Exhibit B_Greenhouse_Project Manual.pdf
PDF 470 KB Posted
- Attached to
- City Greenhouse Structural Repairs and Re-siding
- Solicitation number
- IFB-PRL-25-571
- Issued by
- Adams County, Weston CDP, Colorado
About this file
This project manual is for the Briggs Greenhouse Improvements project for the City of Westminster, located in Westminster, Colorado. The document outlines a comprehensive renovation project that includes multiple construction and improvement tasks, such as removing and replacing downspouts, concrete removal, helical pier and cap construction, structure steel replacement, removing and replacing siding and roof, and various miscellaneous work. The project is scheduled to be completed by November 14, 2025, with construction to be performed according to detailed specifications and drawings.
The contract is structured with multiple bid items, including mobilization (limited to 10% of the total base bid amount), erosion control, site restoration, traffic and pedestrian control, and specific replacement tasks such as industrial downspouts, structural components, and various glazing materials. The project will require detailed submittals, strict adherence to City of Westminster standards and specifications, and careful coordination with city personnel. Contractor responsibilities include maintaining public access, protecting existing utilities and landscaping, managing work hours, and implementing comprehensive erosion and sediment control measures. The project manual provides extensive technical specifications for site preparation, concrete work, and other construction activities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Briggs Greenhouse Improvements_IFB-PRL-25-571 Final.pdf | ||
| Exhibit A_Construction Services Contract.docx | DOCX document | |
| Exhibit D_Greenhouse Bid Sheet.pdf | ||
| Exhibit C_Project Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ISSUED FOR BID
PROJECT MANUAL
BRIGGS GREENHOUSE IMPROVEMENTS
February 2025
PREPARED FOR:
4800 WEST 92ND AVENUE
WESTMINSTER, CO 80031
PREPARED BY:
305 DENVER AVENUE – SUITE D
FORT LUPTON, CO 80621
PHONE: 303-857-6222
FAX: 303-857-6224
City of Westminster Table of Contents Briggs Greenhouse Improvements
TABLE OF CONTENTS
TECHNICAL SPECIFICATIONS
SECTION TITLE PAGE
01010 Summary of Work 01010 01200 Measurement and Payment 01200 01300 Submittals 01300 01310 Schedules 01310 01720 Project Record Documents 01720 02100 Site Preparation 02100 02140 Dewatering and Drainage 02140 02200 Earthwork 02200 02210 Site Grading 02210 02221 Trenching, Backfilling and Compaction 02221 02270 Erosion Control 02270 02632 RCP Pipe 02632 02740 Flexible Pavement 02740 02910 Topsoil 02910 02924a Open Space Revegetation 02924 03301 Cast-In-Place Concrete, Sidewalk, Curb, and Gutter 03301
Exhibit C
01000-1
City of Westminster Special Conditions Briggs Greenhouse Improvements
REQUEST FOR BIDS
SPECIAL CONDITIONS TO THE CONSTRUCTION CONTRACT
PART 1 GENERAL
1.01 PROJECT SIGNS – Not used
1.02 EXISTING CONDITIONS
The bidder represents that he has carefully examined the contract documents and the site where the work is to be performed in accordance with the provisions of the General Conditions, and that he has familiarized himself with all local conditions and federal, state, and local laws, ordinances, rules, and regulations that may affect the performance of the work. The bidder further represents that he has studied all documents pertaining to the job site, that he has performed such additional surveys and investigations as he deems necessary to assure himself of his ability to complete the work at this bid price, and that he has correlated the results of all such data with the requirements of the contract documents.
The submittal of a bid shall be conclusive evidence that the bidder has investigated and is satisfied as to the conditions to be encountered, including locality, uncertainty of weather and all other contingencies, and as to the character, quality quantities, and scope of work.
The plans and specifications for the work show subsurface conditions or otherwise hidden conditions as they might be expected to exist; but it is not intended nor is it to be inferred that showing said conditions constitute a representation that such conditions are accurate or complete.
Where the City or the Engineer or their consultants have made investigations of subsurface conditions in areas where the work is to be performed, such investigations were made only for the purpose of study and design. The conditions indicated by such investigations apply only at the specific location of each boring or excavation at the time the borings or excavations were made.
Where such investigations have been made, bidders or Contractors may inspect the records as to such investigations subject to the above limitations. The record of such investigations is not a part of the contract and is provided solely for the convenience of the bidder or Contractor.
No information derived from such inspection of records of investigation or compilation thereof made by the City, the Engineer, or their consultant will in any way relieve the bidder or Contractor from any risk or from properly fulfilling the terms of the contract nor entitle the Contractor to any additional compensation.
Excavated soils which are excessively wet as determined by soil sampling and testing should be dried prior to being used in the backfill operation, or at the Contractor’s option, be replaced with suitable backfill material from other areas of the project at no additional cost to the City. Also, excavated soils containing debris, rubble, organic, and deleterious substances are not acceptable for use as backfill and shall be disposed of properly by the Contractor at no cost to the City.
1.03 MOBILIZATION
The Contractor shall limit storage equipment and supplies and remain within the staging areas shown on the Drawings or as otherwise approved by the City or acquired by the Contractor.
01000-2
City of Westminster Special Conditions Briggs Greenhouse Improvements
The Contractor shall supply portable sanitary facilities for the site.
Prior to mobilization, the Contractor shall document existing condition of site using photos and/or videos.
The contractor shall obtain all necessary permits.
1.04 MATERIALS TESTING
The City of Westminster will provide testing services for backfill compaction, concrete and asphalt testing.
The Contractor shall be responsible for coordinating testing. The Contractor shall give the testing service 24-hours notice for testing. The testing service reserves the right to reject any request for testing with less than 24-hours notice. The Contractor agrees to pay for all retesting due to failed tests at no cost to the Owner.
1.05 SURVEYING
The Contractor shall obtain and pay for surveying services for the staking of the project. The surveyor employed will be a Colorado Registered Licensed Surveyor and have the expertise to perform such services. All costs associated with surveying shall be included in the price of the project.
1.06 CONTRACTOR’S WORK HOURS
CONTRACTOR (and Subcontractor) regular working hours consist of up to 10 working hours between 7:00 a.m. and 5:00 p.m., on a regularly scheduled basis, excluding Saturdays, Sundays, and holidays. Under special circumstances an exception may be made for evening and weekend work if pre-approved by the City. Contractor needs to be aware of the concerns with local businesses and homes and accommodate local traffic and pedestrians. Contractor also needs to be aware of dust abatement and daily cleanup of trash.
1.07 CONNECTIONS TO EXISTING PIPE SYSTEMS
It shall be the Contractor’s responsibility to verify the location of all existing valves and pipe systems, prior to the start of construction; and also verify the horizontal and vertical locations of all other utilities, sewers or water lines that may be affected by work.
1.08 MAINTENANCE OF PUBLIC ACCESS TO LOCAL BUSINESS
Street access to residences and businesses in the vicinity of the construction shall be maintained by the Contractor during the work. At least one 12-foot wide lane in each direction shall be maintained at all times for local traffic and emergency vehicle access unless the road is specifically noted to be closed on the attached contract drawings. Flagged one lane two-way traffic will be allowed during construction hours if necessary and approved by the City.
A minimum of 2” inches of Asphalt millings or Asphalt cold patch must be provided on all trench patch sections prior to reopening the lane to traffic. This temporary pavement patch must be removed prior to final pavement patching.
1.09 COORDINATION AND NOTIFICATION OF SERVICE DISRUPTION (NOT USED)
01000-3
City of Westminster Special Conditions Briggs Greenhouse Improvements
1.10 COMMUNICATION WITH THE PUBLIC
The City will send out letters to the impacted residences, businesses regarding the construction.
The City will also provide door hangers for the Contractor to use to notify residents immediately impacted by the work. The Contractor should plan on continuous communication with residents regarding work schedule for the duration of the project. The Engineer will help facilitate the efforts, but his responsibilities are not a substitute for an adequate communication plan and implementation of that plan by the Contractor.
1.11 COORDINATION WITH CITY STAFF
City PR&L Department personnel are familiar with the project and the system, and are a valuable resource for information. However, they have many responsibilities, are not available at all times, and individuals may not have all the information available that is needed to make a field decision.
The Contractor will only receive direction in the field from the Engineer and/or the City Project Manager.
1.12 CONSTRUCTION PHASING AND SCHEDULING (NOT USED)
1.13 LOCATING AND MARKING EXISTING UTILITIES
The Contractor shall have all existing utilities marked prior to construction and verify their location. Existing utility information shown on the Drawings has been confirmed by only limited locate and potholing data, and may not reflect the exact position of existing utilities, and may not show all the utility lines present.
The City will mark City-owned utilities, but other utilities will need to be located. Coordinate utility locates through the Utility Notification Center of Colorado, call 811.
City-located utilities will be marked only one time. The Contractor shall be responsible for maintaining the locate marks. The Contractor must request locates of City-owned utilities periodically as the work progresses rather than as a single event. Requests for locates shall not precede the construction activity in any given area by more than 2 weeks.
Utility potholing for location of existing utilities is required. All potholing must be completed and the information provided to the Project Engineer prior to installing any pipe.
1.14 CONSTRUCTION MATERIAL STOCKPILE REQUIREMENTS
Construction stockpiles for earth, bedding materials and pipe materials should be placed in designated areas. Contractor shall coordinate and review stockpiling with the City prior to the work.
Excavated material and imported backfill material that is not scheduled to be placed as backfill within two days shall be moved to a permanent stockpile location. Stockpiles shall not block the gutter flowline. Measures to control migration of sediment from stockpiles should be put in place, especially if left overnight or over a weekend or other breaks in the work.
Manhole riser and cone sections, manhole frames and covers, pipe fittings and valves should not be stored in the work area, but should be stored in a designated area until the day they are to be installed.
01000-4
City of Westminster Special Conditions Briggs Greenhouse Improvements
1.15 CONSTRUCTION EQUIPMENT
The City has expressed the need to maintain the condition of the existing pavement and concrete infrastructure outside the project work areas, and along equipment and material haul routes. The use of appropriate construction equipment that is adequate to complete the required work for this project while minimizing pavement and concrete damage outside the defined work areas shall be required. The Contractor shall be held responsible for damages outside the defined work areas created by his activities.
1.16 PROTECTION OF EXISTING UTILITIES
Existing utilities that are not scheduled for replacement, removal or relocation shall be protected to avoid disruption of service. Adequate shoring, bracing and blocking shall be put in place to avoid damage or shifting of the utility lines and trench materials. All repairs required due to the work of the Contractor shall be the responsibility of the Contractor.
1.17 OPERATING EXISTING VALVES AND HYDRANTS
Existing valves and hydrants are to be operated by City personnel only. If the area is under new construction and the new equipment is not connected to the active system, a contractor can operate fire hydrants or valves after the City’s Field Operations has witnessed their means and methods.
Coordinate with City personnel and the Engineer when operating any new valve.
1.18 CONSTRUCTION WATER
Use of a fire hydrant to supply construction water will require the Contractor to pay the Temporary Fire Hydrant Meter Lease fee for renting a meter and backflow preventer from the City. Water usage is applied to the fee paid, with any balance to be refunded when the meter and backflow preventer are returned. Construction water from the City may not be obtained from an unmetered source.
1.19 PROTECTION OF EXISTING LANDSCAPING
Existing landscaping in the vicinity of the work areas shall be protected from damage, including lawns, shrubs and trees. Landscaping that interferes with the work may be removed after approval from the City and must be replaced in a manner satisfactory to the City and the Engineer.
Damaged landscaping shall be replaced in-kind at the expense of the Contractor.
1.20 END OF WORKDAY SITE CONDITIONS
Pipe trenches shall be backfilled to within a maximum of five (5) feet from the end of the pipe at the end of each work day. A solid traffic-duty cover shall be placed over any open trench.
Trenches in streets shall be resurfaced with two (2) inches of asphalt millings or cold patch pavement immediately upon completion of the pipe backfilling and the area opened to traffic if permanent patching cannot be done immediately.
Areas where there is active work and/or stockpiles placed shall be swept daily at the end of the work shift.
All backfilled and stabilized trenches shall be checked daily and repaired as required by the Engineer.
01000-5
City of Westminster Special Conditions Briggs Greenhouse Improvements
Contractor shall provide ADA access.
1.21 INSURANCE REQUIREMENTS
Additional Insured. Add the following new paragraph immediately after Paragraph 11.2.1:
11.2.2 In regard to commercial general liability, comprehensive automobile liability, and umbrella liability, the certificates of insurance shall also name the Engineer as listed in the Contract Documents, as additional insured. Contractor shall deliver copies of the certificates of insurance to each additional insured.
Builder’s Risk/Property Insurance. Add the following new paragraph immediately after Paragraph 11.3.1.2:
11.3.1.3 In regard to builder’s risk/property insurance, the certificates of insurance shall also name the Engineer as listed in the Contract Documents, as additional insured. Contractor shall deliver copies of the certificates of insurance to each additional insured.
General Requirements. Add the following new sub-paragraph immediately after Paragraph 11.4.2.4:
11.4.2.5 With respect to worker’s compensation and employer’s liability, commercial general liability, comprehensive automobile liability, umbrella liability, Owner’s protective liability, and all other liability insurance required by the Contract Documents to be provided by Contractor, Contractor shall require the insurance carriers to waive all rights of subrogation against Engineer, and their respective officers, directors, partners, employees, and agents.
1.22
1.23
PROJECT SCHEDULE
Construction shall be completed by November 14, 2025.
WORK CONSTRAINTS AND RESTRICTIONS
1. Work Requiring City PR&L Operation Field Staff
a. The terms City PR&L Staff, Operations Staff, and Field Staff are used interchangeably.
b. City PR&L Department personnel are familiar with the project and the system, and are a valuable source for information. However, they have many responsibilities, are not available at all times, and an individual may not have all the information needed to make a field decision. The Contractor shall receive direction in the field from the Engineer and/or the City Project Manager only.
c. Contractor is responsible to stage and schedule their work such that City PR&L staff are not required on Fridays. The contractor’s bid and schedule must account for this constraint.
d. Special circumstances happen during construction. The City may allow one special circumstance event per month where City Staff will provide assistance on a Friday.
The City reserves the right to reject any and all special circumstance requests and is the sole decision-maker as to what constitutes special circumstances.
01000-6
City of Westminster Special Conditions Briggs Greenhouse Improvements
i. Friday work requiring City Staff in excess of one per month shall be billed to the Contractor at a rate of $500 per event.
ii. Weather will not be a justification for special circumstances.
iii. All Friday work requires prior written approval from the City at least 48 hours in advance of the work requested.
iv. All requests for Friday work must utilize the communication path set in place for the project via the City Project Manager or their designee. The contractor shall not call City Operations staff directly.
e. Examples of work that require City Utility Staff
i. Only Utility Operations Staff are to isolate and release pressure off main/load lines and/or flush and remove any turbid water or air. (Contractors are not to operate city owned valves or fire hydrants for flushing of clear waters or valves connected to the city water supply). An exception to this is the special case where a hydrant is used with an approved back flow prevention device, and that assembly is inspected and approved by the City. Under this special case, the contractor is permitted to operate the hydrant.
ii. Shut downs and loading of lines
iii. Flushing for removal of chlorine
iv. All bacteria sampling
v. Setting up new bypass pumping operations
vi. City staff is not intended to continually oversee the installation of pipeline or other improvements being made.
f. City Staff is not responsible to monitor devices and dechlorinating during flushing of water mains. Refer to the disinfection specification for additional requirements.
g. Contractor is responsible to monitor devices and dechlorinating during all flushing.
h. Contractor shall not terminate flow to any device once Utility Operations Field Staff has started the flushing process. Under the unique circumstance where the Contractor is using City hydrants with City-inspected and approved hydrant meter and back flow preventer, the Contractor can start/stop the flow from the hydrant as needed without assistance from City staff.
i. City Staff must be notified of any flushing being performed and flushing equipment will be inspected and approved by City Staff.
j. If flushing into a sanitary manhole is required, written approval from the City is required at least one (1) week prior to the start of the work.
01000-7
City of Westminster Special Conditions Briggs Greenhouse Improvements
1.24 SALVAGED ITEMS (NOT USED)
1.25 PRE-SELECTED EQUIPMENT (NOT USED)
END OF SECTION
01010-1
City of Westminster Summary of Work Briggs Greenhouse Improvements
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. All work to be performed under this Contract is located at the areas shown on the attached drawings
1.02 DESCRIPTION OF WORK
A. The work of this Contract consists of furnishing all labor, materials, equipment, and incidentals required and performing all construction, installation, and testing of all improvements, modifications, and additions, as shown on the Drawings and specified in these specifications.
The work includes, but is not necessarily limited to: gutter and/or downspout removal and replacement, concrete removal, helical pier and cap construction, structure steel replacement, remove and replace siding and roof, miscellaneous work and cleanup. Major items of the work include the following as shown on the Contract Drawings:
Mobilization: This work shall include all labor, equipment, materials, and incidentals required to mobilize the Contractor's work forces to complete the Project. This Base Bid Item shall have a maximum cost of 10 percent of the total Base Bid Amount as shown on the Bid Form.
1.03 CONTRACTOR'S USE OF PREMISES
A. Contractor will not have complete and exclusive use of the premises for the performance of the work.
B. Contractor shall limit the use of the premises for his/her work and for storage to allow for through traffic and operation of existing facilities during construction. The Contractor shall keep in mind that the Owner will continue to operate the existing facilities throughout construction.
C. Contractor shall coordinate the use of the premises with the Owner. Areas requiring shutdown of the existing facilities shall be coordinated with the Owner 48 hours prior to taking those facilities out of service.
D. Contractor shall assume full responsibility for security of all his/her, and his/her subcontractor's, materials and equipment stored on the site.
E. Contractor, if directed by the Owner and/or Engineer, shall move any stored items that interfere with the operations of the Owner.
F. Contractor shall obtain and pay for use of additional storage if needed to perform the work.
01010-2
City of Westminster Summary of Work Briggs Greenhouse Improvements
1.04 OWNER OCCUPANCY
A. Owner will occupy premises during performance of the work for the conduct of his/her normal operations. Coordinate all construction operations with the Owner to minimize conflict and to facilitate Owner usage.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTIONS (NOT USED)
01200-1
City of Westminster Measurement and Payment Briggs Greenhouse Improvements
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.01 REQUIREMENTS INCLUDED
A. Measurement and payment shall be as specified in this Section.
B. Work to be performed under this contract will be paid for on a unit cost or lump sum basis under the appropriate unit cost or lump sum Bid Items shown on the Bid Form. No item of Work shown on the Drawings or in the Specifications will be considered for extra compensation due to a claim that it does not fall within the scope of one of the Bid items.
C. Contractor shall, within 10 days of receipt of Notice to Proceed, submit a complete breakdown of lump sum and unit cost bid items (Schedule of Values) showing value assigned to each part of Work. Payment for materials delivered but not fully incorporated in Work will be made only if such materials are listed and assigned a value in Contractor’s Schedule of Values.
D. The work of this Contract consists of furnishing all labor, materials, equipment and incidentals required and performing all construction, installation and testing of all improvements, modifications and additions, all as shown on the Drawings and as specified in these Specifications.
1.02 BID ITEMS
GENERAL CONSTRUCTION ITEMS
1. Project Mobilization/Demobilization/Bonds/Insurance Shall include all labor, materials, equipment, and incidentals required for the Contractor to mobilize. Shall include all costs for Contractor’s insurance and bonds, construction permits and fees, job trailers and site administration expenses, utilities including power, telephone, etc. This item shall not exceed more than ten (10) percent of the Base Bid. This item will be paid 50 percent of the total at 25 percent project completion, an additional 30 percent of the total at 50 percent project completion, and the remaining 20 percent of the total at 100 percent project completion.
2. Erosion Control Shall include all labor, materials, equipment, and incidentals required for construction.
3. Site Restoration Shall include all labor, materials, equipment, and incidentals required for construction.
4. Traffic and Pedestrian Control Shall include all labor, materials, equipment, and incidentals required for construction.
5. Remove existing downspouts as shown on plans, Complete in Place Shall include all labor, materials, equipment, and incidentals required for construction.
01200-2
City of Westminster Measurement and Payment Briggs Greenhouse Improvements
6. Metal Era Industrial Downspout, 4”x6”, 0.063” aluminum, open face front, with style 2 strap, Cityscape color, or approved equal, including all fittings and appurtenances, Complete in Place Shall include all labor, materials, equipment, and incidentals required for construction.
7. Underdrain, Complete in Place Shall include all labor, materials, equipment, and incidentals required for construction.
8. Remove existing concrete caissons, Complete in Place Shall include all labor, materials, equipment, and incidentals required for construction.
9. Helical Pier and Pier Cap, Complete in Place Shall include all labor, materials, equipment, and incidentals required for construction.
10. Column Repair, including removal of damaged column, splices, replacement stub column with base plate, and appurtenances to attach to the pier cap, Complete in Place Shall include all labor, materials, equipment, and incidentals required for construction.
11. Remove and replace 2x2 steel with 2x2 square steel tube, Complete in Place Shall include all labor, materials, equipment, and incidentals required for construction.
12. Remove existing Lexan and replace with 8mm LEXAN, UV Resistant, White, including all fasteners and appurtenances Shall include all labor, materials, equipment, and incidentals required for construction.
13. Remove existing Lexan and replace with 8mm LEXAN Thermoclear 15 Multiwall Polycarbonate, Clear, including all fasteners and appurtenances Shall include all labor, materials, equipment, and incidentals required for construction.
14. Remove existing DynaGlas and replace with DynaGlas SolarSoft corrugated Polycarbonate, Clear including all fasteners and appurtenances Shall include all labor, materials, equipment, and incidentals required for construction.
15. / 16. Unforeseen Item Shall include any additional work or scope the Contractor notes as necessary to meet project intent. These items will be considered by Owner and Engineeer at their discretion as add-alternates.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
01300-1
City of Westminster Submittals Briggs Greenhouse Improvements
SUBMITTALS
PART 1 GENERAL
1.01 DESCRIPTION OF REQUIREMENTS
A. This Section specifies the general methods and requirements of submissions applicable to the following work-related submittals: Shop drawings, product data, samples, construction or submittal schedules, and work plans as required under specific sections of the specifications.
Detailed submittal requirements will be specified in the Technical Specification sections.
Contractor shall submit a schedule of shop drawings and sample submittals in accordance with the Contract.
B. All submittals shall be clearly identified by reference to specification Section, paragraph, Drawing Number, or Detail, as applicable. Submittals shall be clear and legible and of sufficient size for adequate presentation of data.
1.02 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
A. Shop Drawings
1. Shop drawings, as specified in individual work sections include, but are not necessarily limited to, custom-prepared data such as fabrication and erection/installation (working) drawings, schedule information, setting diagrams, actual shop work manufacturing instructions, custom templates, special wiring diagrams, coordination drawings, individual system or equipment inspection, and test reports including performance curves, and certifications, as applicable to the Work.
2. All shop drawings submitted by subcontractors for approval shall be sent directly to the Contractor for checking. The Contractor shall be responsible for their submission at the proper time so as to prevent delays in delivery of materials.
3. The Contractor shall check all subcontractor's shop drawings regarding measurements, size of members, materials, and details to determine to the Contractor's satisfaction that they conform to the intent of the Drawings and specifications. Shop drawings found to be inaccurate or otherwise in error shall be returned to the subcontractors for correction before submission thereof.
4. All details on shop drawings submitted for approval shall show clearly the relation of the various parts to the main members and lines of the structure and where correct fabrication of the work depends upon field measurements, such measurements shall be made and noted on the Drawings before being submitted for approval.
B. Product Data
1. Product data, as specified in individual sections include, but are not necessarily limited to, standard prepared data for manufactured products (sometimes referred to as catalog data), such as the manufacturer's product specification and installation instructions, availability of colors and patterns, manufacturer's printed statements of compliance and applicability, 01300-2
Briggs Greenhouse Improvements roughing-in diagrams and templates, catalog cuts, product photographs, standard wiring diagrams, printed performance curves and operational-range diagrams, production or quality control inspection, test reports and certifications, mill reports, product operating and maintenance instructions, and recommended spare parts listings and printed product warranties, as applicable to the Work.
C. Samples
1. Samples specified in individual sections, include but are not necessarily limited to, physical examples of the work such as sections of manufactured or fabricated work, small cuts or containers of materials, complete units of repetitively-used products, color/texture/ pattern swatches and range sets, specimens for coordination of visual effect, graphic symbols and units of work to be used by the Engineer or Owner for independent inspection and testing, as applicable to the Work.
1.03 CONTRACTOR'S RESPONSIBILITIES
A. The Contractor shall review shop drawings, product data, and samples, including those by subcontractors, prior to submission to determine and verify the following:
1. Field measurements.
2. Field construction criteria.
3. Catalog numbers and similar data.
4. Conformance with the specifications.
B. Each shop drawing, sample, and product data submitted by the Contractor shall have affixed to it the following Certification of Statement including the Contractor's Company name and signed by the Contractor:
"Certification Statement: By this submittal, I hereby represent that I have determined and verified all field measurements, field construction criteria, materials, dimensions, catalog numbers, and similar data, and I have checked and coordinated each item with other applicable approved Shop Drawings and all Contract requirements."
Shop drawings and product data sheets 11-in x 17-in and smaller shall be bound together in an orderly fashion and bear the above Certification Statement on the cover sheet. The cover sheet shall fully describe the packaged data and include a listing of all items within the package.
Provide to the Resident Project Representative a copy of each submittal transmittal sheet for shop drawings, product data, and samples at the time of submittal of said drawings, product data, and samples to the Engineer.
D. Notify the Engineer in writing, at the time of submittal, of any deviations in the submittals from the requirements of the Contract Documents.
E. The review and approval of shop drawings, samples, or product data by the Engineer shall not relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms of
01300-3
Briggs Greenhouse Improvements the Contract. All risks of error and omission are assumed by the Contractor and the Engineer will have no responsibility therefore.
F. No portion of the work requiring a shop drawing, sample, or product data shall be started nor shall any materials be fabricated or installed prior to the approval or qualified approval of such item. Fabrication performed, materials purchased, or onsite construction accomplished that does not conform to approved shop drawings and data shall be at the Contractor's risk. The Owner will not be liable for any expense or delay due to corrections or remedies required to accomplish conformity.
G. Project work, materials, fabrication, and installation shall conform with approved shop drawings, applicable samples, and product data.
1.04 SUBMISSION REQUIREMENTS
A. Make submittals promptly in accordance with approved schedule and in such sequence as to cause no delay in the Work.
B. Each submittal, appropriately coded, will be returned within 7 working days following receipt of submittal by the Engineer.
C. Number of submittals required: (Note: electronic copies via email are preferred)
1. Shop drawings as defined in Paragraph 1.02A: four copies (minimum). Three copies will be retained by the Engineer and Owner after the review.
2. Product Data as defined in Paragraph 1.02B: four copies (minimum). Three copies will be retained by the Engineer and Owner.
3. Samples: Submit the number stated in the respective specifications Sections.
D. Submittals shall contain:
1. The date of submission and the dates of any previous submissions.
2. The project title and number.
3. Contractor identification.
4. The names of:
a. Contractor.
b. Supplier.
c. Manufacturer.
5. Identification of the product, with the specifications Section number, page, and paragraph(s).
01300-4
Briggs Greenhouse Improvements
6. Field dimensions, clearly identified as such.
7. Relation to adjacent or critical features of the Work or materials.
8. Applicable standards, such as ASTM or Federal Specification numbers.
9. Identification of deviations from Contract Documents.
10. Identification of revisions or resubmittals.
11. A blank space suitably sized for Contractor and Engineer stamps.
1.05 REVIEW OF SHOP DRAWINGS, PRODUCT DATA, WORKING DRAWINGS, AND
SAMPLES
A. The review of shop drawings, data, and samples will be for general conformance with the design concept and Contract Documents. They shall not be construed:
1. As permitting any departure from the Contract requirements.
2. As relieving the Contractor of responsibility for any errors, including details, dimensions, and materials.
3. As approving departures from details furnished by the Engineer, except as otherwise provided herein.
B. The Contractor remains responsible for details and accuracy for coordinating the work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly, and for performing work in a safe manner.
C. If the shop drawings, data, or samples as submitted describe variations and show a departure from the Contract requirements that Engineer finds to be in the interest of the Owner and to be so minor as not to involve a change in Contract Price or time for performance, the Engineer may return the reviewed drawings without noting an exception.
E. Resubmittals will be handled in the same manner as first submittals. On resubmittals, the Contractor shall direct specific attention, in writing on the letter of transmittal and on resubmitted shop drawings, by use of revision triangles or other similar methods, to revisions other than the corrections requested by the Engineer, on previous submissions. Any such revisions that are not clearly identified shall be made at the risk of the Contractor. The Contractor shall make corrections to any work done because of this type of revision that is not in accordance to the Contract Documents as may be required by the Engineer.
F. Partial submittals may not be reviewed. The Engineer will be the only judge as to the completeness of a submittal. Submittals not complete will be returned to the Contractor and will be considered "Not Approved" until resubmitted. The Engineer may, at his/her option, provide a list or make the submittal directing the Contractor to the areas that are incomplete.
01300-5
Briggs Greenhouse Improvements
G. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, the Contractor shall give written notice thereof to the Engineer at least seven working days prior to release for manufacture.
H. When the shop drawings have been completed to the satisfaction of the Engineer, the Contractor shall carry out the construction in accordance therewith and shall make no further changes therein except upon written instructions from the Engineer.
1.06 DISTRIBUTION
A. Distribute reproductions of approved shop drawings and copies of approved product data and samples, where required, to the job site file and elsewhere as directed by the Engineer. Number of copies shall be directed by the Engineer but shall not exceed six.
1.07 SCHEDULES
A. Provide all schedules required by Section 01310.
1.08 GENERAL PROCEDURES FOR SUBMITTALS
A. Coordination of Submittal Times: Prepare and transmit each submittal sufficiently in advance of performing the related work or other applicable activities, or within the time specified in the individual work sections of the specifications, so that the installation will not be delayed by processing times, including disapproval and resubmittal (if required), coordination with other submittals, testing, purchasing, fabrication, delivery, and similar sequenced activities. No extension of time will be authorized because of the Contractor's failure to transmit submittals sufficiently in advance of the Work.
PART 2 PRODUCTS (NOT USED)
01310-1
City of Westminster Construction Schedules Briggs Greenhouse Improvements
CONSTRUCTION SCHEDULES
PART 1 GENERAL
1.01 CONTRACTOR REQUIREMENTS INCLUDED
A. The Contractor shall submit his/her proposed Schedule of Work in accordance with the provisions and time frames stated in this Section and in the Contract. Three copies of all Schedules and Schedule updates shall be submitted initially and monthly thereafter.
C. Contractor shall submit updated Schedule of Work monthly or more frequently when required and acceptable to the Engineer. Progress payment shall not be made unless the Contractor submits the monthly schedule update.
D. Contractor's Schedule is to be considered and used as a working tool, and will not become part of Contract or Contract Documents.
1.02 RELATED REQUIREMENTS
A. Conditions of Contract
B. Section 01010: Summary of Work
C. Section 01300: Submittals
1.03 FORM OF SCHEDULES
A. The Schedule of Work shall utilize a Critical Path Method (CPM). Contractor shall prepare, maintain, and furnish current detailed progress and schedule charts using the CPM schedule, which shall support the Contract performance dates. Schedule shall identify Work in Contract in sufficient detail to ensure compliance with Contract dates, schedules, and sequences of construction.
B. CPM schedule shall be maintained throughout life of Contract. Contractor shall designate an authorized representative within its firm who will be responsible for preparation of the CPM network plan and schedule and for monitoring progress of Project.
1. Schedule submittal: In accordance with the Contract. Contractor shall submit to the Engineer complete CPM. A schedule of estimated monthly progress payments shall be developed by Contractor and submitted with CPM network plan. Contractor shall also submit Schedule of Values and schedule of Shop Drawings and sample submittals.
2. Acceptance of Contractor's Schedule by Engineer will not relieve Contractor from compliance with all conditions of the Contract. Errors and omissions in accepted Contractor's Schedule will not be cause for future claims by Contractor for extra costs or increased Contract Time.
01310-2
City of Westminster Construction Schedules Briggs Greenhouse Improvements
4. Schedule is Contractor's schedule, prepared by him and he remains solely responsible for adherence thereto.
5. Changes to Schedule: Contractor may at any time make changes to its current plan and schedule upon notification to Engineer. Contractor shall submit changes schedule for any of the following reasons:
a. When delay in completion of any activity or group of activities indicates an extension of scheduled Project completion including delays which may be involved with change orders, strikes, unusual weather, etc.
b. Delays in submittals or deliveries or work stoppage are encountered which make re-planning or rescheduling of Work necessary.
c. Schedule does not represent actual prosecution and progress of Project.
6. Engineer's acceptance of changes to Schedule and all relevant data is contingent upon compliance with all other paragraphs of this Section and any other previous agreements or requirements by Engineer.
7. Contractor's cost of revisions to Schedule due to any cause shall be responsibility of Contractor.
8. Adjustment of Contract Completion: Contract Time will be adjusted only by Change Order for causes specified in this Contract. In the event Contractor requests an extension of Contract Time, he shall furnish such justification, CPM data, and supporting evidence as follows for a determination as to whether or not Contractor is entitled to an extension of Time under provisions of Contract: all CPM logic revisions, duration changes, and cost changes for Work in question and its relationship to other activities on accepted, current network plan.
9. Contractor shall submit a brief narrative report as part of monthly update. Narrative report shall include a description of problem areas; current and anticipated delaying factors and their estimated impact on performance of other activities and completion dates; and an explanation of corrective action taken or proposed.
C. Contractor failure to comply with this Section shall be a material breach of this Contract.
PART 2 PRODUCTS (NOT USED)
01720-1
City of Westminster Project Record Documents
PROJECT RECORD DOCUMENTS
PART 1 GENERAL
1.01 REQUIREMENTS INCLUDED
A. Contractor shall maintain at Site for Owner:
1. One record copy of:
a. Specifications
b. Addenda
c. Change Orders and other Modifications to Agreement
d. Reviewed Shop Drawings and Samples
e. Field test records
2. One copy of Record Drawings, marked and updated after each working day. These documents shall only be used for recording as-built conditions and shall not be used for day-to-day construction coordination by the Contractor.
1.02 RELATED REQUIREMENTS
A. Section 01300: Submittals.
1.03 MAINTENANCE OF DOCUMENTS AND SAMPLES
A. Contractor shall maintain Documents in clean, dry, legible condition, and in good order. Do not use Record Documents for construction purposes.
B. Contractor shall make Documents available at all times for reference by Engineer or Owner.
1.04 RECORD DRAWINGS
A. Contractor shall record information concurrently with construction progress. Do not cover any Work until required information is recorded.
B. Drawings shall be legibly marked by Contractor to record actual construction.
C. Specifications and Addenda shall be legibly marked by Contractor to record:
1. Manufacturer, trade name, catalog number, and supplier of each product and item of equipment actually installed
2. Changes made by field order or by Change Order
01720-2
City of Westminster Project Record Documents
1.05 SUBMITTAL
A. At Agreement closeout, Contractor shall deliver Record Documents to Engineer for Owner.
B. Accompany submittal with transmittal letter in duplicate, containing:
1. Date
2. Project title and number
3. Contractor's name and address
4. Title and number of each Record Document
5. Signature of Contractor or its authorized representative
PART 2 PRODUCTS (NOT USED)
02100-1
City of Westminster Site Preparation
SITE PREPARATION
PART 1 GENERAL
1.01 SCOPE OF WORK
A. Furnish all labor, materials, and equipment required and perform all site preparation; complete as shown on the Drawings and as specified herein.
B. Clear, grub, and strip areas actually needed for site improvements within limits shown or specified.
C. Do not injure or deface vegetation that is not designated for removal.
1.02 DEFINITIONS
A. Clearing: Cut and remove all timber, trees, stumps, brush, shrubs, roots, grass, weeds, rubbish, and any other objectionable material resting on or protruding through the surface of the ground.
B. Grubbing: Removal of vegetation and other organic matter including stumps, buried logs, roots in excess of 1-1/2-in in diameter, matted roots, brush, timber, concrete rubble, and other debris encountered to a depth of 18-in below original grade or 18-in beneath the bottom of foundations, whichever is deeper.
C. Stripping: Removal of topsoil remaining after applicable scalping is competed.
D. Project Limits: Areas, as shown or specified, within which work is to be performed.
1.03 QUALITY ASSURANCE
A. Obtain Engineer's approval of staked clearing, grubbing, and stripping limits, prior to commencing clearing, grubbing, and stripping.
1.04 SCHEDULING AND SEQUENCING
A. Prepare Site only after adequate erosion and sediment controls are in place. Limit areas exposed uncontrolled to erosion during installation of temporary erosion and sediment controls to maximum of 1 acre.
1.05 LIMITS
A. Clearing, grubbing, scalping, and stripping (unless noted) shall be performed to the following limits, but shall not extend beyond project limits.
1. Excavation Excluding Trenches: 5-ft beyond top of cut slopes.
2. Trench Excavation: 10-ft on either side of trench centerline, regardless of actual trench width, or 2-ft beyond the top of trench excavation, whichever is greater.
02100-2
3. Fill Areas: 5-ft beyond toe of permanent fill
4. Structures: 15-ft outside of new structures.
5. Wherever grading is required: to 2-ft beyond grading limits, unless a larger dimension is specified or shown for specific activities.
6. Remove rubbish, trash, and junk from entire area within project limits.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.01 CLEARING
A. Preserve and protect trees and other vegetation designated on the Drawings to remain.
3.02 GRUBBING
A. See paragraph 1.02, Definitions.
3.03 STRIPPING
A. Do not remove topsoil until after scalping is completed.
B. Strip areas within limits to minimum depth shown or as specified (6 inches). Do not remove subsoil with topsoil.
C. Stockpile strippings separately from other excavated material.
3.04 DISPOSAL
A. Clearing and Grubbing Debris:
1. Dispose of debris offsite.
2. Burning of debris onsite will not be allowed.
3. Limit offsite disposal of clearing and grubbing debris to locations that are approved by federal, state, and local authorities.
B. Strippings:
1. Dispose of strippings that are unsuitable for topsoil or that exceed quantity required for topsoil offsite.
2. Stockpile topsoil in sufficient quantity to meet project needs. Dispose of excess strippings as specified for clearing and grubbing.
02100-3
3.05 PROTECTION
A. Maintain protection until all construction activities in the vicinity of the Work being protected has been completed.
B. Restrict construction activities to those areas within the limits of construction designated on the
Drawings. Adjacent properties and improvements thereon, which become damaged by construction operations, shall be promptly restored to their original condition, as acceptable to the affected property owners or the improvements of the Owner.
02270-1
City of Westminster Erosion Control
EROSION CONTROL
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and Contract Documents apply to the provisions of this section.
1.02 SECTION INCLUDES
A. Sediment fence as shown on the Drawings or as required to prevent sediment transport.
D. Other erosion control devices required for permits to control erosion and sedimentation.
1.03 REFERENCES
A. The latest issue of the publications listed below and referenced to thereafter by basic designation only, forms a part of this specification to the extent indicated by the reference thereto:
B. Urban Storm Drainage Criteria Manual, - Volume 3, Best Management Practices, Urban
Drainage and Flood Control District (UD&FCD).
1.04 REGULATORY REQUIREMENTS
A. Comply with Local, State and Federal requirements.
1.05 SUBMITTALS
A. Completed Erosion Control Permit Application.
PART 2 - PRODUCTS
2.01 SEDIMENT FENCE
A. Provide Sediment Fence with reinforced backing and staking materials.
B. Sediment materials shall be as specified in the City of Westminster detail.
2.02 GENERAL
A. All other erosion control devices shall be as specified in the Urban Drainage and Flood Control District Criteria Manual.
PART 3 - EXECUTION
3.01 SEDIMENT FENCE
02270-2
City of Westminster Erosion Control
A. Follow the detail shown on the Westminster Standards.
B. Sediment fence material shall be placed around all on site storage stockpiles.
3.02 MAINTENANCE
A. Contractor is responsible for maintaining temporary erosion control devices throughout project.
B. Remove and replace sediment fence that has become damaged, sediment laden, and/or ineffective.
03301-1
City of Westminster Cast-in-Place Concrete, Sidewalk, Curb, and Gutter
CAST-IN-PLACE CONCRETE, SIDEWALK, CURB, AND GUTTER
PART 1 – GENERAL
1.01 DESCRIPTION
A. Drawings and General Provisions of the Contract apply to the provisions of this section.
B. Description of Work: Construction of curbs, curbs with gutters, square cross-pan sections, driveways and sidewalks.
C. The terms "State Specifications" and "CDOT" in this section refers to State Department of Highways, Division of Highways, State of Colorado "Standard Specifications for Road and Bridge Construction - current edition.
1.02 QUALITY ASSURANCE
A. Testing.
1. Test in accordance with the City of Westminster Standards and Specifications.
B. Reference Standards.
1. American Association of State Highway and Transportation Officials (AASHTO):
a. AASHTO M213 - Preformed Expansion Fillers for Concrete Paving and Structural Construction.
b. AASHTO M148 - Liquid Membrane-Forming Compounds for Curing Concrete.
c. AASHTO M-55 - Welded Steel Wire Fabric for Concrete Reinforcement.
PART 2 – PRODUCTS
2.01 MATERIALS
A. Concrete: Conform to requirements from City of Westminster Standards and Specifications.
B. Wire Mesh: Conform to requirements from City of Westminster Standards and Specifications.
C. Expansion joint filler shall be 1/2-inch wide and comply with AASHTO M213, for full depth and thickness.
D. Joint Sealer: Comply with FS TT-S-001543A. Deliver each lot of sealer in containers plainly marked with manufacturer's name or trademark and date of manufacture.
03301-2
E. Fiber Reinforcing: 1.5 pounds per cubic yard, minimum.
PART 3 – EXECUTION
3.01 PREPARATION
A. Prepare foundation to lines, grades, and cross-sections as shown on Drawings. Remove and replace soft or unsuitable material with compacted granular material. Moisten base foundation immediately prior to placing of concrete. Concrete shall not be placed until all forms and reinforcing steel have been inspected and approved by the Project Engineer.
3.02 FORMING
A. Forms shall be of wood or metal and be straight and of sufficient strength to resist springing, tipping, or other displacement during process of depositing and consolidating concrete.
B. Forms shall be of full depth and shall be of such design as to permit secure fastening.
C. Face boards if used, shall be so constructed and shaped that their lower edge conforms to lines and radii indicated by cross-section on Drawings.
D. Use flexible or curved forms of proper radius for curves of 100-foot radius or less.
E. Forms shall be cleaned and oiled before concrete is placed against them.
3.03 INSTALLATION
A. Place on prepared subgrade.
B. Consolidate and slip form concrete to required section or deposit it in forms to proper…
This is the start of the file's text. The full file is on GovTribe.