Statement of Work (SOW) For AN/APR-39 Radar Warning Receiver Antenna
20 January 2022
PREPARED BY:
CECOM ILSC/ ESI
Document Revisions
| Date |
| Section / Paragraph / Item |
| Revision |
Table of Contents
| 1.0 | Scope | 1 |
| 2.0 | Applicable Documents | 1 |
| 3.0 | Requirements | 1 |
| 3.0.1 Surge Requirement | 1 | |
| 3.1 | Requirements for Configuration | 2 |
| 3.1.1 | Product Definition Information | 2 |
| 3.1.2 | Configuration Change Process | 2 |
| 3.1.3 | CIPN Configuration Baseline | 2 |
| 3.1.4 | Configuration | 2 |
| 3.1.5 | Application Management | 2 |
| 3.1.5.1 | Application Management | 2 |
| 3.1.5.2 | Application Activity | 3 |
| 3.1.5.3 | Departures from CB | 3 |
| 3.1.5.3.1 | Request for Change (RFC) | 3 |
| 3.2 | Requirements for Quality Assurance System | 4 |
| 3.2.1 | Quality Approach | 4 |
| 3.2.2 | Initial Quality Planning | 4 |
| 3.2.3 | Document Control | 4 |
| 3.2.4 | Records | 5 |
| 3.2.5 | Control of Purchases | 5 |
| 3.2.6 | 5 | |
| 3.2.7 | Materials Control | 5 |
| 3.2.8 | Nonconforming Material | 5 |
| 3.2.9 | Corrective Action | 5 |
| 3.2.10 | Manufacturing Operations/Process Controls | 5 |
| 3.2.11 | Quality Audits | 5 |
| 3.2.12 | Training Requirements | 5 |
| 3.2.13 | Continuous Process Improvement | 6 |
| 3.3 | Inspection and Testing | 6 |
| 3.3.1 | Requirements for Contractor Performed First Article Testing. | 6 |
| 3.3.1.1 | General | 6 |
| 3.3.1.2 | Test Requirements | 6 |
| 3.3.1.3 | Production of First Article Units | 7 |
| 3.3.1.4 | Test Plan | 7 |
| 3.3.1.5 | Notice of FAT Performance | 7 |
| 3.3.1.5.1 | Selection of First Article Samples | 7 |
| 3.3.1.5.2 | Reporting of FAT Failures | 7 |
| 3.3.1.6 | FAT Report | 7 |
| 3.3.1.6.1 | General Data. | 8 |
| 3.3.1.6.2 | Cross Reference | 8 |
| 3.3.1.6.3 | Test Results | 8 |
| 3.3.1.6.4 | FAT Failures | 8 |
| 3.3.1.6.5 | FAT/Production Discrepancies | 8 |
| 3.3.1.7 | FAT Approval | 8 |
| 3.3.1.8 | FAT Samples and First Production Lot Inspection | 9 |
| 3.3.1.8.1 | 9 | |
| 3.3.1.9 | Disposition of First Article Samples | 9 |
| 3.3.1.9.1 | 9 | |
| 3.3.1.9.2 | 9 | |
| 3.3.1.9.3 | 9 | |
| 3.3.1.10 | Production Test Procedures | 9 |
| 3.3.1.10.1 | 9 | |
| 3.3.1.10.2 | 9 | |
| 3.3.1.11 | Use of FAT Samples as a Manufacturing Standard | 9 |
| 3.3.2 | Requirements for Electromagnetic Interference (EMI) | 10 |
| 3.3.2.1 | EMI Test Plan | 10 |
| 3.3.2.2 | EMI Qualification Testing | 10 |
| 3.3.2.3 | EMI Test Report | 10 |
| 3.3.2.4 | General | 10 |
| 3.3.2.4.1 | Government Conditional Acceptance of Lots | 10 |
| 3.3.2.4.2 | Delivery Authorization | 11 |
| 3.3.2.4.3 | Shipment of Failed Items | 11 |
| 3.3.2.5 | Notification of Environmental (Group C) or Group D Testing | 11 |
| 3.3.2.6 | Test Reports | 11 |
| 3.3.2.6.1 | Environmental Reports | 11 |
| 3.3.2.6.2 | 12 | |
| 3.3.2.7 | Group D and Environmental Test Failure Reporting | 12 |
| 3.3.2.7.1 | 13 | |
| 3.3.2.8 | Corrective Action | 13 |
| 3.3.2.8.1 | 13 | |
| 3.4 | Requirements for Contractor Performed Unit Level Acceptance Testing. | 13 |
| 3.4.1 | 13 | |
| 3.4.2 | Measuring, Testing, and Inspection Equipment | 14 |
| 3.4.3 | Inspection and Test Status | 14 |
| 3.5 | Technical Review Meetings | 14 |
| 3.6 | Requirements for Item Marking (Gov't Detailed and/or Performance Design Items) | 14 |
| 3.6.1 | Part Number Marking | 14 |
| 3.6.2 | National Stock Number (NSN) Marking | 14 |
| 3.6.3 | Serial Number Marking | 15 |
| 3.6.3.1 | 15 | |
| 3.6.3.2 | 15 | |
| 3.7 | Requirements for Item Unique Identification (IUID) | 15 |
| 3.7.1 | IUID Marking | 15 |
| 3.7.1.1 | New items | 15 |
| 3.7.1.2 | Commercial Markings | 15 |
| 3.7.1.3 | Permanency and Legibility | 15 |
| 3.7.1.4 | Deleterious Effect | 16 |
| 3.7.1.5 | Mandatory Information Reporting for all items requiring IUID marking | 16 |
| 3.7.1.6 | Wide Area Workflow (WAWF) | 16 |
| 3.7.2 | IUID Coding | 16 |
| 3.7.2.1 | 16 | |
| 3.7.2.2 | 16 | |
| 3.7.2.3 | 16 | |
| 3.7.3 | Pricing of IUID Requirements | 17 |
| 3.8 | Requirements for Applying Chemical Agent Resistant Coating (CARC). | 17 |
| 3.8.1 | Technical Requirements for Chemical Agent Resistant Coating: | 17 |
| 3.8.2 | Verification – Visual Inspection Criteria. | 17 |
| 3.8.3 | Touch-up | 17 |
| 3.8.4 | Coating Thickness | 18 |
| 3.8.5 | Exceptions: | 18 |
| 3.8.6 | Marking for CARC | 18 |
| 3.9 | Handling, Storage, Preservation, Packaging, and Shipping | 18 |
| 3.9.1 | Shipping Address | 18 |
| 3.9.2 | Requirements for Packaging | 19 |
| 3.9.3 | Wood Packaging Material | 19 |
| 3.10 | Diminishing Manufacturing Sources and Material Shortages (DMSMS) / Obsolescence Management – Production | 22 |
| 3.10.1 | Definitions | 22 |
| 3.10.2 | DMSMS Management Program | 22 |
| 3.10.3 | DMSMS Management Plan | 22 |
| 3.10.4 | Design Changes | 22 |
| 3.10.5 | Subcontractor Management | 23 |
| 3.10.6 | DMSMS Costs | 23 |
| 3.10.7 | DMSMS BOM Establishment & BOM Monitoring | 23 |
| 3.10.8 | DMSMS BOM Delivery | 24 |
| 3.10.9 | DMSMS Alerts | 24 |
| 3.10.10 | Case Management | 24 |
| 3.10.10.1 | DMSMS Case Management Reports | 24 |
| 3.10.11 | DMSMS Roadmap | 24 |
| 3.10.12 | Metrics Report | 25 |
| 3.10.13 | Obsolescence Working Group (OWG) | 25 |
| 3.11 | Security | 25 |
| 3.11.1 | Threat Awareness Reporting Program | 26 |
| 3.12 | Technical Data | 26 |
| 3.12.1 | CAD Software | 27 |
| 3.12.1.1 | 27 | |
| 3.12.2 | On-Line Access to Data | 27 |
| 3.12.3 | Delivery Requirements for Classified Data | 28 |
| 3.12.4 | Audit of Product Data | 28 |
| 3.12.5 | Flow Down Requirement | 28 |
| Appendix 1 | 29 | |
| Appendix 2 | 31 | |
| Appendix 3 | 33 |
1. Scope This Statement of Work (SOW) defines the work efforts required for the Acquisition of the Radar Warning Receive System items. The contractors shall provide the price quotes for on each National Stock Number (NSN) identified in Table 1 below as requested by the government.
Table 1:
| National Stock Number (NSN) |
| Item Description/CI |
| 5841013586775 |
| Left Antenna |
| 5841013586774 |
| Right Antenna |
Applicable Documents The latest approved revisions of the documents contained in APPENDIX 1 are applicable to the extent specified. The Contractor shall report any conflicts within this SOW or documents referenced herein to the Procuring Contracting Officer (PCO) for resolution.
Requirements The contractor shall produce the items in Table 1 of this Statement of Work SOW and in delivery orders issued by the Government in accordance with Documents listed above and this SOW. In the event of a conflict between the requirements of this SOW and any drawings for the item on contract, the requirements of this SOW shall govern.
3.0.1 Surge Requirement
a. During the course of performance of the requirements identified in this SOW, it is possible that the anticipated effort could potentially expand by as much as 30% depending on Army’s plans to review and implement an increase of support initiative. This 30% within scope “surge” could require the anticipated level of effort to be potentially increased by as much as 30% of the anticipated, on-going support hours, and OPTEMPO. Offerors are requested to utilize the 30% surge figure as a baseline in developing proposed pricing for this task, to ensure an adequate level of support is maintained. The current TEMPO can be modified to become more flexible and agile enough to provide world class support as the Army’s missions evolve. Due to the complexity of the current environment and missions, support requires agility and diversity to support evolving missions.
b. The Offeror shall propose the prices for the Standard Delivery Schedule and Surge Delivery Schedules (Accelerated Delivery Schedule and Increased Quantity with Acceleration Delivery Schedule) as specified in the solicitation.
c. The contractor shall maintain its surge capability to produce and deliver the surge quantity identified in solicitation/contract. The Government reserves the right to exercise either the Standard Delivery Schedule or Surge Delivery Schedules in any Delivery Orders.
Requirements for Configuration
Product Definition Information The Product Definition Information describes a product’s performance, functional and physical attributes, including the requirements and design information (specifications, drawings, design descriptions and software). Interfaces, including interfaces with other products, are also documented in the Product Definition Information. The Product Definition Information shall be specified by the Contractor’s Item Part Number (CIPN).
Configuration Change Process The contractor shall establish a system for managing the configuration changes to the CIPN baseline.
CIPN Configuration Baseline The CIPN, as defined by the Contractor’s specifications, drawings, catalog page, etc., at the time of award of this contract, shall form the Configuration Baseline for this acquisition.
The applicable Configuration Baseline (CB) for the listed Configuration Item (CI)/Computer Software Configuration Item (CSCI) is listed in Table 1.
Configuration Each CI/CSCI, as developed/built and delivered, shall conform to the cited CB and if applicable, any subsequent CB’s that will be made contractually binding by the PCO.
Application Management
Application Management In performing Application Management, the Government must assess the impact of design changes to the Configuration Item. The Government is the Configuration Management authority on application management for all external applications and for all Major changes that affect the CIPN specified in paragraph 3.1.1. A Major change is defined as any change that will impact any of the following conditions of the CIPN:
a) Overall performance and Form, Fit, Function and Interface (F3I) Characteristics
b) Reliability, Maintainability and Survivability
c) Electromagnetic Interference (EMI), air worthiness certification, or other pertinent requirement
d) Safety
e) Support, operational and training requirements
f) Impact on Technical Manuals, Repair Parts and Special Tools Lists (RPSTLs), DMWRs, Provisioning Parts List (PPL), etc.
g) Impact on Cost and/or Schedule
h) Impact on test equipment, support equipment and associated software
i) Software Application Activity The Government is an Application Activity (AA) for changes that affect the CIPN. The Government does not possess document change authority over the changes affecting the CIPN. As part of the Government’s Application Management process, the Government as AA does have a right to review or be notified of changes made by the Contractor that will affect any of the conditions identified in paragraph 3.1.5.1. Any changes that affect these conditions shall be submitted for Government review or notification in accordance with (IAW) the procedures outlined below (para 3.1.5.3). Configuration changes not directly affecting the configuration baseline conditions identified in paragraph 3.1.5.1 do not require Government review or notification.
Departures from CB As required changes that affect the CIPN conditions cited in paragraph 3.1.5.1 shall be submitted within 30 days for Government review or notification in accordance with this SOW and the DD Form 1423 for CDRL A001 for DI-MISC-80711A. Upon receipt of notification, the Government will review the impact of the change within 30 days.
Request for Change (RFC) The Request For Change (RFC) includes both the engineering change and the supporting documentation by which the change is described and suggested. An RFC describes changes to the CI/CSCI and associated Contractor documents and data (if applicable) that are affected by the proposed engineering change. The RFC also describes a full impact analysis of the effect of the change on the logistics, interface, design, cost and schedule requirements of the CIPN.
RFCs could be generated as any of the following categories: Change Directive; Change Request; Engineering Change Package; Engineering Change Proposal; Engineering Change Request; Engineering Change Memo; Engineering Change Notice.
RFCs may contain some of the following elements:
a) A unique change identifier; identification of originating organization and responsible individual
b) Change classification
c) Identification of product(s) (including components and interfacing products) affected by the change
d) Change description and scope (including effects on performance, operation, maintenance, servicing, operation and maintenance training, repair parts, support and test equipment, cost, schedule, and any other effect on physical, functional, and logistics characteristics of the CIPN)
e) Reason and justification for the change and consequences of not incorporating the change
f) Estimated cost increase or savings
g) Change implementation (and effectivity) and impact on delivery schedule
h) Criteria, if any, for retrofitting products
Engineering Change Proposal (ECP) includes both the engineering change and the supporting documentation by which the change is described and suggested. An ECP describes changes to the CI/CSCI and associated Government documents and data that are affected by the proposed engineering change.
A Notice of Revision (NOR) shows the detailed changes that must be made to technical documentation, except specifications, (one NOR per document) following approval of an ECP. The NOR is submitted as part of the ECP.
A Specification Change Notice (SCN) is used to delineate the exact change(s) in a specification that will be distributed to users when the ECP is approved. The SCN is submitted as part of the ECP. The SCN is not used for a military or federal document, only a Request for Waiver can be used for those documents.
Value Engineering Change Proposal (VECP) is the same as an ECP except there are proposed cost savings for the program. The contractor shall follow the guidance in Section I of this contract for VECPs.
Request for Waiver (RFW) describes a departure from configuration documentation for a specific number of units or period of time. Contractor shall identify the impact of the RFW on performance, operational readiness and logistics support of the affected CIs. The Government will require compensation for any RFW.
Contractor shall provide all supporting program or cost data with the CCD. The contractor shall uniquely and sequentially identify (including the use of the contract number) each ECP, VECP, NOR, SCN or RFW. The identification number should use less than 16 characters.
Requirements for Quality Assurance System The contractor shall maintain a Quality Assurance System for higher-level product integrity that meets or exceeds the requirements established below. These requirements are commonly accepted practices employed by industry in both national and international manufacturing environments.
Quality Approach The contractor shall establish/maintain a quality approach to ensure higher-level product integrity and to satisfy contract or order requirements.
Initial Quality Planning The contractor during the earliest practical phase of the contract shall conduct a complete review of the contract requirements to identify all the resources necessary for assuring product integrity.
Document Control The contractor shall establish/maintain procedures that control the adequacy, completeness, currentness, and changes of all documents (work instructions, drawings, specifications, etc.).
Records The contractor shall maintain and utilize all records required for effective operation of the quality approach. The quality approach shall ensure that these records are complete (including subcontractor records) and reliable.
Control of Purchases The contractor shall ensure that all supplies and services purchased from suppliers conform to contract requirements. The contractor shall require that their subcontractors control the product integrity of their services and supplies.
The contractor shall deliver a Supply Chain Risk Management Plan IAW CDRL A002 DI-MGMT-82256. This shall be a separately priced CLIN.
Materials Control The contractor shall maintain controls over all materials and products throughout the manufacturing process. These controls shall enable the identification of materials that have passed inspection from those which have not. The contractor shall maintain records identifying the status and final destination of all materials/products.
Nonconforming Material The contractor shall establish and maintain a system for controlling material that does not satisfy contract requirements, including procedures for its identification, segregation, and disposition (rework/repair, scrap, etc.).
Corrective Action The contractor shall promptly detect nonconforming material and conditions adverse to product integrity. It shall then initiate the corrective actions required to satisfy contract requirements.
Manufacturing Operations/Process Controls The contractor’s quality approach is responsible for assuring/monitoring that all manufacturing operations/processes are accomplished under controlled conditions. Controlled conditions include documented work instructions (including workmanship), place of performance, production equipment, special work environments, inspections/tests, work specifications, and approval/rejection criteria.
Quality Audits The contractor shall perform internal quality audits to verify the effectiveness of their quality approach.
Training Requirements The contractor shall identify/provide for the training needs of their personnel performing quality functions.
Continuous Process Improvement The contractor shall monitor the effectiveness of their quality approach and continually improve quality processes.
Inspection and Testing The quality approach shall assure that all inspections and tests required satisfying contract or order requirements are conducted. Inspection and testing requirements for each item are in accordance with the established drawing and part numbers listed in Table 1.
Requirements for Contractor Performed First Article Testing.
General If the contractor has not previously produced these items, the contractor shall perform First Article Testing (FAT) in accordance with FAR 52.209-3 (see Section I of this contract) and this SOW. As part of FAT, the contractor shall:
a) Select the test unit(s) used for FAT from the first production lot.
b) Develop the test procedures and plans necessary to demonstrate that these units conform to the requirements established by the applicable specification(s) and other technical data provided in this contract.(Para 3.3.1.4)
c) Notify the Government and test the First Article units. (Para 3.3.1.5)
d) Provide a First Article Test Report to the Government which documents the FAT results. (Para 3.3.1.6)
e) Insure all equipment used to take performance readings for acceptance tests are kept within the performance parameters delineated by the manufacturer of that equipment. All equipment manufactured by the contractor shall be listed with the parameters established and maintained for this equipment also.
Test Requirements The following test requirements shall be verified as part of FAT when the first order is placed or place of manufacture has changed:
AN/APR-39A(V) Group A, B, C, D Electromagnetic Interference (EMI)/ Electromagnetic Compatibility (EMC) and burn in IAW ER-SS-3012-001D.
SM-674A/UPM Group A, B, C, D and burn in IAW ER-SS-3009-001D, and this SOW.
MX-9848A/APR-39(V) Group A, C, and EMI/EMC IAW ER-SS-3012-001D, A3084248, A3084249 and this SOW.
The contractor will build the required items that will go through FAT in order to meet first article requirements for all spares and systems listed in this SOW. All spares shall begin being shipped after FAT requirements are met and approved on the four AN/APR-39A(V)1’s. FAT will be waived if end item AN/APR-39A(V)1 has already been subjected to and passed FAT, in the past four years by the contractor, or determined by the government, using the current design of the AN/APR-39A(V)1.
Production of First Article Units All FAT samples shall be assembled at the same location at which production units will be assembled, using the same parts, materials, and manufacturing processes to be employed for subsequent production.
Test Plan The contractor shall prepare and submit a First Article Qualification Test Plan in accordance with CDRL F001 DI-NDTI-81307 as implemented by the DD Form 1423 for DI-NDTI-81307. In addition to the information required by CDRL F001 DI-NDTI-81307, this submission shall contain:
a) The delineation and allocation of tests to be performed on each of the First Article units and the order of such tests (this may be prescribed in applicable technical data).
b) Step-by-step test procedures for each test and the data sheets (see 3.3.1.6.3) to be employed to document the results of testing.
c) Identification of required test facilities, equipment and calibration dates of equipment and personnel.
d) Test milestones schedules and the contractor's test readiness posture.
e) A table which cross references the paragraph number of the specification requirement (including a brief description of the requirement) and the associated paragraph number of the First Article Qualification Test Plan.
Notice of FAT Performance As required by FAR 52.209-3, written notices concerning the time and location of FAT shall be furnished to the PCO, the Administrative Contracting Officer and the Government Technical Activity listed in Block 6 of the DD Form 1423 for CDRL F002 DI-NDTI-82326.
Selection of First Article Samples When Initial Production FAT applies to this contract (i.e., when FAR 52.209-3 ALT I is specified in Section I), four (4) FAT samples shall be selected at random from the initial production lot.
Reporting of FAT Failures Reporting of FAT failures shall be by the FAT Report, in lieu of any other reporting requirements specified in this contract. In addition, FAT failures shall be verbally reported to the Government’s Quality Assurance Representative (QAR) and Government Technical Activity listed in Block 6 of the DD Form 1423 for CDRL F002 DI-NDTI-82326.
FAT Report A FAT Report shall be prepared and submitted in accordance with FAR 52.209-3 and CDRL F002 DI-NDTI-82326 as implemented by the DD Form 1423 for CDRL F002 DI-NDTI-82236. The FAT Report shall be complete, accurate, and readable and shall provide sufficient data to determine that the hardware item meets all the requirements delineated in the contract. The report will include the following:
General Data.
a) Contractor's name and address.
b) Contract number.
c) Nomenclature, type number and (if assigned) stock number of item represented by the First Article.
d) Name and address of plant where First Article was fabricated and assembled.
e) Place and date of performance of tests.
f) Identification (including date) of applicable equipment specifications and associated amendments.
g) Sample size or quantity submitted for test or inspection.
Cross Reference A table which cross-references the paragraph numbers of the specification, the test procedures, and data sheet entry.
Test Results Complete test results showing actual or quantitative observations and all required calculations. ‘GO/NOGO’ data is allowable (under certain circumstances) only with prior Government approval. Allowable tolerances for each parameter shall be presented. Test data should also include the date that the test was performed, name and signature of tester, name and signature of the Government verifier/witness (if applicable) and serial number of the equipment. Test results shall cite detailed qualitative and quantitative data results such as test categories, test conditions, test methods employed, and types of inspection and test equipment used during the test or inspection.
FAT Failures FAT failures shall list all requirements not complied with during FAT. If none, this should be explicitly stated. For each requirement not met, a corrective action to remove the noncompliance will be proposed. This corrective action must include retest or other verification that the corrective action does remedy the problem/failure. The corrective action will address changes in design or manufacturing process which will preclude this deficiency in subsequent production units. Verified corrective action must be implemented prior to contractor entering into production.
FAT/Production Discrepancies Any Government approved (see paragraph 3.3.1.3), difference between the parts, materials and processes used to manufacture FAT samples and production units shall be documented in the FAT report.
FAT Approval FAT samples shall meet all contractual requirements or all variances shall be documented by Government approved waivers. First Article approval will be contingent upon the submission of a complete and acceptable FAT report to include verification of corrective action for reported FAT failures to include adequacy of identified changes to the design/manufacturing process.
FAT Samples and First Production Lot Inspection If FAR 52.209-3 ALT II is specified in Section I, First Article units shall be utilized to satisfy initial production lot inspection requirements. If the quantity of First Article samples is less than that needed to satisfy first production lot sampling requirements, additional samples shall be selected at random from the production lot and inspected to meet first production lot acceptance requirements.
When Initial Production FAT (FAR 52.209-3 ALT I and ALT II) applies and additional units are tested to satisfy production acceptance requirements, failures for these additional units shall be reported as specified in this contract.
Disposition of First Article Samples Upon successful completion of FAT, the contractor shall dispose the FAT samples in the following order:
Four (4) samples shall be retained at the contractor's facility for use as a reference by the QAR.
No Other samples shall be shipped to the Government for further testing.
The first article samples may not be acceptable as production items. Those items which are not refurbishable shall not be delivered as production items. Items which are refurbishable and made fully compliant with contractual requirements shall be delivered as production items. The Government shall determine the acceptability of all FAT samples.
Production Test Procedures Production test procedures used to test production units shall be identical to those used to test First Article samples.
Once FAT is approved, proposed changes to the production test procedures will be submitted to the Government Technical Activity (see paragraph 3.3.1.6) for evaluation. Such submissions will provide complete justification for the change. Changes to the approved test procedures shall not be implemented without written Government approval.
Any notice of approval of test procedures or changes thereto shall not relieve the contractor from complying with all contractual requirements.
Use of FAT Samples as a Manufacturing Standard The FAT samples shall NOT serve as a manufacturing standard.
Requirements for Electromagnetic Interference (EMI) The contractor shall provide the necessary technical expertise to assure that the EMI requirements of this SOW are implemented.
EMI Test Plan The contractor shall prepare an EMI Test Plan in accordance with CDRL F003 DI-NDTI-80201C as implemented by the DD1423 for DI-EMCS-80201C. Use paragraph 4.4 of MIL-STD-461G with Notice 4 as additional guidance. The test plan shall describe how the contractor will develop test methods and procedures to assure that the test item, subsystem or system will be tested for compliance with the EMI requirements imposed by the performance specification. The general test methods and procedures of MIL-STD-462 with Notice 3 can be used as additional guidance. When First Article Testing (FAT) is required, the EMI Test Plan shall be submitted concurrently with (but separately from) the FAT Plan.
EMI Qualification Testing Upon Government approval of the EMI Qualification, EMI Qualification testing will be performed in accordance with this plan, and any subsequently approved revisions.
EMI Test Report The contractor shall prepare and submit an EMI Test Report for First Article EMI Tests (when required) and each Production EMI Test in accordance with CDRL F004 DI-NDTI-80200C as implemented by the DD Form 1423 for DI-NDTI-80200C. MIL-STD-831 and paragraph 4.5 of Notice 4 to MIL-STD-461G can be used as additional guidance. When FAT is required, the EMI Test Report shall be submitted concurrently with (but separately from) the FAT Report.
General Contract items in the first production lot shall not be delivered to the Government until environmental inspection and Group D testing is completed successfully. Delivery of lots between intervals of succeeding tests are authorized subject to the limitations below.
Government Conditional Acceptance of Lots Government acceptance of these lots is conditional. If a sample fails environmental testing or Group D testing subsequent to acceptance, the Government may discontinue acceptance and revoke acceptance of any items accepted between the previous (successful) environmental or Group D (same type) test and the environmental or Group D test where failure occurred. Furthermore, the Government may require the contractor to replace, correct or redesign at the contractor's expense, all units which were accepted between the previous environmental or Group D test and the test where failure occurred. Such corrective action (see paragraph 3.3.3.5 below) may be performed at destination, contractor's facility or any other appropriate area, as directed by the PCO. All costs resulting from the failure and corrective action shall be borne by the contractor.
Delivery Authorization When delivery is authorized prior to the performance of environmental tests, the environmental test shall be completed within sixty days after sample selection. In the event that special environmental test requirements necessitate longer than 60 days for completion, the contractor may seek an authorization for an extension from the PCO. Sample selection shall be made within the time period specified in the applicable contract provision or specification. Failure to satisfactorily complete the environmental tests within the sixty day period shall be grounds for revoking acceptance of all units accepted since the last successful environmental test, and shall be deemed a failure to make delivery within the meaning of the Default clause of this contract.
Shipment of Failed Items When items represented by samples which have failed Group D testing, environmental testing or which have an individual failure inherent in other units are shipped, the contractor shall notify the PCO via electronic mail/writing and telephonic communication within one working day of the occurrence of the failure, with copies furnished to the Administrative Contracting Officer (ACO) and the Government Technical Activity cited in Block 6 of the DD Form 1423-1 IAW CDRL F005 DI-SESS-80255B (herein referred to as 'Technical Activity'). This notification shall indicate the nature of the failure(s) and shipment(s), including the consignee(s), date(s) of shipments, carrier(s), way bill number(s) and quantity. The Government may return such shipment(s) or any portion thereof to the contractor at the contractor's expense.
Notification of Environmental (Group C) or Group D Testing The Contractor shall provide the Government Quality Assurance Representative (QAR) with advance written notice of the time and place of each test. If the Government QAR is resident at the Contractor's plant, this notice shall be provided at least two working days prior to the start of each test. If the Government QAR is not resident, notice shall be provided at least seven working days prior to the start of each test. Within forty eight hours after the Group D or environmental tests have been completed for a specific production lot, the contractor shall provide written notification to the Government QAR as to the time, date of completion and results. Environmental failures shall be reported as they occur.
Test Reports
Environmental Reports The contractor shall notify the PCO and Technical Activity in writing upon successful completion of environmental test. This notification shall be submitted not later than 10 days after the test is completed, and shall include:
- Contract Number.
- Item Identification (Nomenclature and/or Part Number).
- Date of Testing.
If the contractor is required to perform First Article Testing (FAT), the Environmental Tests performed during FAT shall be reported as part of the FAT report.
Group D and Environmental Test Failure Reporting The contractor shall report each Group D or environmental failure verbally to the Government Quality Assurance Representative (QAR) and the Technical Activity (see Block 16 of DD Form 1423-1 IAW CDRL F005 DI-SESS-80255B within one working day. For a Group D test failure this report shall indicate the effect of the failure on the accept/reject decision. Within fifteen working days of failure occurrence, the contractor shall perform and document a failure analysis in accordance with the DD-1423-1 IAW CDRL F005 DI-SESS-80255B and this SOW. In addition to the information required in DI-SESS-80255B, the following information shall be provided:
For Group D failure:
a) Contractor's name, address and applicable contract number.
b) Serial number of the equipment.
c) Identification of the subassembly in which failure occurred.
d) Identification of the major assembly in which failure occurred.
e) Identification of the category and root cause of failure (workmanship, design, etc.)
f) Definition of the failed item's application (power output transistor, diode rectifier, tuning coil, etc.).
g) Identification of similar or related parts within the system which may contain the same inherent weakness.
h) Photograph of the failed part which show the failed part in its entirety and the mode of failure or failure mechanism.
For an Environmental (Group C) test failure:
a) Contractor's name, address and applicable contract number.
b) Number of units in sample and number of failed units subjected to test.
c) Root cause of failure.
d) Environmental re-inspection plan to validate the corrective action, consisting of all applicable environmental test and examinations. The plan shall include identification of previous functional, environmental and reliability tests, if any, invalidated by the corrective action changes and recommendations of those tests, which should be repeated to prove the corrective action.
e) Proposed disposition of items in the inspection lot at time of failure of any and all inspections during environmental test and of items manufactured under the same conditions and which the Government considers subject to the same failure mechanism.
In case of failure of Group D test or a pattern failure which is inherent in other accepted units, the contractor shall:
a) Submit a corrective action plan in accordance with CDRL F005 DI-SESS-80255B as implemented by the DD1423-1 for DI-SESS-80255B as part of DI-SESS-80255B “corrective action” and shall include the following items:
(1.) Description of the corrective action.
(2.) Impact on the contract delivery schedule.
(3.) Any recommended process or process control changes.
(4.) Proposals for retrofit of all equipment already delivered or assembled, including recommended effectivity.
(5.) Disposition of all defective material and material rendered obsolete.
(6.) The cost of corrective action, retest, and any identifiable increases in cost of production items.
(7.) Identification of previous functional and environmental qualification tests invalidated by the corrective action changes, and recommendation of those tests that should be repeated to prove the corrective action.
(8.) Evaluation of the effect of the corrective action on the reliability prediction.
(9.) Effect on operational and diagnostic software programs.
b) Implement the corrective actions described in the corrective action plan on all units in the lot, select a new test sample and rerun reliability inspection starting at zero hours operating time.
c) Document results of the Group D retest in a test report prepared in accordance with the CDRL F005 DI-SESS-80255B as implemented by the DD1423-1.
Corrective Action The contractor shall implement the proposed corrective action on all units in the lot, select new samples and conduct environmental or Group D re-tests and other required re-testing in accordance with the test plan. Results of the environmental or Group D re-tests shall be submitted in accordance with CDRL F005 DI-SESS-80255B as implemented by the DD1423-1.
Final acceptance and shipment approval will be withheld until results of the retest substantiate that the corrective action was effective, as authorized by the PCO. Inability to ascertain root cause of failure or provide corrective action may result in termination of this contract.
Requirements for Contractor Performed Unit Level Acceptance Testing.
After producing the items, the contractor shall test the items to ensure that it meets the operational & performance requirements of the subject antennas (Part Numbers: A3084248 & A3084249). The contractor shall use Section 4.2 of drawing numbers A3084248 & A3084249 to show acceptance of items. Contractors can use their own acceptance test procedure if approved by the Government Task Leader.
A Government witness for the final test is required, but is not required for the intermediate tests. DCMA will sign-off as witnessing the intermediate tests.
Measuring, Testing, and Inspection Equipment The contractor shall provide and maintain gages (including production tooling used for inspection purposes) and other measuring and testing equipment to assure that products conform to contract requirements. These devices shall be calibrated against certified measurement standards that are traceable back to national/international standards.
Inspection and Test Status The contractor shall maintain a system for the identification of the inspection and test status of all products throughout all stages of the manufacturing cycle.
Technical Review Meetings The Contractor shall host up to five (5) one-day Engineering Technical Interchange Meetings (TIMs) at the Contractor’s facility during the period of performance. Engineering TIMs may be conducted concurrently with other APR-39 program meetings.
Requirements for Item Marking (Gov't Detailed and/or Performance Design Items)
Part Number Marking Each item delivered under contract, along with each assembly, sub assembly, and module, shall be legibly marked with the appropriate part number and manufacturer’s identification. Hardware such as screws, nuts, bolts, etc., need not be marked. The marking shall become permanently part of the item after it is applied, and can be applied using deformation, tag, rubber stamp with permanent characteristics, etc. The marking shall not interfere with proper operation of the item, and shall have no deleterious effect on the item. Any item deemed unsuitable for marking as outlined herein shall be identified to the Contracting Officer for resolution as to marking requirement. This requirement may be entirely met by existing marking requirements contained within the drawings or specifications cited in this contract.
National Stock Number (NSN) Marking In addition to the marking required by para 3.7.1 above, each item on contract listed in Section B of the contract, shall be identified with its Government assigned NSN. The intent of this requirement is to ensure that using personnel can identify the circuit card or assembly when it is removed from its assembly, and when it is received from stock as a spare part. The marking can be on a paper label, placed in a location that will not harm the item. If guidance is necessary to implement this requirement, contact the Contracting Officer for guidance.
Serial Number Marking
Any item or subassembly which contains a serialization requirement shall have serial numbers applied to each item in the place provided (generally on a nameplate/serial number plate). In addition the NSN, CAGE Code, Part Number and if space permits Contract Number shall also be applied. When applicable, the Unique Item Identification (UID) requirements, cited elsewhere in this SOW, shall also apply.
The contractor shall maintain an accurate, current list of serial numbers for all manufactured items under this contract. Dates of manufacture, substitutions, shop changes, etc. shall be included on this list. The list shall be available for inspection by the PCO or government representative at any time during the life of the contract and for a period of 3 years following the completion of the contract.
Requirements for Item Unique Identification (IUID) The contractor shall mark all contract deliverables In Accordance With (IAW) Defense Federal Acquisition Regulation Supplement (DFARS) clause 252.211-7003 in Section F of this contract and the following requirements.
IUID Marking
New items The contractor shall provide IUID, or DoD recognized equivalent, for all items delivered with a per unit acquisition cost of $5000 or more. For long term contracts, the Contractor shall implement IUID markings IAW MIL-STD-130N w/Ch1, dated 16 Nov 12 for any item that will exceed the $5,000.00 unit price for any range quantity or contract year. This requirement is effective throughout the life of this contract.
For items which currently have IUID Marking requirements defined on its applicable drawing, the contractor shall continue to apply IUID Marking directly to those items. For all other items that do not currently have IUID Marking requirements on it’s applicable drawing, the contractor shall individually package each item and apply the IUID marking to each individual items packaging.
Commercial Markings All other items shall have acceptable commercial markings that meet the guidelines in Department of Defense (DoD) Guide to Uniquely Identifying Items http://www.acq.osd.mil/dpap/pdi/uid/index.html.
Permanency and Legibility The IUID marking and identification plates, tags, etching, or labels when used on equipment, parts, assemblies, subassemblies, units, sets, groups, or kits shall be as permanent as the normal life expectancy of the item and be capable of withstanding the environment, test, cleaning, repair, and rebuild procedures specified for the item. Legibility shall be as required and verified for ready readability per MIL-STD-130N w/Ch1, dated 16 Nov 12.
Deleterious Effect Marking of items shall be accomplished in a manner that will not adversely affect the life and utility of the item. Marking materials creating hazardous conditions shall not be used. Placement and choice of the marking shall not create hazardous conditions.
Mandatory Information Reporting for all items requiring IUID marking The contractor shall include the NSN, if the item has a NSN, the Serial Number marked on the item, if a Serial Number is marked on the item, the original part number, the current part number (only if not the same as the original part number), the current part number effective date (only if the current part number is used) and the USARMY as the SERVICE /AGENCY/COMMAND data element in the information reported to the IUID Registry, in addition to the information required to be reported to the IUID Registry by DFARS clause 252.211-7003.
Wide Area Workflow (WAWF) Users shall report this mandatory information to the IUID Registry by Direct submission via an X12 Ship Notice/Shipment and Billing Notice (856/857) transaction, an IUID XML transaction, an IUID flat file transaction or a WAWF IUID Material Inspection and Receiving Report/Combo UDF through the Global Exchange (GEX) Service, or manually, via the IUID Web Entry Site at http://www.bpn.gov/iuid. For WAWF users, these methods do not replace the current WAWF interaction, but are performed in addition to it after the shipment has been accepted to provide IUID data that cannot be provided via WAWF. WAWF users access through the website Procurement Integrated Enterprise Environment (PIEE) https://piee.eb.mil/.
IUID Coding IUID markings and readability requirements shall comply with MIL-STD-130N w/Ch1, dated 16 Nov 12.
Symbology markings and the order of priority for marking the hardware shall be in accordance with MIL-STD-130N w/Ch1, dated 16 Nov 12. First priority is the 2D data matrix symbol (machine readable) IUID is the minimum requirement when there are severe space limitations. The second priority is the human readable characters. The third priority is the Linear Bar Code.
If the technical data has not specified the marking location, markings shall be located such that they are visible during item use, provided that sufficient space is available, and does not interfere with equipment operations.
The contractor shall maintain an accurate, current list of IUIDs for all manufactured items on this contract. Dates of manufacture, substitutions, shop changes, etc. shall be included on this list. The list shall be available for inspection by the PCO or other Government representative at any time during the life of this contract. The contractor shall provide this list to the government at the end of the contract.
Pricing of IUID Requirements All efforts required by this SOW and contract, including, but not limited to, the preparation of ECPs or notification of marking deficiencies, serial number data reporting at end of contract and the actual marking of hardware, will be included in the base contract price.
Requirements for Applying Chemical Agent Resistant Coating (CARC).
The contractor shall paint the equipment with Chemical Agent Resistant Coating (CARC) in accordance with the technical requirements below. The contractor shall prepare and submit Engineering Change Proposals (ECPs) to all documents that require changes due to the addition of the CARC finish in accordance with procedures identified in the provision for 'Configuration Control'. The contractor shall have available for Government inspection purchase orders for paint used on this contract showing use of Qualified Product List (QPL) sources.
Technical Requirements for Chemical Agent Resistant Coating:
Paint Finishes. Exterior surfaces of the equipment and interior surfaces, which may be open to the environment during operation of the equipment (such as doors), shall be painted with lusterless green 383 CARC, Color No. 34094 in accordance with (IAW) MIL-C-53039 or MIL-DTL-64159. All coatings shall be from a Qualified Product List (QPL) Source. Materials and processes used in the application of all preconditioning, passivation, pretreatments, primers and final films shall be IAW MIL-DTL-53072 and shall meet all Quality Assurance Provisions of MIL-DTL-53072. For camouflage painting or other applications such as desert colors the following Table shall be used.
Table 2:
Color matches shall be as follows:
| Color |
| Color No FED–STD 595 |
| Green 383 |
| 34904 |
| Black |
| 37030 |
| Tan 686A |
| 33446 |
| Green |
| 24533 |
| Brown |
| 30051 |
| White |
| 27875 |
Verification – Visual Inspection Criteria.
Color match on the finished assembly shall be per paragraph 3.3.3 of MIL-C-53039 or MIL-DTL-64159 as applicable.
Touch-up When piece parts have been finished with complete paint finishes, fixed assemblies shall be touched up in order to provide a continuous film across the interfaces. This requirement does not apply to hairline joints between mating parts, gasketed joints, or where moving parts such as hinges or catches are present. Touch-up paint used shall be identical to the final paint film and shall provide a reasonable color match with that of all other assembled parts.
Coating Thickness The dry film thickness of each pretreatment, primer and final film coating shall be IAW MIL-DTL-53072 except for MIL-PRF-22750 coatings which shall be minimum of 1.3 to 1.7 mils thickness.
Exceptions:
a. When applicable, elements of antennae, to include element protective covers, i.e., fiberglass shields, shall be painted in accordance with the technical data cited elsewhere in this contract.
b. Any part conforming to a Government requirement shall be finished as required by the individual part requirement.
c. Parts which may be subjected to temperatures in excess of 400 degrees F (205 degrees C) shall be painted with a heat resistant paint.
d. Parts which can be flexed should not be painted with CARC since the paint will crack.
e. Interior surfaces of shelters, if painted, shall be finished with epoxy paint IAW MIL-PRF-22750 Green, Color No. 24533 or White, Color No. 27875.
Marking for CARC The equipment shall be marked with the word 'CARC' stenciled in CARC paint in close proximity to the nameplate. A contrasting color shall be used for the marking (e.g. black marking on a green surface). The letters shall be one inch high or of appropriate size for small equipment. The marking shall be durable enough to withstand the full environmental conditions the surface will be exposed to during field use. Plates or embossed lettering may be used. Embossed letters need not be highlighted as long as they are legible.
Handling, Storage, Preservation, Packaging, and Shipping The Contractor shall establish, maintain, control and be responsible for the handling, storage, preservation, packaging and shipping to protect the quality of the materials and to prevent damage from loss, deterioration, degradation, or substitution of products.
Shipping Address
The “ship to” address is below or other destination as defined on task order/delivery order. Task order/delivery order destination will take precedent
DODAAC: W25G1W, RIC: BY6
W1BG UEF DIST DEPOT TOBYHANNA
GIBBS AND FIFTH STREETS
WAREHOUSE 6 BAY 4
TOBYHANNA PA 18466-5059
Requirements for Packaging
Preservation, packing and marking for shipment shall be in accordance with Section "D" of the contract. Marking is in accordance with MIL-STD-129R.
Radio Frequency Identification (RFID) Requirements shall be IAW the Section ‘F’ clause, DFARS 252.211-7006, of the contract.
Shipments will be marked and labeled IAW MIL-STD-129 to include the following information on the outer label:
The contractor shall include the following information on the label affixed to the outside of the shipping container:
a) Contract Number
b) Quantity of item on contract
c) Item’s part number as noted in Section B of the contract
d) Contractor’s name and address
e) NSN
f) CAGE Code
g) Part Number
h) UID
Wood Packaging Material
Wood Packaging Material (WPM) shall meet the following requirements.
Wood packaging material (WPM) includes but is not limited to pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frame and cleats. This requirement excludes materials that have undergone a manufacturing process, such as corrugated fiberboard, plywood, particleboard, veneer, and oriented strand board (OSB). See DLAD T/Q Requirement RP001 DLA Packaging Requirements for Procurement, which includes requirements for treatment of wood packaging material Failure to comply with these requirements may result in refusal, destruction, or treatment of materials at the point of entry. The Government reserves the right to recoup from the contractor any remediation costs incurred by the Government.
Table 3:
DS7029 - DS7033 LEGEND
| Qty |
| Quantity |
| Prot Req |
| Protection Required |
| PKG-REF |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .