Exhibit A ED0042030 PIP-II TTL Cryo Control Valves Specification.pdf

PDF 620 KB Posted

Attached to
Fermilab - Fabrication of Tunnel Transfer Line Control Valves
Solicitation number
368534-RK
Issued by

About this file

This document is a technical specification for cryogenic control valves for the Proton Improvement Plan II (PIP-II) Cryogenic Distribution System at Fermi National Accelerator Laboratory. The specification covers 46 control valves for the Tunnel Transfer Line (TTL), including 25 valves for Bayonet Cans and 6 valves for a Turnaround Can, to be used in helium service across various temperature ranges from 2K to 80K. Key technical requirements include top-load angle body valves with bellows spindle seals, pneumatic diaphragm actuators, specific heat leak and leak tightness performance standards, and compatibility with high radiation environments.

The procurement process requires vendors to submit detailed technical and business proposals by May 19, 2025, with evaluation criteria focusing on technical merit, quality assurance, delivery capabilities, management control, and past experience. The valves will be delivered in four lots within 40 weeks after purchase order, with specific requirements for manufacturing, testing, documentation, and quality control. Vendors must have at least 15 years of experience with 2K helium service valves and demonstrate successful delivery of similar valves for particle accelerator projects. The contract will be awarded on a best-value trade-off basis, with technical factors significantly more important than price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PIP-II Cryogenic Distribution System

ED0042030 – Tunnel Transfer Line Control Valves Specification

PIP-II Cryogenic Distribution System ED0042030 TTL Cryogenic Control Valves Specification

Fermi National Accelerator Laboratory 2

Document Approval

Revision History

Fermi National Accelerator Laboratory 3

1. Introduction and Scope 4

2. Scope 5

3. General technical requirements 6

4. Valve specific technical requirements 9

5. Manufacturing, testing, and miscellaneous requirements. 12

6. Transportation and handling 13

7. Document deliverables 14

8. References 16

Fermi National Accelerator Laboratory 4

1. Introduction and Scope

1.1. PIP II Cryogenic Distribution System (CDS)

1.1.1. Fermi National Accelerator Laboratory (FERMILAB) located in Batavia, IL is building a next generation proton accelerator called the Proton Improvement Plan II (PIP-II). The PIP-II accelerator (Linac) design is based on superconducting radio frequency (SRF) technology employed in twenty-three SRF cryomodules. The linac requires cryogenic helium for operation, which is provided by the Cryogenic Distribution System (CDS).

The CDS comprises the equipment needed to feed and return cryogenic helium from a cryogenic plant to the SRF cryomodules. The CDS includes Distribution Valve Box (DVB), Intermediate Transfer Line (ITL), and Tunnel Transfer Line (TTL). Figure 1.1 presents a schematic overview of the PIP-II CDS. The PIP-II CDS feeds individual cryomodules (CM) in the Linac string with the source of the proton beam emanating upstream.

Figure 1.1 Schematic of PIP-II Cryogenic Distribution System

1.2. Cryogenic control valves in the CDS

1.2.1. The following CDS components use cryogenic valves: The Distribution Valve Box (DVB) in the Cryoplant Building, each CDS Bayonet can, 25 total in the accelerator tunnel, and

1 Turn Around Can in the accelerator tunnel.

Fermi National Accelerator Laboratory 5

2. Scope

2.1.1. This specification is for cryogenic control valves on the Tunnel Transfer Line (TTL).

2.1.2. The control valves on the Distribution Valve Box (DVB) are not in the scope of this specification.

2.2. Acronyms

2.2.1. Technical acronyms

BC Bayonet Can CDS Cryogenic Distribution System CM Cryomodule (a proton beam accelerator cryogenic control valves) CPP Cryogenic Process Piping He Helium HTTS, LTTS High Temperature Thermal Shield, Low Temperature Thermal Shield MAWP Maximum Allowable Working Pressure OEM Original Equipment Manufacturer P&ID Piping and Instrumentation Diagram PQR Procedure Qualification Record TTL Tunnel Transfer Line

2.2.2. Organizational Acronyms

ANSI American National Standards Institute ASME American Society of Mechanical Engineering ASTM American Society for Testing and Materials ISO International Organization for Standardization PIP-II Proton Improvement Plan II NIST National Institute of Standards and Technology FERMILAB Fermi National Accelerator Laboratory

2.3. Definitions

AMBIENT a term used to define nominal environmental conditions, unless otherwise specified, of atmospheric pressure

CRYOGENIC

CONTROL VALVES

a term used to refer collectively to Cryogenic Control Valve assemblies to be procured for installation on the Tunnel Transfer Line

VENDOR a term used to refer to the designer, fabricator, and supplier of the CRYOGENIC

CONTROL VALVES

CODE a term used to refer collectively to the various pressure safety standards to which the CRYOGENIC CONTROL VALVES shall comply.

Fermi National Accelerator Laboratory 6

Linac a term that indicates a set of SRF cryomodules connected in series. In the LCLS-II project there are two Linacs, upstream (US) and downstream (DS), which together comprise the LCLS-II accelerator

May a term which indicates that a provision is neither required nor prohibited

Steady State the nominal operating mode in which the CRYOGENIC CONTROL VALVES operates at superfluid helium temperatures

Transient the mode in which the Linac is either cooling down or warming up and the CRYOGENIC CONTROL VALVES operates in a range between 2 K and 300 K

Shall a term which indicates that a provision is a requirement

Should a term which indicates that a provision is recommended as good practice but is not a requirement

Thermal Cycle a term that describes a temperature change experienced by a component equal to the difference between room temperature and the minimum design temperature of the component. It can apply to either the warming or cooling of a given component.

3. General technical requirements

3.1. The CRYOGENIC CONTROL VALVES shall

3.1.1. Be top load type.

3.1.2. Have angle body pattern.

3.1.3. Have bellows spindle seal with backup sealing.

3.1.4. Have cryogenic length of 34.5 inches (875 mm).

3.1.5. Have body integral weld-in flange for vacuum isolation.

3.1.6. Have Schedule 5S or Schedule 10S connections to process piping as specified in Table 4-1 and Table 4-2.

3.1.7. Be for helium service.

3.1.8. Have provisions for attaching thermal intercept as specified in Table 4-1 and Table 4-2.

The thermal intercept ring on the valve shall provide for TIG brazing to the intercept unless noted differently in Table 4-1 and Table 4-2.

3.1.9. Have pneumatic diaphragm actuators, set to “fail-close” in the case of loss of actuator air supply pressure.

3.1.10. Have 1:100 equal percentage plug profile.

Fermi National Accelerator Laboratory 7

3.2. Heat leak performance

3.2.1. The valve heat leaks should be less than or equal to than the values specified in Table 3-1.

Table 3-1 Total allowable heat loads to cryogenic valves Size Stem material Allowable heat load to 80 K Allowable heat load to 4.5 K

DN15

SS 0.8 W 0.33 W

G10 0.8 W 0.14 W

DN20 SS 0.9 W 0.5 W

DN25 SS 1.2 W 0.66 W

DN40 SS 4.2 W 1.5 W

DN65

SS 6.3 W 2.6 W

G10 6.3 W 0.8 W

3.3. Leak tightness

3.3.1. Maximum integral helium leak rates occurring during testing and operation of a cryogenic control valve shall not exceed the values presented in Table 3-2. Leak testing shall be performed at design pressure, room temperature, using helium gas as the fluid.

Table 3-2 Maximum acceptable leak rates at room temperature

Description Maximum Acceptable

Helium Rate

[Pa*m3/sec]

Welds, tube/pipe, forged material, bellows 1 x 10-9

O-ring seals 1 x 10-7

Seat tightness at maximum system pressure 1 x 10-5

Fermi National Accelerator Laboratory 8

3.4. Labelling

3.4.1. The valve body shall be etched to show serial number, size, class, body material, flow direction.

3.4.2. Valve serial number and tag/ID number shall be labeled on the valve bonnet and actuator. The tag/ID numbers will be provided by FERMILAB.

3.5. Operating environment and lifetime

3.5.1. The cryogenic valves shall operate in an indoor environment.

3.5.2. The cryogenic valve bellows shall be designed for 10,000 cycles full open to full closed at nominal pressure.

3.5.3. Pneumatic actuators shall be suitable for instrument air pressure range of 4.2 bar(g) ≤ P ≤ 6 bar(g)

3.5.4. The valves shall be constructed using materials that can withstand lifetime radiation dose of 1e5 Gy without degradation or valve performance deterioration.

3.6. Service experience requirements

3.6.1. VENDOR shall have previously provided valves suitable for 2 K helium service at sub-atmospheric pressures. VENDOR shall have at least 15 years of experience in providing such valves. (See “Vendor Technical Questionnaire” document for the response requirements for this clause.)

3.6.2. VENDOR shall have within the last 10 years successfully provided cryogenic control valves to at least two particle accelerator projects that resemble this proposal in scale, functionality, and technical requirements. (See “Vendor Technical Questionnaire” document for the response requirements for this clause.)

3.6.3. VENDOR shall have previously provided actuators using Siemens controls per section

4.6.3. (See “Vendor Technical Questionnaire” document for the response requirements for this clause.)

Fermi National Accelerator Laboratory 9

4. Valve specific technical requirements

4.1. Details of Control Valves on TTL Bayonet Cans (TTL-BC) are given in Table 4-1.

Table 4-1 Cryogenic Valves for TTL-BC (nn = 1-25 unless specified otherwise)

FERMILAB

Tag ID

PV-

nn10 PV-nn20 PV-nn30

(nn=01) PV-nn30

(nn=02-25) PV-nn40

PV-

nn50 (nn =

01-10)

PV-

nn50 (nn =

11-25)

PV-nn61 PV-nn62

PV-nn63 (nn = 01-10)

PV-nn63 (nn = 11-

25)

Process line

CM

4.5 K

Supply

CM 2 K

Return

CM LTTS

Return

CM LTTS

Return

CM HTTS

Supply

CM

HTTS

Return

CM

HTTS

Return

CM HTTS

Cooldown

CM

LTTS

Cooldo wn

CM cavity Cooldown

CM cavity Cooldown

Connecting pipe [inch] ½” 2-1/2” ½” ½” ¾” ¾” ¾” ¾” ¾” ¾” 1-1/2”

Connecting pipe schedule 10S 5S 10S 10S 10S 10S 10S 10S 10S 10S 10S

Pipe design pressure [bara]

20 4.1 20 20 24 24 24 24 20 4.1 4.1

MDMT 4 K 1.4 K 4 K 4 K 25 K 25 K 25 K 25 K 4 K 4 K 4 K

Base Temperature 4.5 K 2 K 9 K 9 K 40 K 80 K 80 K 80 K 4.5 K 2 K 2 K

Valve stem material G10 G10 SS SS SS SS SS SS SS SS SS

Requested Cv 6 114 3 1 6 3 2 2 6 12 52

Guard gas around stem

No Yes No No No No No No No Yes Yes

Thermal intercept at 80 K

Yes Yes Yes Yes No No No No Yes Yes Yes

Thermal intercept at 10 K

No

Yes (requires a bolt pattern)

No No No No No No No No No

4.2. Details of Control Valves on TTL Turnaround Can (TTL-TC) are given in Table 4-2.

Table 4-2 Cryogenic Valves for TTL-TC

Tag ID number PV-2710 PV-2720 PV-2730 PV-2750 PV-2760 PV-2761

Process line 4.5K supply 2K Return LTTS return HTTS return cooldown for HTTS Sup cooldown for 4.5K Sup

Connection Pipe [inch] 1/2" 1" 1/2" 1/2" 1/2" 1" Connecting Pipe Schedule 10S 10S 10S 10S 10S 10S Pipe design pressure 20 bara 4.1 bara 20 bara 24 bara 24 bara 20 bara

MDMT 4 K 1.4 K 4 K 25 K 25 K 4 K

Base Temperature 4.5 K 2 K 9 K 80 K 80 K 80 K Stem material SS SS SS SS SS SS Requested Cv* 3 17 1 6 0.5 17

Fermi National Accelerator Laboratory 10

Guard gas around stem Yes Yes No No No No Thermal intercept at 80 K Yes Yes Yes No No Yes

Thermal intercept at 10 K No Yes (requires a bolt pattern) No No No No

*Final values of Cv shall be specified at the Kick-Off Meeting. There shall be no changes to the valve size.

4.3. Lot wise delivery

4.3.1. The VENDOR shall deliver the Cryogenic Control Valves to FERMILAB in 4 lots according to the quantities and required delivery timeframes stated in Table 4-3 and Table 4-4.

Table 4-3 Lot-wise details and required delivery timeframe for TTL-BC.

FERMILA

B Tag ID

PV-

nn10

PV-

nn20

PV-

nn30 (nn = 01)

PV-

nn30

(nn=02- 25)

PV-

nn40

PV-

nn50 (nn =

01-10)

PV-

nn50 (n n = 11-

25)

PV-nn61 PV-nn62

PV-

nn63 (nn =

01-10)

PV-nn63 (nn = 11-25)

Required delivery

Process line

CM 4.5

K

Supply

CM 2 K

Return CM LTTS Return

CM

HTTS

Supply CM HTTS Return

CM HTTS

Cooldow n

CM LTTS

Cooldow n

CM

cavity

Cooldo wn

CM cavity Cooldown

QTY Lot 1 5 5 1 4 5 5 - 5 5 5 0 <= 18 weeks after PO

QTY Lot 2 7 7 - 7 7 5 2 7 7 5 2 <= 26 weeks after PO

QTY Lot 3 8 8 - 8 8 - 8 8 8 0 8 <= 33 weeks after PO

QTY Lot 4 5 5 - 5 5 - 5 5 5 0 5 <= 40 weeks after PO

QTY total 25 25 1 24 25 10 15 25 25 10 15

Table 4-4 Required delivery timeframe for TTL-TC.

FERMILAB

Tag ID PV-2710 PV-2720 PV-2730 PV-2750 PV-2760 PV-2761

Required delivery Process line

4.5K supply

2K Return

LTTS

return

HTTS

return cooldown for HTTS cooldown for 4.5K

QTY 1 1 1 1 1 1 <= 40 weeks after PO

Fermi National Accelerator Laboratory 11

4.4. Additional scope

4.4.1. Four stem assemblies made of SS, each for PV-nn10 and PV-nn20 valves. The stem assemblies shall be supplied in separate packaging.

4.4.2. Tooling required to remove bullet and valve seat (if applicable) for each valve size.

4.4.3. The additional scope defined in 4.4.1 and 4.4.2 shall be delivered in Lot 1 as defined in Table 4-3.

4.5. Optional scope

4.5.1. As option for purchase by FERMILAB, the VENDOR shall include their shipping costs for delivery of the Lots 1-4 to Fermilab. (See “Vendor Form for Pricing- Shipments” document to provide response with proposal.)

4.5.2. As an option for purchase by FERMILAB, the VENDOR shall include cost and delivery times for spare bullets and seals for each valve size. (See “Vendor Form for Pricing- Spare Parts Options” document to provide response with proposal.)

4.6. Other technical requirements

4.6.1. Pneumatic diaphragm actuators on the valves shall be suitable for installation test pressure per ASME for the pressure ranges indicated in Table 4-1 and Table 4-2.

4.6.2. The cryogenic valve seals, actuator, and positioner shall be suitable for use in a high radiation environment.

4.6.2.1. The valve Static seal material should be EPDM and seat seal material should be PEEK. Alternatives may be proposed, their use is subject to FERMILAB written approval.

4.6.2.2. Actuator air thread sealing should use Loctite 580 for thread sealing. Alternatives may be proposed, their use is subject to FERMILAB written approval. Teflon PTFE or other materials not suitable in radiation environment shall not be used.

4.6.2.3. The VENDOR shall identify any plastic or polymer-based components and any low thermal conductivity materials used on the tunnel cryogenic valves and they shall be suitable for service in radiation environment.

Fermi National Accelerator Laboratory 12

4.6.3. The cryogenic control valve actuators shall use an i-p positioner with external analog electronics mounted remotely outside via SIPART PS2 19” drawer with PROFIBUS-PA communication. The control valves shall use the following positioner:

4.6.3.1. Siemens SIPART PS2 6DR5910 with external analog electronics in rack. This component shall be provided by the VENDOR integrated with the CONTROL VALVE assembly. The component shall have readback provision that shows current position of the valve.

4.6.3.2. The external 19” rack for positioner electronics (A5E00250503) will be procured by FERMILAB separately and is not in the scope of this procurement.

4.6.4. Certain tunnel valves will operate in process lines with sub-atmospheric service as noted in Table 4-1 and Table 4-2. The stem side of the valve shall have a helium guard gas connection.

5. Manufacturing, testing, and miscellaneous requirements.

5.1. CODE requirements

5.1.1. All CRYOGENIC CONTROL VALVES shall be built and tested in full compliance with

ASME B31.3.

5.2. Quality Assurance

5.2.1. The VENDOR shall have a current certification to ISO 9001 requirements.

5.2.2. The CRYOGENIC CONTROL VALVES shall be designed and manufactured in accordance with the VENDOR’s Quality Assurance Plan (QAP).

5.2.3. The QAP shall comprise training and qualification records of personnel and/or procedures for the performance of certain special processes. These include, but are not limited to welding, heat treatment, non-destructive examination, helium mass spectrometer leak check, and others as may be required by this specification or by the nature of the process or product.

Fermi National Accelerator Laboratory 13

5.3. Leak tightness testing

5.3.1. Leak testing shall be done in accordance with the following standards as applicable

5.3.1.1. ASTM E493 Testing for Leaks Using the Mass Spectrometer Leak Detector in the Inside-Out Testing

Mode

5.3.1.2. ASTM E498 Testing for Leaks Using the Mass Spectrometer Leak Detector in the Tracer Probe Mode

5.3.1.3. ASTM E499 Testing for Leaks Using the Mass Spectrometer Leak Detector Probe Mode

5.4. Cleanliness

5.4.1. The cryogenic valves shall be thoroughly cleaned of all foreign substances including, but not limited to, scale, spatter, flux, oil, grease, and dust.

5.5. Testing and inspection

5.5.1. All inspections, examinations, and tests shall be documented in a Manufacturing Inspection Plan (MIP). If VENDOR is not familiar with a MIP, FERMILAB can provide guidance, examples, and/or template.

5.5.2. The VENDOR shall pressure test all CRYOGENIC CONTROL VALVES in accordance with ASME B31.3.

5.5.3. Control valve function shall be checked for stroke movement, actuator, and positioner indication.

5.5.4. All inspection, examination, and test reports shall be fully documented and provided to

FERMILAB.

6. Transportation and handling

6.1.1. The CRYOGENIC CONTROL VALVES shall be packed adequately for shipment to prevent any damage during transit to the Fermilab site in Batavia, Illinois, USA.

6.1.2. The CRYOGENIC CONTROL VALVES shall be crated to be readily handled with a forklift truck and shall have suitable lifting attachments for use with an overhead crane.

Fermi National Accelerator Laboratory 14

7. Document deliverables

7.1. The following items shall be submitted in English with the proposal. Information considered proprietary should be identified as such.

7.1.1. Total cost to fabricate, test, and pack for shipment to Fermilab site fully functional Cryogenic Controls valves ready for installation.

7.1.2. Pricing for shipments of lots to deliver to FERMILAB. (See “Vendor Form for Pricing- Shipments”) shall be provided in two options.

7.1.2.1. Option 1: Incoterms 2020 DDP

7.1.2.2. Option 2: Incoterms 2020 EXW

7.1.3. As option, pricing for spare parts option if offered. (See “Vendor Form for Pricing- Spare Part Options”.)

7.1.4. Delivery schedule listing main activities of this project.

7.1.5. Lists of exceptions to this specification and reasoning for exceptions.

7.1.6. Technical details of the offered CRYOGENIC CONTROL VALVES covering:

7.1.6.1. ASME B31.3 compliance strategy

7.1.6.2. Drawings and step files of the following:

• Vacuum connection interface

• Thermal intercept connection interface

• Process piping connection interface

7.1.6.3. Projected heat leak for each valve at the process temperature and at the thermal intercept temperature if appliable

7.1.6.4. Details of materials to be used for constructing the CRYOGENIC CONTROL VALVES

7.1.6.5. All other requirements stated in Section 3 and Section 4 of this specification.

7.1.1. A copy of QAP that demonstrates VENDOR’S capability to satisfy requirements of paragraph 5.2.

Fermi National Accelerator Laboratory 15

7.1.2. Sample welding plan, WPS, examination, and acceptance testing procedures.

7.1.3. Sample packaging and shipping plan. The sample shall serve as illustration of the packing and shipping solutions to be used for this proposal.

7.1.4. VENDOR profile highlighting the key technical personal, staffing level, and workshop facilities.

7.1.5. Description of VENDOR experience of at least 15 years with providing valves suitable for 2 K helium service at sub-atmospheric pressures. (See “Vendor Technical Questionnaire” document.)

7.1.6. VENDOR examples within the last 10 years of providing cryogenic valves for at least two particle accelerator projects that resemble this proposal in scale, functionality, and technical requirements. (See “Vendor Technical Questionnaire” document.)

7.1.7. VENDOR completed “Technical Questionnaire”, “Vendor Form for Pricing- Shipments”, “Vendor Form for Pricing- Spare Part Options”, and other documents provided by FERMILAB with this Technical Specification.

7.2. The following items shall be submitted to FERMILAB in English at the time of manufacturing start

7.2.1. Mill certification reports for all raw materials used in the construction of CRYOGENIC CONTROL VALVES. Reports shall be clearly identified with the CRYOGENIC CONTROL VALVES part number(s) for which the material was used and show cast or heat numbers, chemical analysis, and mechanical properties.

7.2.2. Certificates of compliance (in lieu of mill certification reports) for commercial items such as weld rods, electrodes, and fasteners.

7.2.3. Copies of the WPQ, WPS, and PQR for each welder and welding procedure utilized in welding operations.

7.2.4. Qualification documents of all technical personnel performing the required examinations and inspections of materials, in-process fabrications, non-destructive tests, and acceptance tests.

7.2.5. Final version of Manufacturing Inspection Plan (MIP) including work instruction for meeting the requirements of Section 5.4.

Fermi National Accelerator Laboratory 16

7.2.6. Final drawings and step files of items given in paragraph 7.1.6.2 if modifications were made.

7.2.7. Final transportation and handling plan.

7.3. The following items shall be submitted in English at the time of delivery to FERMILAB

7.3.1. Final quality control reports including, but not limited to, leak check and pressure test reports with name and qualification of the person(s) performing tests.

7.3.2. Completed MIP.

7.3.3. Nonconformances & their resolution.

7.3.4. Instructions for initial uncrating/unpacking and handling upon delivery to FERMILAB.

7.3.5. Certificate of Compliance for the CRYOGENIC CONTROL VALVES stating compliance with ASME B31.3.

8. References

There are no sources in the current document.

1. Introduction and Scope
1.1. PIP II Cryogenic Distribution System (CDS)
1.1.1. Fermi National Accelerator Laboratory (FERMILAB) located in Batavia, IL is building a next generation proton accelerator called the Proton Improvement Plan II (PIP-II). The PIP-II accelerator (Linac) design is based on superconducting radio fre...
1.2. Cryogenic control valves in the CDS
1.2.1. The following CDS components use cryogenic valves: The Distribution Valve Box (DVB) in the Cryoplant Building, each CDS Bayonet can, 25 total in the accelerator tunnel, and 1 Turn Around Can in the accelerator tunnel.
2. Scope
2.1.1. This specification is for cryogenic control valves on the Tunnel Transfer Line (TTL).
2.1.2. The control valves on the Distribution Valve Box (DVB) are not in the scope of this specification.
2.2. Acronyms
2.2.1. Technical acronyms
2.2.2. Organizational Acronyms

2.3. Definitions

3. General technical requirements
3.1. The CRYOGENIC CONTROL VALVES shall
3.1.1. Be top load type.
3.1.2. Have angle body pattern.
3.1.3. Have bellows spindle seal with backup sealing.
3.1.4. Have cryogenic length of 34.5 inches (875 mm).
3.1.5. Have body integral weld-in flange for vacuum isolation.
3.1.6. Have Schedule 5S or Schedule 10S connections to process piping as specified in Table 4-1 and Table 4-2.
3.1.7. Be for helium service.
3.1.8. Have provisions for attaching thermal intercept as specified in Table 4-1 and Table 4-2. The thermal intercept ring on the valve shall provide for TIG brazing to the intercept unless noted differently in Table 4-1 and Table 4-2.
3.1.9. Have pneumatic diaphragm actuators, set to “fail-close” in the case of loss of actuator air supply pressure.
3.1.10. Have 1:100 equal percentage plug profile.
3.2. Heat leak performance
3.2.1. The valve heat leaks should be less than or equal to than the values specified in Table 3-1.
3.3. Leak tightness
3.3.1. Maximum integral helium leak rates occurring during testing and operation of a cryogenic control valve shall not exceed the values presented in Table 3-2. Leak testing shall be performed at design pressure, room temperature, using helium gas as...
3.4. Labelling
3.4.1. The valve body shall be etched to show serial number, size, class, body material, flow direction.
3.4.2. Valve serial number and tag/ID number shall be labeled on the valve bonnet and actuator. The tag/ID numbers will be provided by FERMILAB.
3.5. Operating environment and lifetime
3.5.1. The cryogenic valves shall operate in an indoor environment.
3.5.2. The cryogenic valve bellows shall be designed for 10,000 cycles full open to full closed at nominal pressure.
3.5.3. Pneumatic actuators shall be suitable for instrument air pressure range of 4.2 bar(g) ≤ P ≤ 6 bar(g)
3.5.4. The valves shall be constructed using materials that can withstand lifetime radiation dose of 1e5 Gy without degradation or valve performance deterioration.
3.6. Service experience requirements
3.6.1. VENDOR shall have previously provided valves suitable for 2 K helium service at sub-atmospheric pressures. VENDOR shall have at least 15 years of experience in providing such valves. (See “Vendor Technical Questionnaire” document for the respon...
3.6.2. VENDOR shall have within the last 10 years successfully provided cryogenic control valves to at least two particle accelerator projects that resemble this proposal in scale, functionality, and technical requirements. (See “Vendor Technical Ques...
3.6.3. VENDOR shall have previously provided actuators using Siemens controls per section 4.6.3. (See “Vendor Technical Questionnaire” document for the response requirements for this clause.)
4. Valve specific technical requirements
4.1. Details of Control Valves on TTL Bayonet Cans (TTL-BC) are given in Table 4-1.
4.2. Details of Control Valves on TTL Turnaround Can (TTL-TC) are given in Table 4-2.
4.3. Lot wise delivery
4.3.1. The VENDOR shall deliver the Cryogenic Control Valves to FERMILAB in 4 lots according to the quantities and required delivery timeframes stated in Table 4-3 and Table 4-4.
4.4. Additional scope
4.4.1. Four stem assemblies made of SS, each for PV-nn10 and PV-nn20 valves. The stem assemblies shall be supplied in separate packaging.
4.4.2. Tooling required to remove bullet and valve seat (if applicable) for each valve size.
4.4.3. The additional scope defined in 4.4.1 and 4.4.2 shall be delivered in Lot 1 as defined in Table 4-3.
4.5. Optional scope
4.5.1. As option for purchase by FERMILAB, the VENDOR shall include their shipping costs for delivery of the Lots 1-4 to Fermilab. (See “Vendor Form for Pricing- Shipments” document to provide response with proposal.)
4.5.2. As an option for purchase by FERMILAB, the VENDOR shall include cost and delivery times for spare bullets and seals for each valve size. (See “Vendor Form for Pricing- Spare Parts Options” document to provide response with proposal.)
4.6. Other technical requirements
4.6.1. Pneumatic diaphragm actuators on the valves shall be suitable for installation test pressure per ASME for the pressure ranges indicated in Table 4-1 and Table 4-2.
4.6.2. The cryogenic valve seals, actuator, and positioner shall be suitable for use in a high radiation environment.
4.6.2.1. The valve Static seal material should be EPDM and seat seal material should be PEEK. Alternatives may be proposed, their use is subject to FERMILAB written approval.
4.6.2.2. Actuator air thread sealing should use Loctite 580 for thread sealing. Alternatives may be proposed, their use is subject to FERMILAB written approval. Teflon PTFE or other materials not suitable in radiation environment shall not be used.
4.6.2.3. The VENDOR shall identify any plastic or polymer-based components and any low thermal conductivity materials used on the tunnel cryogenic valves and they shall be suitable for service in radiation environment.
4.6.3. The cryogenic control valve actuators shall use an i-p positioner with external analog electronics mounted remotely outside via SIPART PS2 19” drawer with PROFIBUS-PA communication. The control valves shall use the following positioner:
4.6.3.1. Siemens SIPART PS2 6DR5910 with external analog electronics in rack. This component shall be provided by the VENDOR integrated with the CONTROL VALVE assembly. The component shall have readback provision that shows current position of the val...
4.6.3.2. The external 19” rack for positioner electronics (A5E00250503) will be procured by FERMILAB separately and is not in the scope of this procurement.

4.6.4. Certain tunnel valves will operate in process lines with sub-atmospheric service as noted in Table 4-1 and Table 4-2. The stem side of the valve shall have a helium guard gas connection.

5. Manufacturing, testing, and miscellaneous requirements.
5.1. CODE requirements
5.1.1. All CRYOGENIC CONTROL VALVES shall be built and tested in full compliance with ASME B31.3.
5.2. Quality Assurance
5.2.1. The VENDOR shall have a current certification to ISO 9001 requirements.
5.2.2. The CRYOGENIC CONTROL VALVES shall be designed and manufactured in accordance with the VENDOR’s Quality Assurance Plan (QAP).
5.2.3. The QAP shall comprise training and qualification records of personnel and/or procedures for the performance of certain special processes. These include, but are not limited to welding, heat treatment, non-destructive examination, helium mass s...
5.3. Leak tightness testing
5.3.1. Leak testing shall be done in accordance with the following standards as applicable
5.3.1.1. ASTM E493 Testing for Leaks Using the Mass Spectrometer Leak Detector in the Inside-Out Testing Mode
5.3.1.2. ASTM E498 Testing for Leaks Using the Mass Spectrometer Leak Detector in the Tracer Probe Mode
5.3.1.3. ASTM E499 Testing for Leaks Using the Mass Spectrometer Leak Detector Probe Mode
5.4. Cleanliness
5.4.1. The cryogenic valves shall be thoroughly cleaned of all foreign substances including, but not limited to, scale, spatter, flux, oil, grease, and dust.
5.5. Testing and inspection
5.5.1. All inspections, examinations, and tests shall be documented in a Manufacturing Inspection Plan (MIP). If VENDOR is not familiar with a MIP, FERMILAB can provide guidance, examples, and/or template.
5.5.2. The VENDOR shall pressure test all CRYOGENIC CONTROL VALVES in accordance with ASME B31.3.
5.5.3. Control valve function shall be checked for stroke movement, actuator, and positioner indication.
5.5.4. All inspection, examination, and test reports shall be fully documented and provided to FERMILAB.
6. Transportation and handling
6.1.1. The CRYOGENIC CONTROL VALVES shall be packed adequately for shipment to prevent any damage during transit to the Fermilab site in Batavia, Illinois, USA.
6.1.2. The CRYOGENIC CONTROL VALVES shall be crated to be readily handled with a forklift truck and shall have suitable lifting attachments for use with an overhead crane.
7. Document deliverables
7.1. The following items shall be submitted in English with the proposal. Information considered proprietary should be identified as such.
7.1.1. Total cost to fabricate, test, and pack for shipment to Fermilab site fully functional Cryogenic Controls valves ready for installation.
7.1.2. Pricing for shipments of lots to deliver to FERMILAB. (See “Vendor Form for Pricing- Shipments”) shall be provided in two options.
7.1.2.1. Option 1: Incoterms 2020 DDP
7.1.2.2. Option 2: Incoterms 2020 EXW
7.1.3. As option, pricing for spare parts option if offered. (See “Vendor Form for Pricing- Spare Part Options”.)
7.1.4. Delivery schedule listing main activities of this project.
7.1.5. Lists of exceptions to this specification and reasoning for exceptions.
7.1.6. Technical details of the offered CRYOGENIC CONTROL VALVES covering:
7.1.6.1. ASME B31.3 compliance strategy
7.1.6.2. Drawings and step files of the following:
Vacuum connection interface
Thermal intercept connection interface
Process piping connection interface
7.1.6.3. Projected heat leak for each valve at the process temperature and at the thermal intercept temperature if appliable
7.1.6.4. Details of materials to be used for constructing the CRYOGENIC CONTROL VALVES
7.1.6.5. All other requirements stated in Section 3 and Section 4 of this specification.
7.1.1. A copy of QAP that demonstrates VENDOR’S capability to satisfy requirements of paragraph 5.2.
7.1.2. Sample welding plan, WPS, examination, and acceptance testing procedures.
7.1.3. Sample packaging and shipping plan. The sample shall serve as illustration of the packing and shipping solutions to be used for this proposal.
7.1.4. VENDOR profile highlighting the key technical personal, staffing level, and workshop facilities.
7.1.5. Description of VENDOR experience of at least 15 years with providing valves suitable for 2 K helium service at sub-atmospheric pressures. (See “Vendor Technical Questionnaire” document.)
7.1.6. VENDOR examples within the last 10 years of providing cryogenic valves for at least two particle accelerator projects that resemble this proposal in scale, functionality, and technical requirements. (See “Vendor Technical Questionnaire” document.)
7.1.7. VENDOR completed “Technical Questionnaire”, “Vendor Form for Pricing- Shipments”, “Vendor Form for Pricing- Spare Part Options”, and other documents provided by FERMILAB with this Technical Specification.
7.2. The following items shall be submitted to FERMILAB in English at the time of manufacturing start
7.2.1. Mill certification reports for all raw materials used in the construction of CRYOGENIC CONTROL VALVES. Reports shall be clearly identified with the CRYOGENIC CONTROL VALVES part number(s) for which the material was used and show cast or heat nu...
7.2.2. Certificates of compliance (in lieu of mill certification reports) for commercial items such as weld rods, electrodes, and fasteners.
7.2.3. Copies of the WPQ, WPS, and PQR for each welder and welding procedure utilized in welding operations.
7.2.4. Qualification documents of all technical personnel performing the required examinations and inspections of materials, in-process fabrications, non-destructive tests, and acceptance tests.
7.2.5. Final version of Manufacturing Inspection Plan (MIP) including work instruction for meeting the requirements of Section 5.4.
7.2.6. Final drawings and step files of items given in paragraph 7.1.6.2 if modifications were made.
7.2.7. Final transportation and handling plan.
7.3. The following items shall be submitted in English at the time of delivery to FERMILAB
7.3.1. Final quality control reports including, but not limited to, leak check and pressure test reports with name and qualification of the person(s) performing tests.
7.3.2. Completed MIP.
7.3.3. Nonconformances & their resolution.
7.3.4. Instructions for initial uncrating/unpacking and handling upon delivery to FERMILAB.
7.3.5. Certificate of Compliance for the CRYOGENIC CONTROL VALVES stating compliance with ASME B31.3.

8. References