EXHIBIT A - SITEWORK IMPROVEMENTS.pdf

PDF 3 MB Posted

Attached to
Suwannee State Farmers Market Site Asphalt Paving and Improvements - PROJECT NO. : 1151
Solicitation number
ITB-14002
Issued by
Sumter County, Florida

About this file

This document is an Exhibit A from the Florida Department of Agriculture and Consumer Services (FDACS), Division of Administration, Bureau of General Services, detailing sitework improvements for the Suwannee State Farmers Market located in White Springs, FL. The project involves parking lot repairs and paving improvements, with work divided into six phases and including a base bid for milling and removing existing pavement, installing new asphalt, re-striping parking spaces, and maintaining drainage. The project also includes two add alternates: one for extruded concrete curbing and another for seal coating, covering approximately 850,000 square feet of paving area. The work will be performed in accordance with Florida Department of Transportation (FDOT) specifications, with the contractor responsible for material procurement, product submittals, soil density testing, and maintaining facility operations during construction.

The project includes technical specifications covering material requirements, installation procedures, and quality control measures. The base bid and add alternates specify detailed requirements for concrete mix, asphalt composition, curb installation, and seal coating application. The contractor must use Type SP-12.5 PG-76-22 Traffic Level C asphalt with up to 20% Reclaimed Asphalt Pavement Material, install extruded concrete curbing with specific dimensional and strength requirements, and apply seal coating using bituminous or coal tar emulsion-based products. The project emphasizes compliance with FDOT standards, OSHA and EPA regulations, and requires a one-year material and labor warranty. The specifications provide comprehensive guidelines for surface preparation, application methods, weather conditions, traffic control, and environmental considerations.

View the file

Other files

File Type Posted
ITB FFS 25 26 39_Final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit A

Division of Administration

Bureau of General Services

Sitework Improvements

Date: August 8, 2025 Project: FDACS Project No.: 1151 Facility: Suwannee State Farmers Market Location: 2736 Co Rd 136, White Springs, FL 32096 Client Division: Division of Marketing and Development Commodity Codes: 30121600 Asphalt

72141103 Highway and road paving service 72141100 Infrastructure building, surfacing and paving services.

72152700 Concrete installation and repair services 72141127 Seal coating of roads, highways and parking lots

Purpose: Parking Lot Repairs and Paving Improvements

I. Base Bid

1. Furnish material and labor to mill and remove existing pavement layer in driveway and parking areas and haul debris off-site. Refer to attached exhibits for additional information.

2. Mill existing 1.5” asphalt and haul debris off of property. Install new 1.5” Type SP-12.5 PG-76-22

Traffic Level C with Reclaimed Asphalt Pavement Material (RAP) maximum of twenty percent (20%). Superpave Asphaltic Concrete (SP) shall meet Section 334, FDOT Standard Specifications.

Document, layout and re-stripe existing parking spaces in accordance with FDOT approved traffic paint (Lead-Free Thermoplastic Traffic Paint) and pavement marking standards per the recommendations of the Manual on Uniform Traffic Control Devices.

3. Spread material to uniform thickness specified and compact to appropriate density per FDOT requirements. Modify grade as necessary to maintain drainage direction and stormwater runoff of existing parking lot.

4. Existing pipe bollards shall remain, unless otherwise noted. All existing pipe bollards shall be painted, repaired and/or replaced if damaged.

5. Contractor is responsible for final grading and replacing sod in all disturbed areas of improvement.

Contractor shall water new sod until substantial completion date.

6. It shall be the contractor’s responsibility to furnish and install the material quantities necessary to complete the scope of work as illustrated on the attached exhibits.

7. All work shall be sequenced in accordance with Owner requirements to accommodate continuity of facility operations and parking. The work will commence in logical phases and may require limited weekend hours for areas of essential ingress/ egress.

8. All site improvements described herein shall be in accordance and compliance with current Florida Department of Transportation (FDOT) specifications.

9. Contractor shall provide product submittals and soil density test results for review and approval by the Owner prior to material procurement.

II. Add Alternates

Add Alternate #1: Extruded Concrete Curb Area Scope of Work and Specification

a. Reference Appendix I

Add Alternate #2: Seal Coating Area Scope of Work and Specification

b. Reference Appendix II

III. Technical Specifications

GENERAL REQUIREMENTS:

1) COMPLY WITH THE REQUIREMENTS OF THE "AGREEMENT BETWEEN OWNER AND CONTRACTOR"

IN EFFECT FOR CONSTRUCTION SERVICES FOR PROJECTS AT THE FLORIDA DEPARTMENT OF

AGRICULTURE AND CONSUMER SERVICES.

2) SUMMARY OF WORK: SEE SCOPE OF WORK AS DESCRIBED ABOVE.

3) COMPLY WITH REQUIREMENTS OF APPLICABLE PRODUCT OR TRADE STANDARDS, EXCEPT WHEN

MORE RIGID REQUIREMENTS ARE SPECIFIED OR ARE REQUIRED BY APPLICABLE CODES.

4) THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY PERMITS NEEDED FOR THE CONTRACTOR’S

OR SUBCONTRACTOR’S SCOPE OF WORK.

5) THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY SIGNED AND SEALED DRAWINGS NEEDED

TO OBTAIN IF PERMITS ARE REQUIRED.

6) SUBSTITUTIONS: ALL PRODUCTS SPECIFIED MAY BE SUBSTITUTED WITH AN APPROVED EQUAL

UNLESS SPECIFICALLY NOTED OTHERWISE. PROPOSED SUBSTITUTIONS MUST BE SUBMITTED IN

WRITING WITH SUFFICIENT SUPPORTING DOCUMENTATION FOR FURTHER EVALUATION.

OWNER CONSENT OF THE PRODUCT SUBSTITUTION MUST BE OBTAINED BY THE CONTRACTOR

PRIOR TO BID SUBMISSION.

7) COMPLY WITH THE REQUIREMENTS OF THE DEPARTMENT OF MANAGEMENT SERVICES DESIGN

& CONSTRUCTION GUIDELINES. REFER TO:

HTTPS://WWW.DMS.MYFLORIDA.COM/BUSINESS_OPERATIONS/REAL_ESTATE_DEVELOPMENT_

AND_MANAGEMENT/BUILDING_CONSTRUCTION/FORMS_AND_DOCUMENTS

8) THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CONDITIONS. IF CONFLICTS OR

DISCREPANCIES BETWEEN BUILDING SYSTEMS ARE OBSERVABLE, HE SHALL NOTIFY THE

DEPARTMENT’S PROJECT MANAGER IN WRITING FOR RESOLUTION PRIOR TO COMMENCING

CONSTRUCTION OR INSTALLATION.

9) THE CONTRACTOR SHALL LIMIT THE IMPACT OF HIS WORK ON ALL SYSTEMS, EQUIPMENT AND

SECURITY OF ALL AREAS WITHIN THE SCOPE OF THIS WORK. COORDINATE PROTECTION AND

SECURITY OF AREAS WITH THE DEPARTMENT. THE FOLLOWING SPECIFICATIONS ARE GENERAL

IN NATURE AND APPLY ONLY WHERE APPLICABLE.

10) THESE DOCUMENTS ARE THE PROPERTY OF THE FLORIDA DEPARTMENT OF AGRICULTURE AND

CONSUMER SERVICES. USE OR COPY IS PERMITTED BY CONTRACT ONLY. ANY UNAUTHORIZED

USE OF, OR REVISIONS TO, REGARDLESS OF SCOPE, WITHOUT WRITTEN PERMISSION OF THE

DIVISION OF ADMINISTRATION, BUREAU OF GENERAL SERVICES, IS PROHIBITED.

11) THE CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND CONDITIONS. IF THE CONTRACTOR

IS UNABLE TO INTERPRET THE CONTRACT DOCUMENTS, HE IS RESPONSIBLE FOR REQUESTING

CLARIFICATION IN WRITING TO THE DEPARTMENT. IF THE CONTRACTOR PROCEEDS WITH ANY

WORK BEFORE OBTAINING CLARIFICATION, HE SHALL BE HELD RESPONSIBLE FOR ALL

ASSOCIATED DEFICIENCIES.

12) PRIOR TO COMMENCEMENT OF THE WORK, THE CONTRACTOR SHALL VISIT THE SITE TO EXAMINE

THE PREMISES AND BECOME FAMILIAR WITH EXISTING CONDITIONS UNDER WHICH HE WILL BE

OBLIGED TO OPERATE AND COMPLETE THE WORK UNDER THIS CONTRACT. NO ALLOWANCE WILL

BE MADE SUBSEQUENTLY IN THIS CONNECTION ON BEHALF OF THE CONTRACTOR FOR ANY

ERROR OR NEGLIGENCE ON HIS PART.

13) THE CONTRACTOR SHALL COORDINATE THE WORK WITH ALL SUBCONTRACTORS AND SEQUENCE

DEMOLITION AND CONSTRUCTION TO MINIMIZE INTERRUPTIONS TO THE NORMAL OPERATIONS

OF THE BUILDINGS AND SITE. THIS COORDINATION SHALL ALSO BE REVIEWED AND APPROVED BY

THE BUILDING FACILITY MANAGER AND THE OWNER'S USER REPRESENTATIVE.

14) THE CONTRACTOR SHALL MAINTAIN ALL EGRESS PATHS CLEAR. WHERE AN EGRESS PATH MUST

BE TEMPORARILY BLOCKED, THE CONTRACTOR SHALL PROVIDE BARRICADES AND DIRECTIONAL

SIGNS AS NEEDED TO MAINTAIN EXITING AND SAFETY.

15) THE CONTRACTOR SHALL ERECT AND MAINTAIN ALL REASONABLE SAFEGUARDS FOR SAFETY AND

HEALTH INCLUDING POSTING DANGER SIGNS, AND OTHER WARNING AGAINST HAZARDS, AS

WELL AS PROMULGATING SAFETY REGULATIONS.

16) THE CONTRACTOR SHALL BE RESTRICTED TO AREAS SPECIFIED BY OWNER FOR ON SITE STORAGE

OF CONSTRUCTION MATERIALS.

17) THE CONTRACTOR SHALL MAINTAIN A CLEAN WORK PREMISES AT ALL TIMES AND SHALL CLEAN

CONSTRUCTION SITE OF ALL DEBRIS DAILY. THE WORK PREMISES SHALL BE CLEAN AT

COMPLETION OF THE JOB AND BEFORE FINAL PAYMENT IS MADE.

18) ALL WORK SHALL COMPLY WITH APPLICABLE OSHA AND EPA REGULATIONS AND GUIDELINES.

19) CONTRACTOR SHALL PROVIDE ONE (1) YEAR MATERIAL AND LABOR WARRANTY.

20) ALL NEW WORK TO BE IN ACCORDANCE WITH THE BUILDING CODES LISTED BELOW, BEING THE

LATEST EDITION AS ADOPTED BY THE BUILDING AUTHORITIES HAVING JURISDICTION. WHERE

CONFLICTS OCCUR BETWEEN CODES AND BETWEEN CONSTRUCTION DOCUMENTS AND CODES,

THE MOST RESTRICTIVE REQUIREMENTS SHALL GOVERN.

FLORIDA BUILDING CODE, BUILDING 2023

FLORIDA BUILDING CODE, EXISTING BUILDING 2023

FLORIDA BUILDING CODE, MECHANICAL 2023

FLORIDA BUILDING CODE, ENERGY CONSERVATION 2023

FLORIDA BUILDING CODE, FUEL GAS 2023

FLORIDA BUILDING CODE, PLUMBING 2023

FLORIDA BUILDING CODE, ACCESSIBILITY 2023

FLORIDA FIRE PREVENTION CODE 2023, 8TH EDITION

NATIONAL ELECTRICAL CODE 2023 EDITION

BASE BID SCOPE OF WORK

NOTE: THE BASE BID WILL BE DIVIDED INTO SIX (6) PHASES

APPENDIX I

ADD ALTERNATE #1 SCOPE OF WORK

Extruded Concrete Curb Specification

1. Scope This section covers the materials, equipment, and procedures required to furnish and install extruded concrete curbing for roadway edges, parking lots, or landscaped areas.

2. Materials

Concrete Mix:

o Portland Cement: ASTM C150, Type I o Fine Aggregate: Clean, well-graded sand per ASTM C33 o Water: Potable, minimal content to achieve a 0–1" slump o Fiber Reinforcement: Optional, synthetic fibers (e.g., polypropylene) per ASTM C1116 for crack resistance o Air Entrainment: Not required unless specified by the local agency

Additives: No calcium chloride allowed

3. Mix Proportions

Water-cement ratio: ≤ 0.45 Compressive strength: Minimum 3,500 psi at 28 days Slump: 0–1 inch for optimal extrusion Consistency: Mix should form a firm ball when squeezed, leaving hands nearly dry

4. Equipment

Curb extruding machine with adjustable mold conforming to specified curb profiles Mortar mixer recommended for low-slump dry mix Finishing tools for shaping and smoothing

5. Installation

Site prep: Compact subgrade and remove debris Marking: Use chalk or paint lines for layout Extrusion: Machine-extruded curb placed continuously along marked path Joints:

o Expansion Joints: Install every 10–15 ft using preformed joint material o Control Joints: Sawcut to ⅓ depth within 24 hours of placement

Finishing: Shape and smooth immediately after extrusion Curing: Moist cure for minimum 3 days or apply curing compound per ASTM C309

6. Dimensions

Standard Profile: 6" wide base, 4" tall face (adjustable based on project) Radius Curbs: Minimum radius 3 ft unless otherwise specified Custom molds allowed with engineer approval

7. Quality Control

Field samples to be tested for strength Tolerance: ±¼" in dimensions Visual inspection: Free of cracks, scaling, or honeycombing

8. Compliance All work shall conform to applicable state DOT guidelines, including FDOT Index 300.

APPENDIX II

ADD ALTERNATE #2 SCOPE OF WORK

APPENDIX II

Traffic Seal Coating Specification

1. Scope This specification covers the materials, equipment, and procedures required for applying a seal coat to asphalt surfaces to enhance durability, restore appearance, and protect against environmental damage and wear.

2. Materials

Sealant Type: Bituminous or coal tar emulsion-based seal coat formulated for high-traffic applications.

Additives: Polymer modifiers for enhanced flexibility, sand for traction, and water as needed for dilution.

Approved Products: Must meet ASTM D490, D5727, or equivalent standards.

Storage & Handling: Maintain manufacturer-recommended temperatures. Prevent contamination from water or debris.

3. Surface Preparation

Cleaning: Remove dirt, oil, vegetation, and debris using blowers, brooms, and pressure washers.

Repairs: Potholes and surface cracks >¼ inch, and damaged areas must be patched or filled before seal coat application.

Dry Surface: Surface must be completely dry prior to sealing. No precipitation should be expected within 24 hours.

4. Application Methods

Equipment: Apply using spray rigs, squeegees, or mechanical distributors designed for uniform coverage.

Coverage Rate: Approx. 0.15–0.25 gallons/square yard (adjust based on pavement condition and product type).

Coats: Typically two coats; allow proper curing between layers.

5. Weather Conditions

Temperature: Ambient and surface temp must be ≥50°F and rising.

Humidity: Avoid application during high humidity or imminent rain.

Wind: Monitor to avoid overspray or uneven distribution.

6. Traffic Control

Barricades & Signage: Use cones, warning signs, and tape to prevent access until curing is complete.

Curing Time: Allow 24–48 hours for complete curing before reopening to traffic.

7. Quality Assurance

Visual Inspection: Ensure uniformity in color, texture, and coverage.

Material Certification: Provide documents verifying product compliance with specifications.

Test Areas: A sample application area may be required for approval before full deployment.

8. Cleanup

Post-Application: Remove equipment, excess materials, and debris from the site.

Environmental Care: Prevent runoff into drains or waterways.