This document is an Exhibit A from the Florida Department of Agriculture and Consumer Services (FDACS), Division of Administration, Bureau of General Services, detailing sitework improvements for the Suwannee State Farmers Market located in White Springs, FL. The project involves parking lot repairs and paving improvements, with work divided into six phases and including a base bid for milling and removing existing pavement, installing new asphalt, re-striping parking spaces, and maintaining drainage. The project also includes two add alternates: one for extruded concrete curbing and another for seal coating, covering approximately 850,000 square feet of paving area. The work will be performed in accordance with Florida Department of Transportation (FDOT) specifications, with the contractor responsible for material procurement, product submittals, soil density testing, and maintaining facility operations during construction.
The project includes technical specifications covering material requirements, installation procedures, and quality control measures. The base bid and add alternates specify detailed requirements for concrete mix, asphalt composition, curb installation, and seal coating application. The contractor must use Type SP-12.5 PG-76-22 Traffic Level C asphalt with up to 20% Reclaimed Asphalt Pavement Material, install extruded concrete curbing with specific dimensional and strength requirements, and apply seal coating using bituminous or coal tar emulsion-based products. The project emphasizes compliance with FDOT standards, OSHA and EPA regulations, and requires a one-year material and labor warranty. The specifications provide comprehensive guidelines for surface preparation, application methods, weather conditions, traffic control, and environmental considerations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB FFS 25 26 39_Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit A
Division of Administration
Bureau of General Services
Sitework Improvements
Date: August 8, 2025 Project: FDACS Project No.: 1151 Facility: Suwannee State Farmers Market Location: 2736 Co Rd 136, White Springs, FL 32096 Client Division: Division of Marketing and Development Commodity Codes: 30121600 Asphalt
72141103 Highway and road paving service 72141100 Infrastructure building, surfacing and paving services.
72152700 Concrete installation and repair services 72141127 Seal coating of roads, highways and parking lots
Purpose: Parking Lot Repairs and Paving Improvements
I. Base Bid
1. Furnish material and labor to mill and remove existing pavement layer in driveway and parking areas and haul debris off-site. Refer to attached exhibits for additional information.
2. Mill existing 1.5” asphalt and haul debris off of property. Install new 1.5” Type SP-12.5 PG-76-22
Traffic Level C with Reclaimed Asphalt Pavement Material (RAP) maximum of twenty percent (20%). Superpave Asphaltic Concrete (SP) shall meet Section 334, FDOT Standard Specifications.
Document, layout and re-stripe existing parking spaces in accordance with FDOT approved traffic paint (Lead-Free Thermoplastic Traffic Paint) and pavement marking standards per the recommendations of the Manual on Uniform Traffic Control Devices.
3. Spread material to uniform thickness specified and compact to appropriate density per FDOT requirements. Modify grade as necessary to maintain drainage direction and stormwater runoff of existing parking lot.
4. Existing pipe bollards shall remain, unless otherwise noted. All existing pipe bollards shall be painted, repaired and/or replaced if damaged.
5. Contractor is responsible for final grading and replacing sod in all disturbed areas of improvement.
Contractor shall water new sod until substantial completion date.
6. It shall be the contractor’s responsibility to furnish and install the material quantities necessary to complete the scope of work as illustrated on the attached exhibits.
7. All work shall be sequenced in accordance with Owner requirements to accommodate continuity of facility operations and parking. The work will commence in logical phases and may require limited weekend hours for areas of essential ingress/ egress.
8. All site improvements described herein shall be in accordance and compliance with current Florida Department of Transportation (FDOT) specifications.
9. Contractor shall provide product submittals and soil density test results for review and approval by the Owner prior to material procurement.
II. Add Alternates
Add Alternate #1: Extruded Concrete Curb Area Scope of Work and Specification
a. Reference Appendix I
Add Alternate #2: Seal Coating Area Scope of Work and Specification
b. Reference Appendix II
III. Technical Specifications
GENERAL REQUIREMENTS:
1) COMPLY WITH THE REQUIREMENTS OF THE "AGREEMENT BETWEEN OWNER AND CONTRACTOR"
IN EFFECT FOR CONSTRUCTION SERVICES FOR PROJECTS AT THE FLORIDA DEPARTMENT OF
AGRICULTURE AND CONSUMER SERVICES.
2) SUMMARY OF WORK: SEE SCOPE OF WORK AS DESCRIBED ABOVE.
3) COMPLY WITH REQUIREMENTS OF APPLICABLE PRODUCT OR TRADE STANDARDS, EXCEPT WHEN
MORE RIGID REQUIREMENTS ARE SPECIFIED OR ARE REQUIRED BY APPLICABLE CODES.
4) THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY PERMITS NEEDED FOR THE CONTRACTOR’S
OR SUBCONTRACTOR’S SCOPE OF WORK.
5) THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY SIGNED AND SEALED DRAWINGS NEEDED
TO OBTAIN IF PERMITS ARE REQUIRED.
6) SUBSTITUTIONS: ALL PRODUCTS SPECIFIED MAY BE SUBSTITUTED WITH AN APPROVED EQUAL
UNLESS SPECIFICALLY NOTED OTHERWISE. PROPOSED SUBSTITUTIONS MUST BE SUBMITTED IN
WRITING WITH SUFFICIENT SUPPORTING DOCUMENTATION FOR FURTHER EVALUATION.
OWNER CONSENT OF THE PRODUCT SUBSTITUTION MUST BE OBTAINED BY THE CONTRACTOR
PRIOR TO BID SUBMISSION.
7) COMPLY WITH THE REQUIREMENTS OF THE DEPARTMENT OF MANAGEMENT SERVICES DESIGN
& CONSTRUCTION GUIDELINES. REFER TO:
HTTPS://WWW.DMS.MYFLORIDA.COM/BUSINESS_OPERATIONS/REAL_ESTATE_DEVELOPMENT_
AND_MANAGEMENT/BUILDING_CONSTRUCTION/FORMS_AND_DOCUMENTS
8) THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CONDITIONS. IF CONFLICTS OR
DISCREPANCIES BETWEEN BUILDING SYSTEMS ARE OBSERVABLE, HE SHALL NOTIFY THE
DEPARTMENT’S PROJECT MANAGER IN WRITING FOR RESOLUTION PRIOR TO COMMENCING
CONSTRUCTION OR INSTALLATION.
9) THE CONTRACTOR SHALL LIMIT THE IMPACT OF HIS WORK ON ALL SYSTEMS, EQUIPMENT AND
SECURITY OF ALL AREAS WITHIN THE SCOPE OF THIS WORK. COORDINATE PROTECTION AND
SECURITY OF AREAS WITH THE DEPARTMENT. THE FOLLOWING SPECIFICATIONS ARE GENERAL
IN NATURE AND APPLY ONLY WHERE APPLICABLE.
10) THESE DOCUMENTS ARE THE PROPERTY OF THE FLORIDA DEPARTMENT OF AGRICULTURE AND
CONSUMER SERVICES. USE OR COPY IS PERMITTED BY CONTRACT ONLY. ANY UNAUTHORIZED
USE OF, OR REVISIONS TO, REGARDLESS OF SCOPE, WITHOUT WRITTEN PERMISSION OF THE
DIVISION OF ADMINISTRATION, BUREAU OF GENERAL SERVICES, IS PROHIBITED.
11) THE CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND CONDITIONS. IF THE CONTRACTOR
IS UNABLE TO INTERPRET THE CONTRACT DOCUMENTS, HE IS RESPONSIBLE FOR REQUESTING
CLARIFICATION IN WRITING TO THE DEPARTMENT. IF THE CONTRACTOR PROCEEDS WITH ANY
WORK BEFORE OBTAINING CLARIFICATION, HE SHALL BE HELD RESPONSIBLE FOR ALL
ASSOCIATED DEFICIENCIES.
12) PRIOR TO COMMENCEMENT OF THE WORK, THE CONTRACTOR SHALL VISIT THE SITE TO EXAMINE
THE PREMISES AND BECOME FAMILIAR WITH EXISTING CONDITIONS UNDER WHICH HE WILL BE
OBLIGED TO OPERATE AND COMPLETE THE WORK UNDER THIS CONTRACT. NO ALLOWANCE WILL
BE MADE SUBSEQUENTLY IN THIS CONNECTION ON BEHALF OF THE CONTRACTOR FOR ANY
ERROR OR NEGLIGENCE ON HIS PART.
13) THE CONTRACTOR SHALL COORDINATE THE WORK WITH ALL SUBCONTRACTORS AND SEQUENCE
DEMOLITION AND CONSTRUCTION TO MINIMIZE INTERRUPTIONS TO THE NORMAL OPERATIONS
OF THE BUILDINGS AND SITE. THIS COORDINATION SHALL ALSO BE REVIEWED AND APPROVED BY
THE BUILDING FACILITY MANAGER AND THE OWNER'S USER REPRESENTATIVE.
14) THE CONTRACTOR SHALL MAINTAIN ALL EGRESS PATHS CLEAR. WHERE AN EGRESS PATH MUST
BE TEMPORARILY BLOCKED, THE CONTRACTOR SHALL PROVIDE BARRICADES AND DIRECTIONAL
SIGNS AS NEEDED TO MAINTAIN EXITING AND SAFETY.
15) THE CONTRACTOR SHALL ERECT AND MAINTAIN ALL REASONABLE SAFEGUARDS FOR SAFETY AND
HEALTH INCLUDING POSTING DANGER SIGNS, AND OTHER WARNING AGAINST HAZARDS, AS
WELL AS PROMULGATING SAFETY REGULATIONS.
16) THE CONTRACTOR SHALL BE RESTRICTED TO AREAS SPECIFIED BY OWNER FOR ON SITE STORAGE
OF CONSTRUCTION MATERIALS.
17) THE CONTRACTOR SHALL MAINTAIN A CLEAN WORK PREMISES AT ALL TIMES AND SHALL CLEAN
CONSTRUCTION SITE OF ALL DEBRIS DAILY. THE WORK PREMISES SHALL BE CLEAN AT
COMPLETION OF THE JOB AND BEFORE FINAL PAYMENT IS MADE.
18) ALL WORK SHALL COMPLY WITH APPLICABLE OSHA AND EPA REGULATIONS AND GUIDELINES.
19) CONTRACTOR SHALL PROVIDE ONE (1) YEAR MATERIAL AND LABOR WARRANTY.
20) ALL NEW WORK TO BE IN ACCORDANCE WITH THE BUILDING CODES LISTED BELOW, BEING THE
LATEST EDITION AS ADOPTED BY THE BUILDING AUTHORITIES HAVING JURISDICTION. WHERE
CONFLICTS OCCUR BETWEEN CODES AND BETWEEN CONSTRUCTION DOCUMENTS AND CODES,
THE MOST RESTRICTIVE REQUIREMENTS SHALL GOVERN.
FLORIDA BUILDING CODE, BUILDING 2023
FLORIDA BUILDING CODE, EXISTING BUILDING 2023
FLORIDA BUILDING CODE, MECHANICAL 2023
FLORIDA BUILDING CODE, ENERGY CONSERVATION 2023
FLORIDA BUILDING CODE, FUEL GAS 2023
FLORIDA BUILDING CODE, PLUMBING 2023
FLORIDA BUILDING CODE, ACCESSIBILITY 2023
FLORIDA FIRE PREVENTION CODE 2023, 8TH EDITION
NATIONAL ELECTRICAL CODE 2023 EDITION
BASE BID SCOPE OF WORK
NOTE: THE BASE BID WILL BE DIVIDED INTO SIX (6) PHASES
APPENDIX I
ADD ALTERNATE #1 SCOPE OF WORK
Extruded Concrete Curb Specification
1. Scope This section covers the materials, equipment, and procedures required to furnish and install extruded concrete curbing for roadway edges, parking lots, or landscaped areas.
2. Materials
Concrete Mix:
o Portland Cement: ASTM C150, Type I o Fine Aggregate: Clean, well-graded sand per ASTM C33 o Water: Potable, minimal content to achieve a 0–1" slump o Fiber Reinforcement: Optional, synthetic fibers (e.g., polypropylene) per ASTM C1116 for crack resistance o Air Entrainment: Not required unless specified by the local agency
Additives: No calcium chloride allowed
3. Mix Proportions
Water-cement ratio: ≤ 0.45 Compressive strength: Minimum 3,500 psi at 28 days Slump: 0–1 inch for optimal extrusion Consistency: Mix should form a firm ball when squeezed, leaving hands nearly dry
4. Equipment
Curb extruding machine with adjustable mold conforming to specified curb profiles Mortar mixer recommended for low-slump dry mix Finishing tools for shaping and smoothing
5. Installation
Site prep: Compact subgrade and remove debris Marking: Use chalk or paint lines for layout Extrusion: Machine-extruded curb placed continuously along marked path Joints:
o Expansion Joints: Install every 10–15 ft using preformed joint material o Control Joints: Sawcut to ⅓ depth within 24 hours of placement
Finishing: Shape and smooth immediately after extrusion Curing: Moist cure for minimum 3 days or apply curing compound per ASTM C309
6. Dimensions
Standard Profile: 6" wide base, 4" tall face (adjustable based on project) Radius Curbs: Minimum radius 3 ft unless otherwise specified Custom molds allowed with engineer approval
7. Quality Control
Field samples to be tested for strength Tolerance: ±¼" in dimensions Visual inspection: Free of cracks, scaling, or honeycombing
8. Compliance All work shall conform to applicable state DOT guidelines, including FDOT Index 300.
APPENDIX II
ADD ALTERNATE #2 SCOPE OF WORK
APPENDIX II
Traffic Seal Coating Specification
1. Scope This specification covers the materials, equipment, and procedures required for applying a seal coat to asphalt surfaces to enhance durability, restore appearance, and protect against environmental damage and wear.
2. Materials
Sealant Type: Bituminous or coal tar emulsion-based seal coat formulated for high-traffic applications.
Additives: Polymer modifiers for enhanced flexibility, sand for traction, and water as needed for dilution.
Approved Products: Must meet ASTM D490, D5727, or equivalent standards.
Storage & Handling: Maintain manufacturer-recommended temperatures. Prevent contamination from water or debris.
3. Surface Preparation
Cleaning: Remove dirt, oil, vegetation, and debris using blowers, brooms, and pressure washers.
Repairs: Potholes and surface cracks >¼ inch, and damaged areas must be patched or filled before seal coat application.
Dry Surface: Surface must be completely dry prior to sealing. No precipitation should be expected within 24 hours.
4. Application Methods
Equipment: Apply using spray rigs, squeegees, or mechanical distributors designed for uniform coverage.
Coverage Rate: Approx. 0.15–0.25 gallons/square yard (adjust based on pavement condition and product type).
Coats: Typically two coats; allow proper curing between layers.
5. Weather Conditions
Temperature: Ambient and surface temp must be ≥50°F and rising.
Humidity: Avoid application during high humidity or imminent rain.
Wind: Monitor to avoid overspray or uneven distribution.
6. Traffic Control
Barricades & Signage: Use cones, warning signs, and tape to prevent access until curing is complete.
Curing Time: Allow 24–48 hours for complete curing before reopening to traffic.
7. Quality Assurance
Visual Inspection: Ensure uniformity in color, texture, and coverage.
Material Certification: Provide documents verifying product compliance with specifications.
Test Areas: A sample application area may be required for approval before full deployment.
8. Cleanup
Post-Application: Remove equipment, excess materials, and debris from the site.
Environmental Care: Prevent runoff into drains or waterways.