This is a Statement of Work (SOW) for construction services at Fermi National Accelerator Laboratory. The project, dated February 11, 2026 (Revision 0), is managed by Brian Rubik and supports the Infrastructure Services Division (ISD).

The scope of work involves removal of existing gravel and construction of a new electrical grounding loop and asphalt pad adjacent to the MC-2 (Mu2e) building at Fermilab in Kane County, Illinois. The new asphalt pad will support gas storage racks for the Mu2e experiment, which require electrical grounding. The subcontractor must furnish all supervision, labor, materials, tools, equipment, and appurtenances necessary for project completion in accordance with Drawing Set 6-10-35 (MU2E ASPHALT PAD IMPROVEMENT PROJECT, dated November 6, 2025) and four specification sections covering general requirements, environment/safety/health requirements, submittals, and quality requirements. All work includes transportation, overhead, bonding costs, safety oversight, and quality control oversight. The subcontractor's scope is not limited to the general outline provided; specific quantities and scope definitions must be based on offeror estimates developed from the drawings, specifications, and site examination. Key deliverables include Notice to Proceed submittals per specification section 010010, product submittals and shop drawings, and closeout documentation. The project schedule requires construction completion within 60 calendar days from the Notice to Proceed issuance. Construction activities must include protection of surrounding existing fixtures such as light poles.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Mu2e Asphalt Pad

Construction Services in support of Infrastructure Services Division (ISD)

Brian Rubik Project Manager

2026 / 02 / 11 Revision 0

Subcontractor Construction Statement of Work ISD-Engineering

Fermi National Accelerator Laboratory 2

Introduction and Background

Fermilab is requiring a new electrical grounding loop and asphalt pad adjacent to the MC-2 (Mu2e) building. The project documents establish the functional and procurement requirements of the loop and pad. The new pad will be used for gas storage racks in support of the Mu2e experiment; the racks must be grounded electrically.

Location

The project is located on the Fermi National Accelerator Laboratory (Fermilab) Site, adjacent to the city of Batavia, Illinois. The project is located on the Fermilab Site situated in Kane County at the MC-2 (Mu2e) building. Access to the site is via: Wilson Road, B Road, Discovery Road, Katuz Road, Indian Creek Road, Kautz Road, the Giese Road.

Scope

Provide all work as shown on:

• Drawing Set titled 6-10-35, MU2E ASPHALT PAD IMPROVEMENT PROJECT, dated 6 November 2025

• Specification Sections:

o 010010 GENERAL REQUIREMENTS o 013100 ENVIRONMENT, SAFETY, AND HEALTH REQUIREMENTS o 013300 SUBMITTALS o 014100 QUALITY REQUIREMENTS

The Subcontractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings and technical specifications.

The Subcontractor’s scope of work is not limited to the general work outline described herein.

The Subcontractor shall perform all work required to complete the construction work in accordance with the drawings and/or specifications. The description and quantities listed are general in nature and are only intended to describe the range and complexity of this scope of work. The description and quantities provided below are not to be used as the basis for establishing a cost proposal. Specific quantities and definitions of the scope of work for providing a proposal shall be based solely on estimates developed by the Offeror from the drawings, specifications, and the information obtained from examining of the project site.

The work under this project consists of removal of existing gravel and construction of new electrical grounding loop and asphalt pad. Activities will include protecting the surrounding existing fixtures such as light poles from construction activities.

Subcontractor Construction Statement of Work ISD-Engineering

Fermi National Accelerator Laboratory 3

Deliverables

The following is a list of major deliverable events with a description of FFDG’s expectation of the minimum requirements for accepting each deliverable.

• Notice to Proceed Submittals o Provide submittals referenced in Specification section 010010 General

Requirements

• Product Submittals & Shop Drawings o Provide product submittals and shop drawings as described in the drawings and specifications

• Closeout Documentation o Provide closeout documentation on completion of construction as described in the drawings and specifications.

Schedule

The following table lists each deliverable milestone and FFDG’s expectation of scheduled calendar days for each phase. Calendar days are listed from project start. Values in parenthesis are calendar days from completion of the previous listed entry.

Milestone Calendar

Days Description

1 0 (+0)

Notice to Proceed (NTP). This Milestone marks the point where construction work may begin.

2 60 (+60)

Construction complete.