This Exhibit A Scope of Work document outlines earthquake and flood resilience assessment services for the Oregon Military Department and Department of Administrative Services (DAS) State Data Center (SDC) facility located at 530 Airport Road SE in Salem, Oregon. The project encompasses two primary assessment components: a preliminary earthquake resilience assessment utilizing ASCE 41-17 Seismic Evaluation and Retrofit of Existing Buildings Tier 1 procedures at BSE-1N and BSE-2N hazard levels, and a preliminary flood resilience assessment incorporating FEMA and local Salem flood mapping data for 100-year and 500-year flood zones. The scope of work includes site visits to assess current building conditions, identification of seismic and flood deficiencies, analysis of potential dependencies affecting functional recovery, and preparation of technical memoranda summarizing findings. Deliverables include written reports on building conditions, preliminary assessments, identified deficiencies, dependencies, and conference calls to present findings to DAS SDC personnel. The City of Salem Natural Hazards Mitigation Plan identified earthquake hazard as first in severity of impact and second in relative risk, while flood hazard was ranked second in severity of impact and first in relative risk to the facility.

The Scope of Work identifies specific deliverables for both the earthquake and flood resilience assessments but lists all due dates and payment amounts as "TBD" (to be determined), indicating these terms were not finalized in this document. Invoices are to be submitted to the Oregon State Data Center, Attention: David Jones, at 530 Airport Road SE, Salem, OR 97301, with required documentation including invoice date, deliverable(s) charged, assessor name(s), assessment performance date, and cumulative invoice totals. The document specifies invoice submission via email to SDC.ACCOUNTSPAYABLE@oregon.gov or by telephone at (503) 349-3083. No pricing structure, set-asides, incumbent information, or specific funding amounts are detailed in this Scope of Work document.

View the file

Other files

File Type Posted
ADDENDUM 1 Q and A Dairy Products ITB.docx DOCX document
ITB - RSD - Dairy 2022-2027 - Final.pdf PDF
Notice of Intent to Award - Dairy Products ITB.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Intermediate RFP #S-10700-00004052 Earthquake and Flood Resilience Assessment Services

EXHIBIT A

SCOPE/STATMENT OF WORK

Scope of Work for DCS Earthquake Flood Resilience Assessment.

Upon opening the co-location services building, the Oregon Military Department made an inquiry as to if an earthquake and flood assessment had ever been performed for the Data

Center building located at 530 Airport Road SE, in Salem Oregon.

DAS SDC reported back to the Military Department that an assessment has not been performed for the Data Center location. Data Center Director, James Foster asked for an earthquake and flood resilience assessment to be performed.

The City of Salem Natural Hazards Mitigation Plan identifies winter storms, windstorms, floods, and earthquakes as the leading hazards potentially impacting the City of Salem.

The winter storm and windstorm hazards are tied for highest total threat score but are not anticipated to significantly impede operation of the Data Center.

Earthquake hazard is ranked first in severity of impact and second in relative risk. Flood hazard is ranked second in severity of impact and first in relative risk.

The Scope/Statement of Work is as follows:

Preliminary Earthquake Resilience Assessment

1.1 Conduct a building site visit and survey to observe the current conditions and collect as-built information.

1.2 Perform a preliminary seismic assessment of the building, using the ASCE 41-17 Seismic Evaluation and Retrofit of Existing Buildings Tier 1 Procedure for Immediate Occupancy and Life Safety performance objectives at BSE-1N and BSE-2N hazard levels.

1.3 Identify buildings seismic deficiencies and anticipated performance during an earthquake.

1.4 Identify a list of potential dependencies that will impact the functional recovery of the Data Center.

1.5 Prepare a technical memorandum to summarize the findings and provide DAS SDC a written report of all findings.

1.6 Present assessment findings via conference call scheduled by DAS SDC.

Preliminary Flood Resilience Assessment

2.1 Conduct a building site visit to observe the building’s current conditions and collect as built information related to flood risk.

2.2 Review FEMA and Salem’s local flood maps to estimate the extent of one hundred (100) and five hundred (500) year flood zones and estimate flood inundation depths for one hundred (100) and five hundred (500) year floods.

2.3 Perform a preliminary flood impact assessment of the building.

2.4 Identify building deficiencies and anticipated performance during one hundred (100) and five hundred (500) year flood events.

2.5 Identify a list of potential dependencies that will impact functional recovery of the Data Center.

2.6 Prepare a technical memorandum to summarize our findings and provide DAS SDC a written report of all findings.

2.7 Present assessment findings via conference call scheduled by DAS SDC.

Deliverables and Payments **Note: Each written report may be consolidated into one final report for each assessment.

The reports are broken out below for Deliverable and Due Date purposes.

PRELIMINARY EARTHQUAKE RESILIANCE ASSESSMENT

Service Deliverable Due Date Payment

Amount

1.1 Proposer will conduct an onsite survey

to observe and record the buildings current conditions and collect as-built information as appropriate. Proposer will produce and deliver findings in a written report.

Written report of current building conditions.

TBD TBD

1.2 Proposer will perform a preliminary

seismic assessment of the building using the ASCE 41-17 Seismic Evaluation and Retrofit of Existing Buildings, Tier 1 procedure for Immediate Occupancy and Life Safety performance objectives at BSE-1N and BSE- 2N hazard levels.

preliminary seismic assessment.

TBD TBD

1.3 Proposer will identify and create a

written report regarding buildings seismic deficiencies and anticipated performance.

seismic deficiencies.

TBD TBD

1.4 Proposer will prepare a technical

memorandum to summarize the findings and provide a written copy of all findings to the appropriate data center personnel.

Written Report of findings for Preliminary Earthquake Resilience Assessment.

TBD TBD

1.5 Proposer will deliver findings via

conference call.

Conference call TBD TBD

PRELIMINARY FLOOD RESILIANCE ASSESSMENT

Service Deliverable Due Date Payment

Amount

2.1 Proposer will conduct an onsite survey

to observe and record the buildings current conditions and collect as-built information as appropriate. Proposer will produce and deliver findings in a written report.

buildings current condition.

TBD TBD

2.2 Proposer will review FEMA and Salem's

local flood maps to estimate the extent of one hundred (100) and five hundred (500) year flood zones.

Proposer will estimate and provide in a written report flood inundation depths for one hundred (100) and five hundred (500) year floods.

Proposer will perform a flood impact assessment of the building and provide a written report, of the building’s deficiencies and anticipated performance during one hundred (100) and five hundred (500) year flood events.

A combined written report regarding historical floods and building’s deficiencies.

TBD TBD

2.3 Proposer will identify in writing and

provide a report on potential dependencies that will impact functional recovery of the Data Center.

Written report on potential dependencies that will impact functional recovery of the Data Center

TBD TBD

2.4 Proposer will prepare a technical

memorandum to summarize the findings and provide a written copy of all findings to the appropriate data center personnel.

Written Report of findings for Preliminary Flood Resilience Assessment.

TBD TBD

2.5 Proposer will deliver findings via

conference call.

Conference call TBD TBD

INVOICES

All invoices shall be presented to the Agency with the following information:

• Invoice Date;

• Deliverable(s) being charged;

• Name of assessor(s);

• Date of assessment performance; and

• Total of all invoices to date

Invoices shall be sent to:

Oregon State Data Center

Attn: David Jones

Mailing Address: 530 Airport Rd, SE Salem, OR 97301