This file is Exhibit C, a key dates timeline document for the Georgia World Congress Center Authority's Signa Hilton Atlanta hotel project. The document outlines the critical milestones and occupancy dates for the 2023 opening of the hotel, coordinating activities across multiple construction and installation phases. The schedule begins with hotel procurement processes in April 2021 and extends through the pre-opening inspection scheduled for November 23, 2023 (T-15 days before the opening date of approximately December 8, 2023). The timeline encompasses procurement, installation, and commissioning of owner-furnished furniture, fixtures, and equipment (FF&E), along with operational systems setup. Key installation phases are staggered across guest room levels, with individual floor turnovers beginning in August 2023 and continuing through October 2023. Critical operational milestones include kitchen availability by October 6, 2023, restaurant and bar stockings by November 10, 2023, and completion of elevators, signage, fitness center, and swimming pool by November 22, 2023. All construction must be 100 percent complete with pre-opening documents including certificate of occupancy/temporary certificate of occupancy, completion photographs, and ADA certification delivered by November 17, 2023.

The document establishes a comprehensive phased approach to hotel opening preparation, with specific attention to operational readiness and team member accommodation during the construction-to-operations transition. Notable sequencing includes the early availability of back-of-house areas such as the loading dock (July 21, 2023) and engineering shop (August 4, 2023) to support ongoing construction and equipment distribution, followed by guest-facing area preparation. The timeline coordinates security office availability, IT infrastructure setup, and office occupancy to support pre-opening staffing needs. All dates are measured in days and weeks prior to the occupancy date, with the pre-opening inspection designated as the critical trigger for final approval and opening team mobilization. No pricing, funding sources, set-asides, or contract award information is contained in this exhibit.

Text of this file

GWCCA Signa Hilton Atlanta - Key Dates (T- Refers to amount of Days in advance of Open Date)

Area Detail & Comments T-Days T-Wks

Occupancy

Date

Model Room Start Hotel Procurement Process -967 -138 4/15/2021

OS&E Procurement Start Hotel Procurement Process -560 -80 5/27/2022

FF&E Procurement Start Hotel Procurement Process -560 -80 5/27/2022

AV, Security & Equipment Start Hotel Procurement Process -604 -86 4/13/2022

Security Start Install of Owner Furnished FF&E -506 -72 7/20/2022

AV Equipment Start Install of Owner Furnished FF&E -506 -72 7/20/2022

IT equipment Start Install of Owner Furnished FF&E -506 -72 7/20/2022

OS&E Start Install of Owner Furnished FF&E -506 -72 7/20/2022

Podium Start Install of Owner Furnished FF&E -506 -72 7/20/2022

Kitchen Equipment Start Install of Owner Furnished FF&E -330 -47 1/12/2023

Lobby Art Install Start Install of Owner Furnished FF&E -283 -40 2/28/2023

Commissioning Start Commission Process -276 -39 3/7/2023

Guest Room Tower Start Install of Owner Furnished FF&E -262 -37 3/21/2023

Levels 06-14 Start Install of Owner Furnished FF&E -262 -37 3/21/2023

Levels 15-22 Start Install of Owner Furnished FF&E -231 -33 4/21/2023

Levels 23-30 Start Install of Owner Furnished FF&E -199 -28 5/23/2023

Levels 31-38 Start Install of Owner Furnished FF&E -169 -24 6/22/2023

Guestroom Corridors Ice Machines (Rough-in Info) -438 -63 9/26/2022

Guestrooms Lighting (Hardwired) -438 -63 9/26/2022

Guestrooms Carpet and Wall Covering -380 -54 11/23/2022

Pubic Area Lighting (Hardwired) -368 -53 12/5/2022

Guestrooms Built -in Case Goods and Vanities -364 -52 12/9/2022

Function Areas (Banquet & Meeting

Rooms) Wall Covering Finish

-361 -52 12/12/2022

Guestroom Corridors Carpet and Wall Covering -357 -51 12/16/2022

Public Restrooms (incl. Pool

Washrooms) Decorative & Custom Lighting

-332 -47 1/10/2023

Public Restrooms (incl. Pool

Washrooms) Wall Covering Finish

-332 -47 1/10/2023

Public Restrooms (incl. Pool

Washrooms) Framed Mirrors

-332 -47 1/10/2023

Back-of-House (General) Decorative and Hardwired Lighting (Hardwired) -283 -40 2/28/2023

Back-of-House (General) Carpet and Wall Covering -283 -40 2/28/2023

Guestroom Corridors Lighting (Hardwired) -270 -39 3/13/2023

Pubic Area Carpet and Wall Covering -233 -33 4/19/2023

Kitchen & Pantry Equipment Podium -216 -31 5/6/2023

Reception Safety Deposit Boxes -199 -28 5/23/2023

Laundry Work Tables -196 -28 5/26/2023

Laundry Shelving and Racks -196 -28 5/26/2023

Fitness Center & Pool Decorative and Hardwired Lighting (Hardwired) -192 -27 5/30/2023

Fitness Center & Pool Carpet and Wall Covering -192 -27 5/30/2023

Function Areas (Banquet & Meeting

Rooms) Movable (Other Equipment)

-186 -27 6/5/2023

Pantry Equipment (Glass Washing &

ICE Machine) Tower

-166 -24 6/25/2023

Hilton Operations Occupation Target Times

Loading Dock

Loading Dock available to be shared with Operations for beginning of acceptance of OSE for on-property storage and distribution -140 -20 7/21/2023

Meeting Rooms Available for temporary OSE storage and distribution -126 -18 8/4/2023

Computer Room, MDF, IDF, DAS Required to support office occupancy -126 -18 8/4/2023

HR & Security Offices Available for beginning discipline processed and actual security of the property -126 -18 8/4/2023

Owner Furnished Contractor Installed FF&E

Owner Purchased Owner Installed FF&E

Start Owner Furnished FF&E Procurement Process richard.currier Text Box Exhibit C

Area Detail & Comments T-Days T-Wks

Occupancy

Date

Engineering Shop Area is available for occupation and product storage.

-126 -18 8/4/2023

Service Elevators Shared use to support guestroom setup -112 -16 8/18/2023

Guestroom Turnover

Level 10 - 6 guestrooms punch listing and correction completed and turnover to operations for OSE outfitting -112 -16 8/18/2023

Guestroom Turnover

Level 15 - 11 guestrooms punch listing and correction completed and turnover to operations for OSE outfitting -98 -14 9/1/2023

Guestroom Turnover

Level 19 - 16 guestrooms punch listing and correction completed and turnover to operations for OSE outfitting -84 -12 9/15/2023

Executive & Sales Offices

Offices available for Team Member occupation under

TCO as PO Offices have been outgrown. FFE must have completed installation by this time.

-77 -11 9/22/2023

Guestroom Turnover

Level 23 - 20 guestrooms punch listing and correction completed and turnover to operations for OSE outfitting -70 -10 9/29/2023

Kitchens Main Kitchen, Banquet Kitchen, R/S, & outlet kitchen -63 -9 10/6/2023

Meeting Rooms Available for set up of OnQ and POS Lab for training -63 -9 10/6/2023

BOH Front Desk Available for Staffing with FFE in Place -63 -9 10/6/2023

Guestroom Turnover Level 27 - 24 guestrooms punch listing and correction completed ad turnover to Operations for OSE outfitting -56 -8 10/13/2023

Banquet Storage Rooms Available for storage of banquet furniture that will be delivered to dock -56 -8 10/13/2023

Kitchen and China Storage Rooms Available for storage of OSE as delivered to dock -49 -7 10/20/2023

Guestroom Turnover

Level 31 - 28 Guestrooms punch listing and correction completed and turnover to operations for OSE outfitting -42 -6 10/27/2023

Employee Café Available for set up and beverage services -35 -5 11/3/2023

Food Service Pantries Available for stocking -35 -5 11/3/2023

Employee Locker Rooms Available for assignment and stocking -35 -5 11/3/2023

Guestroom Turnover

Level 35 - 32 Guestrooms punch listing and correction completed and turnover to operations for OSE outfitting -28 -4 11/10/2023

Market Café Available for occupation with all FFE, racking and shelving in place -28 -4 11/10/2023

ADD Restaurant Available for stocking and training -28 -4 11/10/2023

Lobby Bar/Destination Bar Available for stocking and training -28 -4 11/10/2023

Front Desk Area Available for stocking and training -28 -4 11/10/2023

Pre-opening Documents

Deliver the following to Hilton - CO/TCO allowing full use and occupancy - pre-opening photos of all spaces confirming completion - ADA certificate signed by architect -21 -3 11/17/2023

Beverage Storage Room Available for stocking of products -21 -3 11/17/2023

Guest Elevators Complete and operational -16 *2 11/22/2023

Signage Complete and operational -16 *2 11/22/2023

Fitness Available for equipment installation -16 *2 11/22/2023

Swimming Pool Available for water testing and treatment -16 *2 11/22/2023

Exterior landscape & amenities Complete with all construction barriers and storage removed -16 *2 11/22/2023

Guestroom Turnover

Level 38 - 35 Guestrooms punch listing and correction completed and turnover to operations for OSE outfitting -16 *2 11/22/2023

Area Detail & Comments T-Days T-Wks

Occupancy

Date

TS Pre-opening inspection

Property must be 100% complete with construction.

Operational setup & Training will be ongoing. Date is tentative until pre-opening documents are received.

This inspection triggers approval for the opening team

(Implementation, QA, & BPS) to make travel arrangements and move forward with the forecast opening date. Pre-opening inspection must occur 15 days prior to opening to allow time for the openings team to complete their work.

-15 -2 11/23/2023

* Items are coordinated with go/no go pre-opening inspection at T- 15 days.

Other files

File Type Posted
Addendum Two —
RFP Distributed Antenna System —
Addendum One —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .