Exhibit B is a metering installation specification document for Anchor Bay Schools in Michigan, detailing the deployment of utility monitoring devices across eight school facilities as part of a Kitchen Utility Monitoring RFP. The installation schedule identifies specific meter types and quantities for each school campus: Great Oaks requires 24 total devices including variable displacement (VD-8"), variable temperature (VT), and various meter designations (RP-E, RP-D, LP-B, AHU, RF); New Anchor Bay High School requires 24 devices; Light House Elementary requires 24 devices; Lottie Elementary requires 8 devices; MacDonald Elementary requires 14 devices; Maconce Elementary requires 15 devices; Middle School North requires 27 devices; Middle School South requires 18 devices; and Naldrett and Ashley Elementary schools require additional monitoring equipment. The total scope encompasses 135 utility monitoring devices to be installed across all facilities, with meter placements identified by specific codes corresponding to different utility measurement points such as return paths (RP), load paths (LP), exhaust fans (EF), makeup air units (MUA), roof-top units (RTU), and air handling units (AHU).

The document serves as a technical specification exhibit establishing the exact metering infrastructure requirements for the school district's utility monitoring initiative. No pricing terms, contract duration, award dates, response deadlines, or financial details are specified within this exhibit, which functions purely as an enumeration of equipment specifications and installation locations required to support the broader Kitchen Utility Monitoring project across the Anchor Bay Schools system.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT B. METERING INSTALLATION

School Name Panel VD-8" VT HD 300A Great Oaks RP-E 1

RP-D 7

LP-B 2

AHU-4 RF 3

AHU-4 SF 3

New Anchor Bay HS SF-1 3

SF-2 3

EF-81 3

EF-82 3

DP-K 1

RP-KK1 1

RP-KK2 1

RP-KK3 1

AHU-29 3

AHU-28 3

Light House Elementary RP-G 3

RP-J 3

KP-1 1

KP-2 1

RP-K3 1

EF 3

MUA 3

Lottie Elementary LP-C 4

RP-G 1

RP-F 1

RTU-1 3

MacDonald Elementary RP-E 1

RP-D 5

LP-B 2

AHU-4 6

Maconce Elementary RP-D 4

LP-B 2

RP-E 1

AHU-4 6

RP-EE 1

Middle School North RP-K1 1

RP-K2 1

RP-K3 1

RP-EG2 1

EF-3,5 & 6 9

RTU-2 & 3 6

Middle School South RP-EG2 3

RP-BB 1

PP-5 2-Panels 2

KP-2 1

RPAF 1

LPHG 2

RTU-2 & 3 6

Naldrett Elementary RP-L 7

RP-L5 5

RP-K 1

RP-J 10

RTU-2 3

Ashley Elementary RPN 1

RPN2 1

RTU-2 3

RTU-3 3

Total Devices 24 135