On-Call Construction Management Services
Solicitation number
RFP-TH-0118
Issued by
Los Angeles County, California

About this file

This document is Exhibit B of a Request for Proposals issued by West Basin Municipal Water District in California for On-Call Construction Management Services. The exhibit provides a non-exhaustive list of potential projects that may be performed under the contract over a four-year period. The projects are categorized by facility location and include work at five primary sites: Chevron Nitrification Treatment Plant (CNTP), Edward C. Little Water Recycling Facility (ECLWRF), Hyperion Secondary Effluent Pumping Station, Juanita Millender-McDonald Carson Regional Water Recycling Plant (JMMCRWRP), and Torrance Regional Water Recycling Plant (TRWRP). Projects span capital improvements, rehabilitation and replacement activities, and operations support across water treatment infrastructure, including equipment replacements, system upgrades, chemical storage improvements, and pipeline work. Multi-plant and pipeline projects are also identified, encompassing chemical containment, customer service pipelines and laterals, distribution facilities, and SCADA systems.

The construction management services requested include project management, safety management, contract administration, document control, change management, inspection services, quality assurance and control, schedule management, materials testing, labor compliance, constructability reviews, and cost estimating. The specific project list is presented for reference purposes and represents examples of work that may be assigned; the actual projects to be performed and their scope will be determined on an as-needed basis through the on-call contract term. No pricing information, specific funding amounts, award dates, or contract term details are provided in this exhibit.

View the file

Other files

File Type Posted
On-Call_Construction_Management_Services_(Addendum_#1_Revision).pdf PDF
On-Call_Construction_Management_Services.pdf PDF
Vendor_Information_Request_Form_.pdf PDF
Vendor_Information_Request_Form_.pdf PDF
EXHIBIT_A_Scope_of_Services_CM_Final.pdf PDF
EXHIBIT_A_Scope_of_Services_CM_Final.pdf PDF
Exhibit_B_Project_list_CM-final.pdf PDF
Form_1_-_Engineering_Service_-_102618.docx DOCX document
Form_3_-_Pro-Svc_Non-Tech_-_102618.docx DOCX document
Sample_Agreement_-_Form_7_-_General_Services.docx DOCX document
Sample_Agreement_-_Form_9_-_Supply.docx DOCX document
Sample_Agreement_-_Form_7_-_General_Services.docx DOCX document
Sample_Agreement_-_Form_9_-_Supply.docx DOCX document
Form_3_-_Pro-Svc_Non-Tech_-_102618.docx DOCX document
Form_1_-_Engineering_Service_-_102618.docx DOCX document
Sample_Agreement_-_Form_8_-_Transportation_Services.docx DOCX document
Sample_Agreement_-_Form_5_-_On-Call_Engineering_Service.docx DOCX document
Sample_Agreement_-_Form_4_-_Non-Pro_Consultant.docx DOCX document
Sample_Agreement_-_Form_8_-_Transportation_Services.docx DOCX document
Sample_Agreement_-_Form_5_-_On-Call_Engineering_Service.docx DOCX document
Sample_Agreement_-_Form_4_-_Non-Pro_Consultant.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

West Basin Municipal Water District On-Call CM Services RFP

EXHIBIT B: POTENTIAL PROJECT LIST

This exhibit contains a non-exhaustive list of potential projects that may fall under this contract over the next 4 years. These projects have been categorized according to the location of work.

Addresses for each site listed below can be obtained from West Basin Municipal Water District.

CHEVRON NITRIFICATION TREATMENT PLANT (CNTP)

- Chevron Nitrification Tank

- CNTP DCS Replacement Project

- CNTP Bulk Chemical Storage

EDWARD C. LITTLE WATER RECYCLING FACILITY (ECLWRF)

- ECLWRF Title 22 Filters R&R Project

- DCS Replacement Project

- ECLWRF Barrier Basin & Pump Station R&R

- ECLWRF Reverse Osmosis Pre-Treatment System R&R

- ECLWRF Reverse Osmosis Post Treatment and Distribution

- ECLWRF Reverse Osmosis Treatment

- ECLWRF Bulk Chemical Storage Improvements

- ECLWRF Title 22 Isolation Valve replacement

- ECLWRF Title 22 Ozone System Improvement

- ECLWRF Disinfected Tertiary Product Pumps & VFDs Rehabilitation

HYPERION SECONDARY EFFLUENT PUMPING STATION

- Hyperion Force Main

- Hyperion Pump Station R&R Project

JUANITA MILLENDER-MCDONALD CARSON REGIONAL WATER RECYCLING PLANT

(JMMCRWRP)

- JMMCRWRP Bulk Chemical Storage Improvements

- JMMCRWRP Site Improvements Project

TORRANCE REGIONAL WATER RECYCLING PLANT (TRWRP)

- TRWRP Boiler feed Potable Water Backup

- TRWRP PLCs - DCS Replacement Project

- TRWRP Bulk Chemical Storage Improvements

- TRWRP Nitrification Tank R&R

- TRWRF MF Replacement Project

- TRWRF Waste Discharge Improvements

- TRWRF Fiberglass Pipe Replacement

- TRWRF 93MCC 2 Replacement

- TRWRF Sulfuric Acid Day Tank Chemical Containment

MULTI-PLANT AND PIPELINE PROJECTS

- Chemical Containment R&R Project (All Satellite Sites)

West Basin Municipal Water District On-Call CM Services RFP

- Customer Service Pipelines & Laterals

- Distribution Facilities – SCADA Project

File details come from the government source that posted it. Updated .