EXHIBIT_A Specifications.pdf
PDF 197 KB Posted
- Attached to
- PIP-II PCS Flowmeters
- Solicitation number
- 386074-DSF
About this file
This is a technical specification document for equipment procurement under the Proton Improvement Plan-II (PIP-II) Building Infrastructure project at Fermi National Accelerator Laboratory. The document specifies instrumentation requirements for the Process Clean Water (PCW) System's Linac Gallery portion.
The specification requires 257 units of Series CT Coolpoint Vortex Shedding Flow Meters with temperature capability, equivalent to Dwyer Part Number CT8-M1T1C1-W1. Each meter must feature a 1-inch female NPT connection with brass body construction, operate within a 10-50 GPM minimum flow range, require 24VDC power input, provide 4-20 mA output signal through one M12 connector, and deliver a 20:1 turndown ratio. The document was released for review on July 24, 2026, and is managed by Fermi Research Alliance, LLC on behalf of the U.S. Department of Energy Office of Science.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EXHIBIT_B FFDG_General Terms and Conditions.pdf | ||
| EXHIBIT_C FL-55.pdf | ||
| EXHIBIT_E PUR-466.pdf | ||
| EXHIBIT_D SARC.pdf | ||
| RFP 386074-DSF.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PIP-II Process Clean Water (PCW) System Linac Gallery 1in Flowmeter Specification
Document number: ED0048825
Document Approval
Signatures Required Date Approved
Originator: Mike Hanson, Technical Integration
Reviewer: V. Grzelak, HPRF
Approver: M. Slabaugh, L3 Manager, Building Infrastructure
Approver:
Revision History
Revision Date of Release Description of Change
7/24/26 Initial Release for Review
PIP-II Template
Fermi National Accelerator Laboratory 2
1. Purpose
This document is part of the Proton Improvement Plan-II (PIP-II) Building Infrastructure procurement package for the Process Clean Water (PCW) System. It contains a detailed description of the instrumentation that will be procured and installed in the Linac Gallery portion of the PIP-II PCW System.
This document can be found in Teamcenter under #ED0025634.
2. Equipment Specification for Linac Gallery
Item Requirement Statement Quantity
Series CT Coolpoint Vortex Shedding Flow Meter with temperature
• Equivalent vortex meter to Dwyer Part Number: CT8- M1T1C1-W1
• Connection:1” FNPT
• Brass body
• Flow minimum:10- 50 GPM
• Power 24VDC
• Output Signal: 4-20 mA, 1 x M12
• 20:1 Turndown