About this file

Exhibit B is a price worksheet associated with a state or local service contract opportunity for facility maintenance and operations. The contract encompasses boiler plant and cooling tower system management, requiring bidders to provide itemized monthly costs for system checks, monitoring, required testing, equipment usage, and materials/chemical costs for both boiler and cooling tower operations. Additional services include training with health and safety components, disposal fees as applicable, and miscellaneous cleaning and maintenance. Bidders must also specify one-time mobilization costs, any additional fees, and transition fees for setting, fine-tuning equipment, and coordinating the transfer from existing vendors to the selected contractor's equipment.

The pricing structure requires bidders to calculate total monthly operational costs and clearly identify all one-time fees separately, with a final total cost figure provided for the first year including mobilization and transition expenses. The worksheet format allows for systematic evaluation of cost proposals across standardized line items, enabling comparative analysis of bids. The document was last revised in July 2025 and serves as the primary cost submission vehicle for this facility services contract, with pricing transparency required across all operational categories and special project costs to facilitate fair competition and accurate budget projections.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT B

Price Work Sheet

EXHIBIT B, TABLE 1 – COST TABLE

In the following table list the cost of each item and what it will cost per month:

Bid Item
Per month Cost

Boiler Plant Requirements: System Checks, Monitoring and Required Testing

Boiler Plant Equipment Usage Cost

Boiler Plant Material/Chemical cost

Cooling Towers Requirements: System Checks, Monitoring and Required Tests

Cooling Tower Equipment Usage Cost

Cooling Tower Materials/Chemical Cost

Training including Health and Safety

Disposal Fees, if applicable

Misc. Cleaning and Maintenance

TOTAL

One time Mobilization Cost: $_______________________________________________________________________________ Additional Fees: $_____________________________________________________________________________________________ Transition fee, setting and fine tuning all equipment to meet site requirements, coordinating the transition of existing equipment to chosen vendors equipment.

Total Cost (First year with one-time fees): $ ______________________________________________________________

Exhibit B, Rev 7/2025 Page 1 of 2