Exhibit C Bid Price Proposal Revised 1.xlsx

XLSX spreadsheet 47 KB Posted

Attached to
D/W Right of Way Asbestos and Air Monitoring Consulting Services
Solicitation number
ITB-06217
Issued by
Miami-Dade County, Florida

About this file

This document is an Exhibit C Bid Price Proposal for a state and local contract opportunity issued by the Florida Department of Transportation (FDOT) to provide District-Wide Right-of-Way Asbestos and Air Monitoring Consulting Services in Miami-Dade and Monroe Counties. The project/proposal number is DOT-ITB-23-6181IZ Rebid, with a Financial Project Number of Various. The work description includes asbestos survey and reporting, operation and maintenance plans, asbestos airborne fiber assessment, operations and maintenance implementation, abatement specifications, agreement administration, asbestos abatement, and final clearance reports. The bid proposal contains estimated unit quantities and unit prices for these various services. Proposals are due on September 06, 2023, at 10:00 AM via email to D6.Purch@dot.state.fl.us.

The bid price proposal form requires the consultant to provide their company name, federal ID number, authorized signature, and contact information. The consultant must acknowledge that the unit prices submitted include overhead, profits, permits, travel, administrative expenses, materials, equipment, insurance, bonding, and all other incidentals required to complete the contract services. The contract may be renewed for the same price, terms, and conditions as the original agreement. The low bidder will be determined by the "Grand Total" bid amount, which is not to be considered the final contract amount.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule

State of Florida
Department of Transportation

EXHIBIT “C”, BID BLANK/PRICE PROPOSAL

TO PROVIDE DISTRICT-WIDE RIGHT-OF-WAY ASBESTOS AND AIR MONITORING CONSULTING SERVICES
IN MIAMI-DADE AND MONROE COUNTIES FOR THE FLORIDA DEPARTMENT OF TRANSPORTATION (FDOT).
PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZRebid
FINANCIAL PROJECT NUMBER:Various
Company Name:
Federal ID Number:
Authorized Signature:
Type or Print Name:
Title:
Address:
City, State, Zip Code:
Telephone Number:
Fax Number:
E-mail Address:

By signing above, the Bidder acknowledges they have read and understand the Scope of Services and Method of Compensation and that the unit prIces submitted in this price proposal form includes the Consultant's overhead, profits, permits, travel, administrative expenses, materials, equipment, insurance, bonding, all other incidentals and all direct and indirect costs required to complete the contract services. The Consultant named below agrees that if this Contract/Agreement is renewed, it shall be renewed for the same price, terms, and conditions as set forth in the original Contract/Agreement.

Consultant shall return all eight (8) pages of the Exhibit "C", Bid Price Proposal.

PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZRebid
FINANCIAL PROJECT NUMBER:Various
CONSULTANT'S NAME:
SECTION 1.0
ASBESTOS SURVEY AND REPORT
ITEM #WORK DESCRIPTIONAVERAGE SIZEUNITUNIT PRICEXESTIMATED UNITS=TOTAL COST
1.1RESIDENTIAL FACILITY1,500 SQUARE FOOTPER SQUARE FOOTX40=$0.00
1.2COMMERCIAL FACILITY (LESS THAN 10,000 SQUARE FEET)5,000 SQUARE FOOTPER SQUARE FOOTX40=$0.00
1.3COMMERCIAL FACILITY (MORE THAN 10,000 SQUARE FEET)12,000 SQUARE FOOTPER SQUARE FOOTX40=$0.00
1.4MOBILE HOMES500 SQUARE FOOTPER SQUARE FOOTX10=$0.00
1.5BUILDING CUTOFF100 PER SQUARE FOOTPER SQUARE FOOTX10=$0.00
1.6INSPECTION (NO SAMPLING)PER BUILDINGX10=$0.00
1.7INSPECTIONPER BRIDGEX10=$0.00
TOTAL COST FOR SECTION 1.0 - ASBESTOS SURVEY AND REPORT$0.00
Note: The number of units specified may not match the actual number of parcels. The estimated units shown on the Price Proposal are for price evaluation only. The actual quantities for this agreement will be dependant on the number of tasks assigned. The unit cost per task will apply for the full term of agreement.
PROJECT/PROPOSAL NUMBER:DOT-ITB -23-6181IZRebid
FINANCIAL PROJECT NUMBER:Various
CONSULTANT'S NAME:
SECTION 2.0
OPERATION AND MAINTENANCE PLAN
ITEM #WORK DESCRIPTIONAVERAGE SIZEUNITUNIT PRICEXESTIMATED UNITS=TOTAL COST
2.1LETTER PLANPER PLANX10=$0.00
2.2FULL-SCALE PLANPER PLANX10=$0.00
TOTAL FOR SECTION 2.0 - OPERATION AND MAINTENANCE PLAN$0.00
Note: The number of units specified may not match the actual number of parcels. The estimated units shown on the Price Proposal are for price evaluation only. The actual quantities for this agreement will be dependant on the number of tasks assigned. The unit cost per task will apply for the full term of agreement.
PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZ
FINANCIAL PROJECT NUMBER:TBA
CONSULTANT'S NAME:
SECTION 3.0
ASBESTOS AIRBORNE FIBER
ITEM #WORK DESCRIPTIONAVERAGE SIZEUNITUNIT PRICEXESTIMATED UNITS=TOTAL COST
3.1ASSESSMENT (SHIFT RATE)PER 8 HOUR SHIFTX40=$0.00
3.2ASSESSMENT-OVERTIME RATE (SHIFT RATE)PER PLANX10=$0.00
TOTAL FOR SECTION 3.0 - ASBESTOS AIRBORNE FIBER$0.00
Note: The number of units specified may not match the actual number of parcels. The estimated units shown on the Price Proposal are for price evaluation only. The actual quantities for this agreement will be dependant on the number of tasks assigned. The unit cost per task will apply for the full term of agreement.
PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZRebid
FINANCIAL PROJECT NUMBER:Various
CONSULTANT'S NAME:
SECTION 4.0
OPERATIONS AND MAINTENANCE IMPLEMENTATION
ITEM #WORK DESCRIPTIONAVERAGE SIZEUNITUNIT PRICEXESTIMATED UNITS=TOTAL COST
4.1OPERATIONS AND MAINTENANCE IMPLEMENTATION (SHIFT RATE)PER 8 HOUR SHIFTX10=$0.00
TOTAL FOR SECTION 4.0 - OPERATIONS AND MAINTENANCE IMPLEMENTATION$0.00
Note: The number of units specified may not match the actual number of parcels. The estimated units shown on the Price Proposal are for price evaluation only. The actual quantities for this agreement will be dependant on the number of tasks assigned. The unit cost per task will apply for the full term of agreement.
PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZ
FINANCIAL PROJECT NUMBER:Various
CONSULTANT'S NAME:
SECTION 5.0
ABATEMENT SPECIFICATIONS
ITEM #WORK DESCRIPTIONAVERAGE SIZEUNITUNIT PRICEXESTIMATED UNITS=TOTAL COST
5.1ABATEMENT SPECIFICATIONSPER SET OF SPECSX10=$0.00
TOTAL FOR SECTION 5.0 - ABATEMENT SPECIFICATIONS$0.00
Note: The number of units specified may not match the actual number of parcels. The estimated units shown on the Price Proposal are for price evaluation only. The actual quantities for this agreement will be dependant on the number of tasks assigned. The unit cost per task will apply for the full term of agreement.
PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZRebid
FINANCIAL PROJECT NUMBER:Various
CONSULTANT'S NAME:
SECTION 6.0
AGREEMENT ADMINISTRATION
ITEM #WORK DESCRIPTIONAVERAGE SIZEUNITUNIT PRICEXESTIMATED UNITS=TOTAL COST
6.1AGREEMENT ADMINISTRATIONPER HOURX140=$0.00
TOTAL FOR SECTION 6.0 - AGREEMENT ADMINISTRATION$0.00
Note: The number of units specified may not match the actual number of parcels. The estimated units shown on the Price Proposal are for price evaluation only. The actual quantities for this agreement will be dependant on the number of tasks assigned. The unit cost per task will apply for the full term of agreement.
PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZRebid
FINANCIAL PROJECT NUMBER:Various
CONSULTANT'S NAME:
Section 7.0
ASBESTOS ABATEMENT
ITEM #WORK DESCRIPTIONAVERAGE SIZEUNITUNIT PRICEXESTIMATED UNITS=TOTAL COST
7.1LICENSED ASBESTOS CONSULTANT (SHIFT RATE)PER 8 HOUR SHIFTx10=$0.00
7.2ASBESTOS PROJECY MANAGER (SHIFT RATE)PER 8 HOUR SHIFTx10=$0.00
7.3ASBESTOS PROJECT MONITOR (SHIFT RATE)PER 8 HOUR SHIFTx10=$0.00
7.4ASBESTOS INSPECTOR/SUPERVISOR (SHIFT RATE)PER 8 HOUR SHIFTx10=$0.00
7.5ADMINISTRATIVE ASSISTANT (SHIFT RATE)PER 8 HOUR SHIFTx10=$0.00
TOTAL FOR SECTION 7.0 - ASBESTOS ABATEMENT$0.00
Note: The number of units specified may not match the actual number of parcels. The estimated units shown on the Price Proposal are for price evaluation only. The actual quantities for this agreement will be dependant on the number of tasks assigned. The unit cost per task will apply for the full term of agreement.
PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZRebid
FINANCIAL PROJECT NUMBER:Various
CONSULTANT'S NAME:
Section 8.0
FINAL CLEARANCE REPORTS
ITEM #WORK DESCRIPTIONAVERAGE SIZEUNITUNIT PRICEXESTIMATED UNITS=TOTAL COST
8.1ASBESTOS ABATEMENTPER REPORTx40=$0.00
8.2DEMOLITION CLEARANCE REPORTSPER REPORTx40=$0.00
TOTAL FOR SECTION 8.0 - FINAL CLEARANCE REPORTS$0.00
Note: The number of units specified may not match the actual number of parcels. The estimated units shown on the Price Proposal are for price evaluation only. The actual quantities for this agreement will be dependant on the number of tasks assigned. The unit cost per task will apply for the full term of agreement.
PROJECT/PROPOSAL NUMBER:DOT-ITB-23-6181IZRebid
FINANCIAL PROJECT NUMBER:Various
BIDDER'S NAME:
TOTAL AMOUNTS FOR SECTIONS 1.0 THROUGH 8.0
TOTAL AMOUNT FOR SECTION 1.0 - ASBESTOS SURVEY AND REPORT$0.00

TOTAL AMOUNT FOR SECTION 2.0 - OPERATION AND MAINTENANCE PLAN $0.00

TOTAL AMOUNT FOR SECTION 3.0 - ASBESTOS AIRBORNE FIBER $0.00

TOTAL AMOUNT FOR SECTION 4.0 - OPERATIONS AND MAINTENANCE IMPLEMENTATION $0.00

TOTAL AMOUNT FOR SECTION 5.0 - ABATEMENT SPECIFICATIONS $0.00

TOTAL AMOUNT FOR SECTION 6.0 - AGREEMENT ADMINSTRATION $0.00

TOTAL AMOUNT FOR SECTION 7.0 - ASBESTOS ABATEMENT $0.00

TOTAL AMOUNT FOR SECTION 8.0 - FINAL CLEARANCE REPORTS $0.00

SECTIONS 1.0 THROUGH 8.0 - GRAND TOTAL AMOUNT FOR ASBESTOS CONSULTING SERVICES AND ASSOCIATED WORK $0.00

IMPORTANT NOTE:

Unless otherwise allowed for and authorized in the Letter of Authorization all the above unit costs shown include overhead, labor, travel, administrative expenses, materials, equipment, profit, insurance, bonding and all other incidentals required for the work described in the Contractor's unit price.

No set volume of work is intended to be guaranteed and the estimated quantities above are shown for purposes of determining the GRAND TOTAL. Low bidder will be determined by the "Grand Total" bid amount.Bidders MUST enter the grand total as a total dollar amount, otherwise the Propsal will be considered non-responsive.

If the actual quantities during the agreement period are less than or greater than what it is identified, the unit rates shall remain unchanged. Compensation shall be at the unit rates set forth above as proposed by the Contractor.

The Department and the Contractor shall negotiate any item of work not included in this bid sheet as they are identified for each individual job assignment. Additional Line Items will be added/amended to Contract/Agreement on a "As Needed Basis" per Job/Project.

If any items are left blank, the bid shall be considered as non-responsive. “Contractor shall be responsible for returning all eight (8) pages of the Exhibit “C”, Price Proposal, and ensuring the entire eight (8) pages are legible in the one (01) PDF format in which it was submitted.” This ensure it is their responsibility to make sure they test drive the attachment so that they show properly otherwise the "Price Propsal" will be considered non-responsive.

THE " GRAND TOTAL" PRICE IS NOT TO BE CONSIDERED THE CONTRACT AMOUNT.

Page-&P &"Calibri,Regular"&8

Sheet1 image1.jpeg

File details come from the government source that posted it. Updated .