This is an exhibit document detailing signage replacement specifications for the Zulu Sign Project at Buckley Air Space Force Base in Colorado, prepared for the 140th Civil Engineering division. The project encompasses the replacement of multiple taxiway and pad signage arrays at Runway/Taxiway Z, including five distinct sign locations: the Z Pad/Taxiway Signage area (requiring replacement of an 18-foot by 4-foot by 12-inch deep concrete base and a new L-858 Size 3 3-step LED sign), the Mandatory Sign Array west of Z Pad (L-858 Size 3 3-step LED), the Mandatory/Location Sign Array east of Z Pad (L-858 Size 3 5-step LED with repositioned directional markers), the Mandatory/Location Sign Array at the Runway/Taxiway Z intersection (L-858 Size 3 5-step LED), and the Directional Sign Arrays on both the south and north sides of the intersection (L-858 Size 3 5-step LED). All existing signs are to be removed and replaced with new LED signage featuring updated legends where applicable.

All signs must comply with FAA standards including L-858Y(L), L-858R(L), L-858L(L), L-858H(L), and L-858B(L) designations, AC 150/5345-44 standards, and FAA Engineering Brief No. 67. The signs must be ETL certified and compatible with both ferroresonant and thyristor Constant Current Regulators, operate on 3-step, 5-step, and 1-step CCRs with current loads between 2.8 and 6.6 amperes, and include lightning protection compliant with FAA Engineering Brief No. 67D and ANSI/IEEE standards. Required construction materials include non-ferrous aluminum frames, stainless-steel hardware, impact-resistant modified acrylic legend panels, and retroreflective sheeting. All signs must include tethers on all legs, external grounding lugs, and no external power switches. Contractors are required to submit sign legend proofs to 140th Civil Engineering for review and approval prior to ordering new signage.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Z PAD / TWY SIGNAGE

* REMOVE EXISTING 18FT X 4FT X12” DEEP CONCRETE BASE AND REPLACE WITH NEW.

* REMOVE EXISTING SIGN AND REPLACE WITH NEW L-858, SIZE 3, 3-STEP, LED.

* PROVIDE UPDATED LEGEND SHOWN IN NEXT SLIDE

* NEW SIGN MAY BE SHORTER IN LENGTH DUE TO NEW LEGEND

(1) EXISTING SIGN ARRAY WEST OF Z PAD

FACING EAST FACING WEST

MANDATORY SIGN ARRAY WEST OF Z PAD

BACK SIDE, Z APRON DESTN SIGN

Facing East

Facing West Z APRON

* REMOVE EXISTING SIGN AND REPLACE WITH NEW L-858, SIZE 3, 3-STEP, LED.

* PROVIDE NEW SIGN WITH UPDATED LEGEND SHOWN IN NEXT SLIDE

* NEW SIGN MAY BE SHORTER IN LENGTH DUE TO NEW LEGEND

(2) EXISTING SIGN ARRAY EAST OF Z PAD

Facing West

East

MANDATORY / LOCATION SIGN ARRAY EAST OF Z PAD

BACK SIDE EXAMPLE

Facing West

East

* REMOVE EXISTING SIGN AND REPLACE WITH NEW L-858, SIZE 3, 5-STEP, LED

* NEW SIGN TO HAVE SAME LEGEND AS EXISTING. * MOVE DIRECTIONAL Z ON SIDE FACING WEST TO RIGHT SIDE OF NEW

SIGN

(3) MANDATORY/LOCATION SIGN ARRRAY AT RWY/TWY Z

INTERSECTION

Facing East

West

* REMOVE EXISTING SIGN AND REPLACE WITH NEW L-858, SIZE 3, 5-STEP LED

* NEW SIGN TO HAVE SAME LEGEND AS EXISTING

(4) DIRECTIONAL SIGN ARRRAY AT SOUTH SIDE OF RWY/TWY Z

INTERSECTION

South Side

North Side

* REMOVE EXISTING SIGN AND REPLACE WITH NEW L-858, SIZE 3, 5-STEP LED

* NEW SIGN TO HAVE SAME LEGEND AS EXISTING

(5) DIRECTIONAL SIGN ARRRAY AT NORTH SIDE RWY/TWY Z

INTERSECTION

North Side

South Side

Sign Requirements:

• Signs must comply with FAA standards: L-858Y(L), L-858R(L), L-858L(L), L-858H(L), and L-858B(L) AC 150/5345-44 (Current Edition) and the FAA Engineering Brief No. 67. ETL Certified

• Compatible with ferroresonant and thyristor CCRs in compliance with FAA and IEC requirements.

• Provides constant illumination on all CCR steps 2.8 - 6.6 A. Operates on all steps of a 3-step, 5-step, and 1-step CCRs.

• Lightning protection that complies with FAA Engineering Brief No. 67D and ANSI/IEEE C62.41- 1991 Location Category C2.

• Non-ferrous aluminum frame and mounting. Stainless-steel hardware. Impact resistant modified acrylic legend panels. Retroreflective sheeting

• Signs to be LED size 3, tethers on all legs, external grounding lug, no external power switch

• Contractor shall submit sign legend proofs to 140th Civil Engineering for review and approval prior to ordering new signs.

Concrete Base Detail

Concrete Base Detail

TWY ZULU MAP

Z Pad / TWY Signage
* Remove existing 18ft x 4ft x12” deep concrete base and replace with new.��* Remove existing sign and replace with new l-858, Size 3, 3-step, led. ��* Provide updated legend shown in next slide��* New sign may be shorter in length due to new legend�
mandatory sign array west of z pad
����* Remove existing sign and replace with new l-858, Size 3, 3-step, led. ��* Provide new sign with updated legend shown in next slide��* New sign may be shorter in length due to new legend����
MANDATORY / LOCATION SIGN ARRAY east OF Z PAD
* Remove existing sign and replace with new L-858, size 3, 5-step, led��* new sign to have same legend as existing. * Move Directional z on side facing west to right side of new sign
* Remove existing sign and replace with new l-858, size 3, 5-step led��* New sign to have same legend as existing�
* Remove existing sign and replace with new l-858, size 3, 5-step led��* new sign to have same legend as existing
Slide Number 9
Slide Number 10
Slide Number 11
Slide Number 12

File details come from the government source that posted it. Updated .