
| Vehicle for On-Site Superintendent | X | |||||
| Vehicle Repairs/Maintenance | X | |||||
| Water - Coolers | X | |||||
| Water Barrels | X | |||||
| Ice Machine | X | |||||
| Ice and/or Cups | X | |||||
| Temporary Toilets Install | X | |||||
| Temporary Toilets | X | |||||
| Cold Weather Protection | X | |||||
| Temp. Heat for Bldg. | X | |||||
| Job Signs | X | |||||
| Progress Photos | X | |||||
| Extra Plans & Specs. | X | |||||
| Blueprint/Photostat. | X | |||||
| Temp. Electric -Building | X | |||||
| Building Permit | X | |||||
| Plan Check Fees | X | |||||
| Temporary Roads | X | |||||
| Project Taxes | X | |||||
| Moving Coordination & Costs for Project | X | |||||
| Materials Incorporated Into the Building | X | |||||
| Corrective Work | X | |||||
| Punchlist Work | X | |||||
| Advertising for Bids | X | |||||
| Soils Testing & Investigation | X | |||||
| Construction Materials Testing | X | 0 | $0 | |||
| Special Inspections | X | |||||
| Water Connection Fees | X | |||||
| Sanitary Connection Fees | X | |||||
| Storm Connection Fees | X | |||||
| Gas Service Fees | X | |||||
| Power Service Fees | X | |||||
| Impact Fee | X |
&"Arial,Bold"&16&UExhibit F
Sheet2