This document is an Exhibit A outlining the objectives and scope of services for West Virginia University's (WVU) comprehensive electrical infrastructure assessment project. The project encompasses a two-phase evaluation of the Morgantown campus electrical system, with Phase I consisting of a detailed survey and assessment that will define the scope for Phase II; pricing is requested for Phase I only, with Phase II to be negotiated upon completion. Phase I deliverables include an assessment of electrical supply capabilities across seven utility connection points, evaluation of the primary and secondary electrical distribution systems, condition assessment of major equipment, electrical demand analysis, operational and maintenance review, and development of an infrastructure improvement plan with prioritized recommendations and cost estimates. Additional deliverables include an equipment inventory, critical repair or replacement priorities, capital planning renewal strategy, updated one-line drawings, substation elevation diagrams, building-level component inventory, and optional Geographical Information Systems (GIS) modelling; the contractor will also provide an in-person presentation of findings to the University.

Qualified proposers must be licensed professional engineers or firms with a minimum of five years' experience in electrical infrastructure studies, demonstrated experience with utility coordination and medium-voltage infrastructure (4160V and 23kV systems), and preferably experience with higher education facilities or similar campus-style government environments. WVU will provide existing documentation including utility invoices, one-line diagrams, previous coordination studies and testing reports, and all available system equipment documentation to support the assessment. The contract does not establish any small business set-asides, and no specific pricing terms, funding sources, or contract term information is detailed in this scope of services document.

View the file

Other files

File Type Posted
Authorized Agent Form.pdf PDF
1475341-event.pdf PDF
Purchasing Affidavit Form.pdf PDF
RFP202790000751.pdf PDF
Exhibit B - Background and Summary of WVU Electrical Infrastructure.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit A - Objectives and Scope of Services

The purpose of this project is to perform a comprehensive assessment of the University’s campus electrical infrastructure regarding capacity, condition, resiliency, maintenance requirements, safety, and deferred maintenance needs. This study will evaluate current electrical supply, distribution, and capability for current use and future expansion. The study will be divided into two phases: Phase I will be a survey of the system that will provide the Scope of Phase II; which will include a deeper analysis of the system’s performance. For the purposes of this RFP, a fee will be requested for Phase I only and Phase II may be negotiated after Phase I is complete. The University does not guarantee Phase II will be conducted upon completion of Phase I.

The highlights of Phase I include, but are not limited to the following:

• Assess current supply capabilities of utility connections

• Evaluate existing electrical distribution infrastructure including code compliance, system redundancy, reliability, safety, and risks

• Analyze capacity and utilization of distribution systems

• Identify system deficiencies and opportunities for improvement

• Perform a condition assessment of the system including age, life expectancy and condition

• Develop recommendations for deferred maintenance, replacements, upgrades and expansion including cost estimates

• Review past load studies and perform new studies as needed (load verification, coordination, short circuit, protective device and arc flash)

• Assist with reviewing and development of design guidelines and standards for future improvements

Scope of Services

1. Electrical Supply Assessment

• Primary electrical service configuration and capacity of seven (7) utility connection points o Voltage levels and service characteristics o Rate structures and demand charges o Main campus service entrances o Primary protection at service connection o Utility metering systems and configurations o Interconnection with WVU system (description of transfer at demarcation point) o Power quality measurements and analysis (Phase II)

2. Electrical Distribution System Evaluation

• Primary distribution system o Substation switching and protection equipment o Substation transformers (capacity, characteristics, age) o Underground and overhead distribution networks o System redundancy and reliability o Branch capacity and utilization

• Secondary distribution analysis o Building-level primary service switchgear and protection o Building-level primary transformers and main breakers o Grounding and bonding systems (Phase II) o Emergency backup power systems (Phase II)

3. System Performance and Condition Assessment

• Equipment condition evaluation o Age and condition of all major electrical equipment such as transformers, switches, relays, cables, etc.

o Equipment replacement prioritization; identify critical replacement priorities o Identify any single points of failure o Safety and code compliance issues o Identify obsolete and antiquated equipment o Maintenance history and issues including historical outage data and causes o Critical facility backup power requirements (Phase II)

• Electrical Demand Analysis:

o Current electrical load assessment o Peak demand analysis by building and system (Phase II) o Load factor and diversity factor calculations (Phase II) o Seasonal demand variations (Phase II) o Power factor analysis (Phase II) o Energy consumption patterns (Phase II)

• Operation and Maintenance o Perform and update power studies as needed including coordination, short circuit, protective device and arc flash (Phase II) o Review existing arc flash notices and provide safety recommendations (Phase

II)

o Assess standard maintenance and testing guidelines and procedures for campus equipment (Phase II)

4. Future Planning and Recommendations

• Infrastructure improvement plan o Review existing coordination studies and recommend future improvements and/or replacements o Priority ranking of deferred maintenance recommendations, system upgrades and Capital Improvement Plan o Equipment replacement schedules per type o Additional metering recommendations o Cost estimates for deferred maintenance recommendations and improvements o Capacity expansion recommendations (Phase II) o Sustainability and efficiency initiatives (Phase II) o Technology upgrades and electrification trends (Phase II) o Electric vehicle charging infrastructure needs (Phase II) o Renewable energy integration considerations (Phase II)

5. Deliverables

• Reports and documentation in support of all items in the Scope of Services including but not limited to the specific items below.

o Infrastructure equipment inventory grouped by system detailing component characteristics, age, condition, remaining useful life, and failure risk o Critical repair or replacement priorities o Capital planning renewal strategy with budget cost estimates o Updated one-line drawings o Substation elevation diagrams o Secondary building-level component inventory detailing characteristics, age, condition, and failure risk o Geographical Information Systems (GIS) modelling. GIS models of the campus electrical system would be desirable as an optional service. WVU can provide background GIS information for GIS models.

o In person presentation of information to the University o Standard guidelines for periodic maintenance and testing of specific equipment

(Phase II)

6. WVU Provided Documentation

• WVU will provide any existing documentation (to the selected Proposer) related to the following o Utility invoices o One-line diagrams o Previous coordination studies o Previous testing reports o All available documentation regarding system equipment

7. Qualifications

• Licensed professional engineers or firms with a minimum of five (5) years’ experience in electrical infrastructure studies

• Experience with utility coordination

• Experience with higher education facilities or similar campus style/government environment

• Experience with medium-voltage infrastructure including 4160V and 23kV