About this file

This document is a comprehensive Construction Contract between the City of Westminster, Colorado, and an unnamed contractor for the Briggs Greenhouse Structural Repairs and Re-siding project. The contract outlines the terms, conditions, and specifications for construction services, with a scope of work focused on improving the Briggs Greenhouse building. The contract will commence upon receipt of the Notice to Proceed and has an initial term that expires on a specified date, with potential for two additional one-year renewal terms. The contractor is required to complete the work within a designated time frame after receiving the Notice to Proceed, and the project involves furnishing all necessary labor, materials, equipment, and resources to perform the work in a workmanlike manner.

The total contract amount is specified in the document, with the City agreeing to pay the contractor for performance of the work not to exceed a defined sum. The contract includes provisions for liquidated damages of a specified amount per day for late completion, and requires the contractor to provide performance and payment bonds each equal to 100% of the contract sum. Insurance requirements are extensive, including workers' compensation, commercial general liability, automobile liability, umbrella liability, and owner's liability insurance with specific minimum coverage amounts. The contractor is responsible for all costs, permits, and compliance with local, state, and federal regulations, and must maintain detailed documentation and provide comprehensive warranties for the work performed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

{--rcl--Project Number--rcl--} {---City Project Number---}

CONSTRUCTION CONTRACT (CITY PROJECT MANAGER)

FOR THE FOLLOWING PROJECT:

{---CONSTRUCTION PROJECT TITLE---}

This Construction Contract, effective {---Effective Date---}, by and between {---COMPANY NAME---} (hereinafter, “Contractor”), a {---Vendor Enitity Type---} organized pursuant to the laws of the State of {---Vendor State of Organization---} and located at {---Vendor Street1---} {---Vendor City---}, {---Vendor State/Province---} {---Vendor Postal Code---} and the CITY OF WESTMINSTER (hereinafter, “City” or “Owner”), a home-rule municipal corporation organized pursuant to the laws of the State of Colorado, located at 4800 West 92nd Avenue, Westminster, Colorado, 80031, provides that the Contractor and City, in consideration of the mutual covenants hereinafter set forth, agree as follows:

PART 1 – WORK; TIME

1.01 The Contractor agrees to furnish all of the technical, administrative, professional, and other labor, all supplies and materials, equipment, printing, vehicles, local travel, office space and facilities, testing and analyses, calculations, and any other facilities or resources necessary to perform in a workmanlike manner all Work required by the Contract Documents.

1.02 The Contractor agrees to undertake the performance of the Work within ten (10) days after receipt of the Notice to Proceed and agrees that the Work will be completed within {---Project Complete Time---} of the date of the Notice to Proceed unless the contract time is extended by the City as provided in the Contract Documents.

1.03 The Parties agree that, in any section in which the Contractor prepares any document for “the approval of the City,” such approval does not mean that City is responsible for the accuracy, thoroughness, or judgment contained in the document. City does not waive the right to hold the Contractor responsible for the accuracy, thoroughness, or judgment expressed in the document, as it is expressly agreed by the Parties that the City is relying on the expertise of the Contractor.

1.04 The term of this Construction Contract shall be commenced upon receipt of the Notice to Proceed. The initial term shall begin on the date of commencement of the project and shall expire on {---Expiration Date---}. Subject to annual appropriation by the City, and subject to the provisions of section 2.05, below, this Construction Contract may renew for two (2) additional one (1) year terms unless the City gives written notice of its intent not to renew this agreement no less than sixty (60) days prior to its expiration.

PART 2 - CONTRACT PRICE AND PAYMENT

2.01 The City shall pay the Contractor for performance of the Work in accordance with the Contract Documents the amount(s) shown on Contractor's Bid Proposal, not to exceed {---Contract Amount in Words---} dollars (${---Contract Amount---}).

2.02 The City shall make payments as set forth in Article 9 of the General Conditions, subject to the City's obligation to retain a portion of the payments until final completion and acceptance by the City of all Work included in the Contract Documents.

2.03 Prior to final payment, all Work specified by the Contract Documents must be completed. Payment shall be made only after the procedure specified by the General Conditions is completed.

2.04 The City represents that either an appropriation for the price specified in this Construction Contract has been made by the City Council or that sufficient funds have otherwise been made available for the payment of this Construction Contract.

{--rcl--Construction Renewal Limit--rcl--}

PART 3 - CONTRACTOR'S REPRESENTATIONS

3.01 In order to induce the City to enter into this Construction Contract, the Contractor makes the following representations:

(a) The Contractor has familiarized himself with the nature and the extent of the Contract Documents, Work, the location and site of the Work and all local conditions and federal, state and local laws, ordinances, rules and regulations that in any manner may affect cost, progress or performance of the Work.

(b) Contractor has carefully studied all physical conditions at the site and existing facilities affecting cost, progress or performance of the Work.

(c) Contractor has given the City written notice of all conflicts, errors or discrepancies that he has discovered in the Contract Documents and the written resolution thereof by the City is acceptable to the Contractor.

3.02 Contractor agrees to remedy all defects appearing in the Work or developing in the materials furnished and the workmanship performed under this Construction Contract for a period of one (1) year or such other time that is specified in the Contract Documents after the date of acceptance of the Work by the City, and further agrees to indemnify and save the City harmless from any costs encountered in remedying such defects. Contractor shall provide a performance bond that shall remain in effect until all defects are corrected as required by this paragraph.

3.03 Contractor is an independent contractor and nothing herein contained shall constitute or designate the Contractor or any of its employees or agents as agents or employees of the City.

PART 4 - CONTRACT DOCUMENTS

4.01 The Contract Documents, which comprise the entire Construction Contract between the City and the Contractor, are attached to this Construction Contract and made a part hereof, including:

Bid Packet, including but not limited to Bid Notice, Invitation to Bid, Instructions to Bidders, Bid Form, NonCollusion Affidavit of Prime Bidder, Bidder’s Certification, Bid Bond, and any attachments and exhibits Notice of Award Notice to Proceed Construction Contract Construction Drawings Performance Bond Payment Bond General Conditions, including table of contents Special Conditions Addendum Project Specifications and any industry standards or regulations referenced therein Change Orders Insurance Certificates Tax-Exempt Certificates

In the event of an inconsistency between any provisions of the Contract Documents, the more specific provisions shall govern the less specific provisions, and written addenda, change orders, or other modifications approved in writing by both parties shall govern the original documents.

4.02 There are no Contract Documents other than those listed above. The Contract Documents may only be altered, amended or repealed by a modification, in writing, executed by the City and the Contractor.

PART 5 - PROJECT MANAGER

5.01 The Project Manager, for the purposes of the Contract Documents, is the following, or such other person or firm as the City may designate in writing:

Name: {---Employee First Name---} {---Employee Last Name---} Address: {---Employee Address---} {---Employee City---}, {---Employee State/Province---} {---Employee Postal Code---} Telephone: {---Employee Office Phone---}

The Project Manager is authorized to represent and act as agent for the City with respect to City’s rights and duties under the Contract Documents, provided, however, the Project Manager shall not have any authority to approve any Change Order or approve any amendment to the Construction Contract or Contract Documents, except for those minor Change Orders defined in paragraph 7.4.1 of the General Conditions, such authority being specifically reserved to the duly authorized official of the City having such approval authority pursuant to the City’s Charter and ordinances. In the event of doubt as to such authority, the Contractor may request a written representation from the City Manager resolving such doubt and designating the person with authority under the circumstances, which written representation shall be conclusive and binding upon the City.

PART 6 - ASSIGNMENT

6.01 No assignment by a party hereto of any rights under or interest in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically, but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents. This restriction on assignment includes, without limitation, assignment of the Contractor's right to payment to its surety or lender.

6.02 It is agreed that this Construction Contract shall be binding on and inure to the benefit of the parties hereto, their heirs, executors, administrators, assigns and successors.

PART 7 - GOVERNING LAW AND VENUE

7.01 This Construction Contract shall be governed by the laws of the State of Colorado and the Charter of the City of Westminster.

7.02 This Construction Contract shall be deemed entered into in both Adams County and Jefferson County, State of Colorado, as the City is located in both counties. At the Owner's option, the location for settlement of any and all claims, controversies and disputes arising out of or related to this Construction Contract or any breach thereof, whether by alternative dispute resolution or litigation, shall be proper only in either county.

PART 8 - LIQUIDATED DAMAGES

8.01 The City and the Contractor recognize that time is of the essence in this Construction Contract and that the City will suffer financial loss if the Work is not substantially completed within the time specified in paragraph 1.02 above, plus any extensions thereof allowed by the City by written Change Order. They also recognize the delays, expense, and difficulties involved in proving, in a legal or arbitration proceeding, the actual loss suffered by the City if the Work is not substantially complete on time. Accordingly, rather than requiring any such proof, the City and the Contractor agree that as liquidated damages for delay (but not as a penalty) the Contractor shall pay the City {---Liquidated Damages Amount in Words---} dollars (${---Liquidated Damages Amount---}) for each day that expires after the time specified in paragraph 1.02 until the Work is complete. It is agreed that this is a reasonable estimate of the damages likely to be suffered by the City for late completion of the Work. If the Contractor shall fail to pay such liquidated damages promptly upon demand therefor, the Surety on the Performance Bond shall pay such damages. Also, the City may withhold all, or any part of, such liquidated damages from any payment due the Contractor.

PART 9 - MODIFICATIONS

This Construction Contract shall be modified only by written Change Orders or Addenda agreed upon by the parties hereto, duly issued in form approved by the City Attorney and in conformance with the other Contract Documents.

PART 10 - AUTHORITY

The person or persons signing and executing this Construction Contract on behalf of each Party, do hereby warrant and guarantee that he/she or they have been fully authorized to execute this Construction Contract and to validly and legally bind such Party to all the terms, performances and provisions herein set forth.

PART 11 - CONTINGENCY

This Construction Contract is expressly contingent upon the approval of the City of Westminster's City Council of all of the terms set forth herein. In the event this Construction Contract is not approved in its entirety by City Council, neither Party shall be bound to the terms of this Construction Contract.

INSURANCE CERTIFICATES REQUIRED BY THE GENERAL CONDITIONS OF THIS CONTRACT SHALL BE SENT TO {---DEPARTMENT/BUSINESS UNIT---} DEPARTMENT, ATTENTION: {---EMPLOYEE FIRST NAME---} {---EMPLOYEE LAST NAME---}.

SIGNATURE PAGE FOLLOWS.

IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract in triplicate. Two counterparts have been delivered to the City and one counterpart has been delivered to the Contractor. All portions of the Contract Documents have been signed or identified by the City and the Contractor.

{--rmc--Corporation Signature Block--rmc--}{--rmc--LLC or Individual Notary Signature Block--rmc--}

Address for giving notice: Address for giving notice:

{---Vendor Street1---}4800 West 92nd Avenue
{---Vendor City---}, {---Vendor State/Province---} {---Vendor Postal Code---}Westminster, Colorado 80031

I certify that either an appropriation has been made by the City Council or that sufficient funds have otherwise been made available for the payment of this Construction Contract.

_______________________________
City Manager

Account No. ____________________

EXHIBIT B

{--rcl--Project Number--rcl--} {---City Project Number---}

GENERAL CONDITIONS TO THE CONSTRUCTION CONTRACT

(CITY PROJECT MANAGER)

TABLE OF CONTENTS

ARTICLE 1 GENERAL PROVISIONS

1.1Definitions
1.2Execution, Correlation and Intent
1.3Ownership and Use of Documents

ARTICLE 2 OWNER

2.1Information and Services Required of the Owner
2.2Owner’s Right to Stop the Work
2.3Owner’s Right to Carry Out the Work

ARTICLE 3 CONTRACTOR

3.1Review of Contract Documents and Field Conditions by Contractor
3.2Supervision and Construction Procedures
3.3Labor and Materials
3.4Reserved
3.5Warranty
3.6Taxes
3.7Permits, Fees and Notices
3.8Allowances
3.9Superintendent
3.10Contractor's Construction Schedule
3.11Documents and Samples at the Site
3.12Shop Drawings, Product Data and Samples
3.13Use of Site
3.14Cutting and Patching of Work
3.15Cleaning Up
3.16Communications
3.17Royalties and Patents
3.18Indemnification
3.19Attorneys Fees

ARTICLE 4 ADMINISTRATION OF THE CONTRACT

4.1Project Manager
4.2Project Manager’s Administration of the Construction Contract
4.3Claims and Disputes
4.4Resolution of Claims and Disputes

ARTICLE 5 SUBCONTRACTORS

5.1Award of Subcontracts and Other Contracts for Portions of the Work
5.2Subcontractual Relations
5.3Contingent Assignment of Subcontracts

ARTICLE 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS

6.1Owner's Right to Perform Work and to Award Separate Contracts
6.2Mutual Responsibility
6.3Owner's Right to Clean Up

ARTICLE 7 CHANGES IN THE WORK

7.1Changes
7.2Change Orders
7.3Construction Change Directives
7.4Minor Changes in the Work

ARTICLE 8 TIME

8.1Date of Commencement of the Work
8.2Progress and Completion
8.3Delays and Extensions of Time

ARTICLE 9 PAYMENTS AND COMPLETION

9.1Contract Sum
9.2Schedule of Values
9.3Applications for Payment
9.4Certificates for Payment
9.5Decisions to Withhold Certification
9.6Progress Payments
9.7Failure of Payment
9.8Substantial Completion
9.9Partial Occupancy or Use
9.10Final Completion and Final Payment

ARTICLE 10 PROTECTION OF PERSONS AND PROPERTY

10.1Safety Precautions and Programs
10.2Safety of Persons and Property
10.3Emergencies
10.4Use of Explosives, Driving or Removal of Piles, Wrecking, Excavation Work or Other Similar and Potentially Dangerous Work
10.5Underground Utilities

ARTICLE 11 INSURANCE REQUIREMENTS

11.1Contractor's Insurance
11.2Additional Named Insured
11.3Builder’s Risk/Property Insurance
11.4General Requirements

ARTICLE 12 UNCOVERING AND CORRECTION OF WORK

12.1Uncovering of Work
12.2Correction of Work
12.3Acceptance of Defective or Non-Conforming Work

ARTICLE 13 MISCELLANEOUS PROVISIONS

13.1Governing Law
13.2Successors and Assigns
13.3Written Notice
13.4Claims for Damages
13.5Performance and Payment bond
13.6Rights and Remedies
13.7Tests and Inspections
13.8Litigation and Work Progress
13.9Equal Employment Opportunity
13.10Commercial Driver’s License Substance Screening

ARTICLE 14 TERMINATION OF THE CONTRACT

14.1Termination by the Contractor
14.2Termination by the Owner for Cause
14.3Suspension by the Owner for Convenience

ARTICLE 1

GENERAL PROVISIONS

1.0 This Construction Contract is expressly contingent upon the approval of the City of Westminster's City Council of all of the terms set forth herein. In the event this Construction Contract is not approved in its entirety by City Council neither Party shall be bound to the terms of this Construction Contract.

1.1 DEFINITIONS

1.1.1 “Application for Payment” means the Contractor’s request for payment submitted to the Project Manager according to the process set forth in paragraphs 9.3.1- 9.3.4.

1.1.2 “Bidding Documents” means the Bid Packet including its Bid Notice, Invitation to Bid, Instructions to Bidders, Bid Form, Non-Collusion Affidavit of Prime Bidder, Bidder’s Certification, Bid Bond, and any attachments and exhibits to the Bid Packet.

1.1.3 “Certificate for Payment” means the amount approved for payment by the Project Manager after the receipt of the Contractor’s Application for Payment, as more fully defined in paragraph 9.4.1.

1.1.4 “Change Order” means a written order to the Contractor, signed by the Contractor and the Owner stating their agreement upon a change in the Work; the amount of the adjustment in the Contract Sum, if any; or the extent of the adjustment in the Contract Time, if any, as more fully defined in paragraph 7.2.

1.1.5 “Claim” means a demand or assertion by one of the parties seeking, as a matter of right, adjustment of contract terms, payment of money, extension of time, or other relief with respect to the terms of the Construction Contract, or other disputes between the Owner and Contractor arising out of or relating to the Construction Contract.

1.1.6 “Construction Change Directive” means a written order directed to the Contractor and signed by the Owner, directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both, as defined more fully in paragraphs 7.3.1-7.3.9.

1.1.7 “Construction Contract” or “Contract” means the entire and integrated agreement between the parties hereto, evidenced by the Contract Documents, which supersedes all prior negotiations, representations, or agreements, either written or oral, subject only to amendment or modification as permitted by Article 7.

1.1.8 “Contract Documents” means the Construction Contract, the Conditions of the Contract (General, Special, Supplementary and other Conditions), the Drawings, the Specifications, all Addenda issued prior to and all Modifications issued after execution of the Contract, and all other documents listed in the Contract, including the Bidding Documents, the Notice of Award, Notice to Proceed; Performance Bond; Payment Bond; Certificates of Insurance; and Tax-Exempt Certificates. Nothing contained in the Contract Documents creates any contractual relationship between the Owner any subcontractor, sub-subcontractor, or supplier of equipment or materials (except as provided in paragraph 5.4 hereof).

1.1.9 “Contract Sum” means the amount stated in paragraph 2.01 of the Construction Contract and, including authorized adjustments thereto, is the total amount payable by the Owner to the Contractor for the performance of the Work under the Contract Documents.

1.1.10 “Contract Time” means the period of time allotted in the Contract Documents for Substantial Completion of the Work, including authorized adjustments thereto.

1.1.11 “Contractor” means the person or entity identified as such in the Construction Contract or an authorized representative thereof.

1.1.12 “Date of Commencement of the Work” is the date established in the Notice to Proceed. If there is no Notice to Proceed, it shall be the date of the Construction Contract or such other date as may be established therein.

1.1.13 The “Date of Substantial Completion” is the date certified by the Project Manager in accordance with paragraph 9.8.

1.1.14 “Day” as used in the Contract Documents shall mean calendar day unless otherwise specifically designated.

1.1.15 “Drawings” are the graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules, and diagrams.

1.1.16 “Final Completion” means the finding by the Project Manager that the final Certificate for Payment should be issued based on his knowledge, information and belief that the Work has been completed in accordance with the terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor, and noted in said final Certificate for Payment, is due and payable, as more fully defined in paragraph 9.10.1.

1.1.17 “Modification” means (1) a written amendment to the Construction Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive, or (4) a written Order for a Minor Change in the Work approved by the Owner pursuant to paragraph 7.4.

1.1.18 “Notice to Proceed” means the form issued by the City and accepted in writing by the Contractor that notifies Contractor to begin work on or before a date certain, establishes an end date, and returns bid security.

1.1.19 “Order for a Minor Change in the Work” means an order issued by the Project Manager adjusting the Contract Sum or extending the Contract Time as permitted by paragraph 7.4.1.

1.1.20 “Owner” means the person or entity identified as such in the Construction Contract or an authorized representative thereof. The term “City” may be used interchangeably with the term “Owner.”

1.1.21 “Project” means the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner or by separate contractors.

1.1.22 “Project Manager” means the City representative identified as such in Part 5 of the Contract.

1.1.23 “Project Manual” means the volume usually assembled for the Work which may include the bidding requirements, sample forms, conditions of the Contract, and Specifications.

1.1.24 “Specifications” or “Project Specifications” are that portion of the Contract Documents consisting of the written requirements for materials, equipment, construction systems, standards, and workmanship for the Work, and performance of related services.

1.1.25 “Subcontractor” means a person or entity who has a direct contract with the Contractor to perform any of the Work at the site or an authorized representative thereof. "Subcontractor" does not include any separate contractor or his subcontractor.

1.1.26 “Substantial Completion” means the stage in the progress of the Work when the Work (or designated portion thereof that the Owner agrees to accept separately) is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or use the Work for its intended use as more fully explained in paragraph 9.8.1.

1.1.27 “Sub-subcontractor” means a person or entity who has a direct or indirect contract with a subcontractor to perform any of the Work at the site or an authorized representative thereof.

1.1.28 “Underground Utilities” means any below ground line, structure, facility or installation used by a utility or service provider including, but not limited to, telephone company lines, cable and conduit; cable television lines, cable and conduit; internet lines, cable and conduit; sewer lines and water lines, including individual sewer and water service lines; stormwater lines; gas lines; electrical lines, cables and conduit; and traffic signal lines, cable and conduit.

1.1.29 “Work” means the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor's obligations for the completed construction required by the Contract Documents. The Work may constitute the whole or a part of the Project.

1.2 EXECUTION, CORRELATION AND INTENT

1.2.1 The Contract Documents shall be signed in not less than triplicate by the Owner and Contractor and shall be maintained by the Project Manager.

1.2.2 By executing the Contract, the Contractor represents that he has visited the site, familiarized himself with the local conditions under which the Work is to be performed, and correlated his observations with the requirements of the Contract Documents.

In connection with the foregoing, and having carefully examined all Contract Documents, as aforesaid, and having visited the Site, and having familiarized himself with the urban site construction circumstances of the Project, the Contractor acknowledges and declares that it has no knowledge of any discrepancies, omissions, ambiguities, or conflicts in said Contract Documents and that if it becomes aware of any such discrepancies, omissions, ambiguities, or conflicts, it will promptly notify Owner and Project Manager of such fact.

1.2.3 The Contract Documents include all items necessary for the proper execution and completion of the Work by the Contractor. The Work shall consist of all items specifically included in the Contract Documents as well as all additional items of work which are reasonably inferable from that which is specified in order to complete the Work in accordance with the Contract Documents. The Contract Documents are complementary, and what is required by any one Contract Document shall be as binding as if required by all. Any differences between the requirements of the Drawings and the Specifications or any differences within the Drawings themselves or within the Specifications themselves have been referred to the Owner by Contractor prior to the submission of bids and have been clarified by an Addendum issued to all Bidders.

If any such differences or conflicts were not called to the Owner’s attention prior to submission of bids, the Project Manager shall decide which of the conflicting requirements will govern based upon the most stringent of the requirements, and subject to the approval of the Owner, the Contractor shall perform the work at no additional cost or time to the Owner in accordance with the Project Manager’s decision. Work not covered in the Contract Documents will not be required unless it is consistent therewith and is reasonably inferable therefrom as being necessary to produce the intended results.

1.2.4 The organization of the Specifications into divisions, sections and articles, and the arrangement of Drawings shall not control the Contractor in dividing the Work among subcontractors or in establishing the extent of Work to be performed by any trade.

1.2.5 Unless otherwise stated in the Contract Documents, words and abbreviations which have well-known technical or trade meanings are used in the Contract Documents in accordance with such recognized meanings.

1.2.6 In the interest of brevity, the Contract Documents frequently omit modifying words such as “all” and “any” and articles such as “the“ and “an.” The fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement.

1.2.7 Interpretation of Contract Documents - masculine includes both the masculine and the feminine; singular includes the singular and the plural; headings are for reference only and are not substantive

1.3 OWNERSHIP AND USE OF DOCUMENTS

1.3.1 The Drawings, Specifications, and other similar or related documents and copies thereof are furnished to the Contractor for the purpose of performing the Work and are, and shall remain, the property of the Owner. The Contractor may retain one record set. Neither the Contractor nor any subcontractor, sub-subcontractor or material or equipment supplier shall own or claim a copyright in the Drawings, Specifications and other similar or related documents, and Owner will retain all common law, statutory, and other reserved rights, in addition to the copyright (including, without limitation, the right to create derivative works therefrom). All copies of such documents shall be returned to the Owner upon completion of the Work. The Drawings, Specifications, and other similar or related documents and copies thereof furnished to the Contractor, are for use solely with respect to this Project. They are not to be used by the Contractor or any subcontractor, sub-subcontractor or material or equipment supplier on other projects or for additions to this Project outside the scope of the Work without the specific written consent of the Owner. The Contractor, subcontractors, sub-subcontractors and material or equipment suppliers are granted a limited license to use and reproduce applicable portions of the Drawings, Specifications and other documents appropriate to and solely for use in the execution of their Work under the Contract Documents. All copies made under this license shall bear the statutory copyright notice, if any, shown on the Drawings, Specifications and other documents. Submittal or distribution to meet official regulatory requirements or for other purposes in connection with this Project is not to be construed as publication in derogation of any copyright or other reserved rights.

ARTICLE 2

OWNER

2.1 INFORMATION AND SERVICES REQUIRED OF THE OWNER

2.1.1 The Owner shall furnish surveys describing the physical characteristics, legal limitations and utility locations, if such utilities are the property of Owner, for the site of the Project, and a legal description of the site, if necessary. The Contractor shall undertake such further investigations and studies as may be necessary or useful to determine site characteristics and conditions. In connection with the foregoing, Contractor shall locate prior to performing any work, all Underground Utilities. If utility locate services are provided in the field by utility owners, Contractor nonetheless remains solely responsible to determine the actual location of all Underground Utilities.

2.1.2 Except for permits and fees which are the responsibility of the Contractor under the Contract Documents, the Owner shall secure and pay for necessary approvals, easements, assessments and charges required for the construction, use or occupancy of permanent structures or for permanent changes in existing facilities. Such approvals and the like shall be provided by Owner within a time and in a manner as to avoid any unreasonable delays in the Work or schedule of Contractor and shall include only such approvals for permanent facilities which are necessary to perform the Work as set forth in the Contract Documents.

2.1.3 Information or services required to be furnished by Owner shall be furnished by the Owner with reasonable promptness to avoid unreasonable delay in the orderly progress of the Work.

2.1.4 Unless otherwise provided in the Contract Documents, the Contractor will be furnished, free of charge, all copies of Drawings and Specifications reasonably necessary for the execution of the Work.

2.1.5 The Owner shall forward all instructions to the Contractor through the Project Manager.

2.1.6 The foregoing are in addition to other duties and responsibilities of the Owner enumerated herein and especially those in respect to Work by Owner or by Separate Contractors, Payments and Completion, and Insurance in Articles 6, 9, and 11 respectively.

2.2 OWNER'S RIGHT TO STOP THE WORK

2.2.1 If the Contractor fails to correct defective Work as required by Paragraph 12.2 or fails to carry out the Work in accordance with the Contract Documents, or fails or refuses to provide a sufficient amount of properly supervised and coordinated labor, materials, or equipment so as to be able to complete the Work within the Contract Time, or fails to remove and discharge (within ten days) any lien filed upon Owner’s property by anyone claiming by, through, or under Contractor, or disregards the instructions of the Project Manager or Owner when based on the requirements of the Contract Documents, the Owner or the Project Manager, by a written order, may order the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of the Owner and the Project Manager to stop the Work shall not give rise to any duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity.

2.3 OWNER'S RIGHT TO CARRY OUT THE WORK

2.3.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a seven-day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, or fails within such seven-day period to eliminate (or diligently commence to eliminate) the cause of any stop work order issued under paragraph 2.3.1 hereof, the Owner may, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation and additional services and expenses made necessary by such default, neglect or failure. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner.

ARTICLE 3

CONTRACTOR

3.1 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR

3.1.1 In addition to and not in derogation of Contractor’s duties under paragraphs 1.2.2 and 1.2.3 hereof, Contractor shall carefully study and compare the Contract Documents and shall at once report to the Owner any error, inconsistency or omission discovered. The Contractor shall not be liable to the Owner for any damage resulting from any such errors, inconsistencies or omissions in the Contract Documents hereof unless the Contractor recognized or reasonably should have recognized such error, inconsistency or omission and failed to report it to the Owner. If the Contractor performs any construction activity involving an error, inconsistency or omissions in the Contract Documents that Contractor recognized or reasonably should have recognized, without such notice to the Owner, the Contractor shall assume complete responsibility for such performance and shall bear the full amount of the attributable costs for correction. The Contractor shall perform no portion of the Work at any time without Contract Documents or, where required, approved Shop Drawings, Product Data or Samples for such portion of the Work.

3.1.1.1 If any errors, inconsistencies, or omissions in Contract Documents are recognized or reasonably should have been recognized by the Contractor, any member of its organization, or any of its subcontractors, the Contractor shall be responsible for notifying the Owner in writing of such error, inconsistency, or omission before proceeding with the Work. The Owner will take such notice under advisement and within a reasonable time commensurate with job progress, render a decision. If Contractor fails to give such notice and proceeds with such work, it shall correct any such error, inconsistency, or omission at no additional cost to Owner.

3.1.2 In addition to and not in derogation of Contractor's duties under paragraphs 1.2.2 and 1.2.3 hereof, the Contractor shall take field measurements and verify field conditions and shall carefully compare such field measurements and conditions and other information known to the Contractor with the Contract Documents before commencing activities. Errors, inconsistencies or omissions discovered shall be reported to the Project Manager at once.

3.1.3 The Contractor shall perform the Work in accordance with the Contract Documents and submittals approved pursuant to paragraph 3.12.

3.2 SUPERVISION AND CONSTRUCTION PROCEDURES

3.2.1 The Contractor shall supervise and direct the Work, using his best skill and attention. The Contractor shall be solely (subject to the terms and provisions of Article 4 hereof), responsible for and have control over all construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless Contract Documents give other specific instructions concerning these matters.

The Contractor shall review any specified construction or installation procedure, including those recommended by manufacturers, and shall advise the Owner if the specified procedure deviates from good construction practice or if following the procedure will affect any warranties, and may propose any alternative procedure which the Contractor will warrant.

3.2.2 The Contractor shall be responsible to the Owner for the acts and omissions of his employees, subcontractors and their agents and employees, and other persons performing any of the Work under a contract or other arrangements with the Contractor. It is understood and agreed that the relationship of Contractor to Owner shall be that of an independent contractor. Nothing contained herein or inferable herefrom shall be deemed or construed to (1) make Contractor the agent, servant, or employee of the Owner, or (2) create any partnership, joint venture, or other association between Owner and Contractor. Any direction or instruction by Owner in respect of the Work shall relate to the results the Owner desires to obtain from the Work, and shall in no way affect Contractor's independent contractor status as described herein.

3.2.3 The Contractor shall not be relieved from his obligations to perform the Work in accordance with the Contract Documents either by the activities or duties of the Project Manager in his administration of the Contract, or by inspections, tests or approvals required or performed under Paragraph 13.7 by persons other than the Contractor.

3.2.4 The Contractor shall be solely responsible for locating all existing underground installations, including Underground Utilities and their service connections, in advance of excavating or trenching, by contacting the owners thereof and prospecting. Notwithstanding utility locate services that may be provided in the field by utility owners, Contractor remains ultimately responsible to determine the actual location of all Underground Utilities, facilities, structure, or installations. The Contractor shall use his own information and shall not rely upon any information shown or not shown on the plans or on field locates provided by the utility owner concerning existing Underground Utilities, facilities, structure, or installations. Any delay, additional work, or extra cost to the Contractor caused by existing Underground Utilities, facilities, structures or installations shall not constitute a claim for extra work, additional payment, or damage.

3.2.5 The Contractor has the responsibility to ensure that all equipment and material suppliers and subcontractors, their agents, and employees adhere to the Contract Documents, and that they order material and equipment on time, taking into account the current market and delivery conditions and that they provide equipment and materials on time. The Contractor shall coordinate its Work with that of all others on the Project, including deliveries, storage, installations, and construction utilities. The Contractor shall be responsible for the space requirements, locations, and routing of its equipment. In areas and locations where the proper and most effective space requirements, locations, and routing cannot be made as indicated, the Contractor shall meet with all others involved, before installation, to plan the most effective and efficient methods of overall installation.

3.2.6 The Contractor shall establish and maintain bench marks and all other grades, lines, and levels necessary for the Work, report errors or inconsistencies to the Owner before commencing work, and review the placement of the structure(s) and permanent facilities on the site with the Owner after all lines are staked out and before foundation work is started. Contractor shall provide access to the Work for the Owner, the Project Manager, other persons designated by Owner, and governmental inspectors. Any encroachments, as revealed by an improvement survey, made by Contractor or its subcontractors (of any tier) on adjacent properties due to construction, except for encroachments arising from errors or omissions not reasonably discoverable by Contractor in the Contract Documents, shall be the sole responsibility of the Contractor and Contractor shall correct such encroachments within thirty (30) days of the improvement survey (or as soon thereafter as reasonably possible), at Contractor’s sole expense, either by the removal of the encroachment (and subsequent reconstruction on the project site) or agreement with the adjacent property owner(s) (in form and substance satisfactory to Owner in its sole discretion) allowing the encroachments to remain.

3.3 LABOR AND MATERIALS

3.3.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.

3.3.2 The Contractor shall at all times enforce strict discipline and good order among his employees and shall not employ on the Work any unfit person or anyone not skilled in the task assigned to him.

3.4.3 Materials shall conform to manufacturer's standards in effect at the date of execution of the Construction Contract and shall be installed in strict accordance with manufacturer's directions. The Contractor shall, if required by the Owner, furnish satisfactory evidence as to the kind and quality of any materials. All packaged materials shall be shipped to the site in the original containers clearly labeled, and delivery slips shall be submitted with bulk materials identifying thereon the source, and warranting quality and compliance with Contract Documents.

3.3.4 When the Contract Documents require the Work, or any part of same, to be above the standards required by applicable laws, ordinances, rules, regulations, and other statutory provisions pertaining to the Work, such Work shall be performed and completed by the Contractor in accordance with the Contract Documents.

3.4 RESERVED

3.5 WARRANTY

3.5.1 The Contractor warrants to the Owner that all materials and equipment furnished under this Contract will be of good quality and new unless otherwise required or permitted by the Contract Documents, and that all Work will be of good quality, free from faults and defects and in conformance with the Contract Documents. All Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective. If required by the Owner, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment.

3.5.2 Experienced manufacturer's representatives shall be used to supervise the installation of equipment as may be required by the Owner. Any special tools or equipment which may be required for first class work shall be provided by the Contractor.

3.5.3 The acceptance at any time of materials or equipment by or on behalf of the Owner shall not be a bar to future rejection if they are subsequently found to be defective, inferior in quality or uniformity, to the material or equipment specified, or are not as represented to the Owner.

3.5.4 In the absence of detailed specifications, all materials shall conform to the latest standards of the American Society for Testing Materials (ASTM) available at the time notice inviting Contractors to bid is published unless otherwise indicated.

3.5.5 Any reference to standard specifications in any of the Contract Documents shall always imply the latest edition of such standard specifications or specifications available at the time notice inviting contractors to bid is published unless otherwise indicated.

3.5.6 Within one year after the date of Final Completion of the Work or within such longer period of time as may be prescribed by law or by the terms of any applicable special warranty required by the Contract Documents, the Contractor shall make all needed repairs arising out of defective workmanship or materials, or both, which in the judgment of the Owner shall become necessary during such period. If within ten (10) days after the mailing of a notice in writing to the Contractor or his agent, the Contractor shall neglect to make, or undertake with due diligence to make the aforesaid repairs, the Owner is hereby authorized to make such repairs at the Contractor's expense. In case of an emergency, the Contractor will be notified and shall correct and make repairs within the necessary time constraints. Failure of the Contractor to respond to the notification shall result in the Owner making the necessary repairs at the Contractor's expense. This obligation shall survive termination of the Contract.

3.5.7 Should the Owner claim by written communication before the warranty period expires that certain defects exist and that these require repair or replacement, the warranty period and applicable surety shall be automatically extended for as long as these defects remain unremedied.

3.6 TAXES

3.6.1 All sales of construction and building materials to contractors and subcontractors for use in the building, erection, alteration or repair of structures, highways, roads, streets and other public works owned and used by the Owner are exempt from State and other State-collected sales and use taxes and from Westminster sales and use taxes. However, such materials may be subject to sales and use taxes imposed by other local taxing authorities.

3.6.2 Prior to City’s issuance of the Notice to Proceed and start of work, the Contractor shall deliver to the Project Manager two copies of the completed and executed "Application for Exemption Certificate" with the approval of the Department of Revenue, State of Colorado, affixed. These certificates will serve as an indication to the Owner that the Contractor has acquired the necessary exemption for State and other State-collected sales and use taxes. The Contractor also agrees to make the same requirement, as contained above, of the material suppliers and subcontractors on this project.

3.6.3 Westminster use tax will be due on construction tools and equipment used on the Project if a legally imposed local sales or use tax was not paid on the full purchase price of these items. If such local sales or use tax was less than that of the City of Westminster, Contractor, equipment suppliers, and subcontractors shall pay to Westminster the difference between such local sales or use tax and the tax imposed by Westminster. Any sales or use tax due Westminster may be prorated according to the time the tools or equipment are located within the City, providing an equipment declaration form is properly filed with the City. This paragraph 3.6.3 shall apply to all construction tools and equipment which had a purchase price of $2,500 or more.

3.6.4 All books and records pertaining to the Project that will allow the accurate determination of any tax due must be retained and be kept available for inspection by the City for three years after the completion of the Project.

3.6.5 All applicable taxes are to be paid by Contractor and are to be included in appropriate bid items; except that, the Contractor shall not be reimbursed for any State or other sales or use taxes incurred as a result of failure to obtain an exemption certificate prior to City’s issuance of the Notice to Proceed.

3.6.6 A copy of the Construction Equipment Declaration for Proration of Municipal Use Tax form shall be obtained from the City's Finance Department.

3.7 PERMITS, FEES AND NOTICES

3.7.1 Unless otherwise provided in the Contract Documents, the Contractor shall obtain any necessary building permits and applicable inspections and shall secure and pay for all other permits and governmental fees, licenses and inspections, including but not limited to City right-of-way permits and street cut impacts fees, necessary for the proper execution and completion of the Work, which are customarily secured after execution of the Contract and are legally required. Contractor shall secure and pay for such permits, fees, licenses, and inspections as may be required for the Work by any jurisdiction.

3.7.2 The Contractor shall give all notices and comply with all laws, ordinances, rules, regulations and lawful orders of any public authority bearing on the performance of the Work.

3.7.3 It is not the responsibility of the Contractor to make certain that the Contract Documents are in accordance with applicable laws, statutes, building codes and regulations. If the Contractor observes or in the exercise of due care should observe that any of the Contract Documents are at variance therewith in any respect, he shall promptly notify the Project Manager in writing, and any suggested changes shall be made to the Owner. The Contractor shall notify the Project Manager of all conflicts between the Drawings and Specifications and any laws, ordinances, rules, regulations, or restrictions that come to the Contractor's attention or should have come to his attention in the exercise of due care.

3.7.4 It is the responsibility of the Contractor to make certain that all his Work is done in accordance with applicable laws, statutes, building codes and regulations, and the Contractor shall bear any costs related to his failure to do so.

3.7.5 If the Contractor performs Work, including without limitations, the installation of any materials or equipment that it knows, or reasonably should know, would be contrary to laws, statutes, ordinances, building codes, rules, and regulations, the Contractor shall assume full responsibility for such work and shall bear all costs attributable to the correction thereof or related thereto, including all fines and penalties.

3.8 ALLOWANCES

3.8.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents. Items covered by these allowances shall be supplied for such amounts and by such persons as the Owner may direct, but the Contractor will not be required…