Exhibit D

16 KB Posted

Attached to
“15th Street Parking Deck”
Solicitation number
PPV-40-2201-DB
Issued by
Richmond County, Atlanta City, Georgia

About this file

Exhibit D is a preconstruction costs and expenses breakdown form for the 15th Street Parking Deck design-build project at Augusta University in Augusta, Georgia. The form provides a detailed template for itemizing preconstruction costs across two primary categories: preconstruction supervision and management, and miscellaneous preconstruction expenses. The supervision and management section includes line items for senior project manager, project manager, preconstruction manager, project superintendent, cost control, scheduling, secretary, consultant, and other identified positions, all measured in months. The miscellaneous expenses section covers office supplies, postage and shipping, blueprint and photostat services, phone charges, long-distance phone charges, courier service, travel expenses, and other identified costs. Each line item contains columns for quantity, unit, labor costs, material costs, subcontractor costs, and corresponding subtotals, with a final total for all preconstruction costs and expenses.

The form currently reflects all costs at zero dollars, with the exception of a $30,000 entry in the cost control line item, indicating that the document serves as a template awaiting completion by the design-build contractor. Certain expenses are noted as being provided by the architect, such as blueprint and photostat services, or included in other line items, such as long-distance phone charges. The total preconstruction costs and expenses line shows $0, suggesting this exhibit requires the contractor's detailed cost proposal submission as part of the design-build services response for the 15th Street Parking Deck project.

Text of this file

Attach. A - Precon Cost & Exp.

EXHIBIT D

PRECONSTRUCTION COSTS AND EXPENSES BREAKDOWNBeers
DescriptionQtyUnitLabor*Mat'l**SubLabor SubtotalMat'l SubtotalSub SubtotalTotalNotesQtyUnitLabor*Mat'l**SubLabor SubtotalMat'l SubtotalSub SubtotalTotalNotes
A.Preconstruction - Supervision & Management:
1Senior Project Mgr.mos$0$0$0$0$0$00$0
2Project Mgr.mos$0$0$0$0$0$00$0
3Preconstruction Managermos$0$0$0$0
4Project Supt.mos$0$0$0$0$0$00$0
5Cost Controlmos$0$0$0$00$30,000
6Schedulingmos$0$0$0$00$0
7Secretarymos$0$0$0$0$0$00$0
8Consultantmos$0$0$0$0
9Other (Identify)mos$0$0$0$0
Subtotal$0
B.Preconstruction - Miscellaneous
10Office Suppliesmos$0$0$0$0$0$00$0
11Postage & Shippingmos$0$0$0$0$0$00$0
12Blueprint/Photostat.ls$0$0$0$0By Arch.
13Phone Chargesmos$0$0$0$0$0$00$0
14Phone Charges-Long Dist.mos$0$0$0$0Incl.
15Courier Servicemos$0$0$0$0
16Travel Expensesmos$0$0$0$0
17Other (Identify)mos$0$0$0$0
Subtotal$0

TOTAL ALL PRECONSTRUCTION COST AND EXPENSES $0

&D &T &P

Sheet2

Sheet3

Other files

File Type Posted
Exhibit B —
Exhibit F —
AU PPV-40-2201-DB Addn. No. 1 —
AU PPV-40-2201- DB RFQ-RFP —
Exhibit A —
AU PPV-40-2201-DB Addn. No. 2 —
Award Information —
Exhibit C —
Egnyte Upload Instructions —
Exhibit G —
Exhibit E —
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .