This Scope of Services document is from the Seminole County Leisure Services Department, Greenways and Natural Lands Division, detailing improvements for the Spring Hammock Preserve located at 2985 Osprey Trail. The project encompasses multiple infrastructure enhancements, including paving Osprey Trail, installing ADA parking stalls, constructing a new pavilion, replacing footbridges at multiple locations, and building a new elevated boardwalk terminating at Lake Jesup's edge. The county is seeking a contractor to provide labor, materials, and equipment to complete these improvements, with a specific request for an alternate bid using Fiber Reinforced Polymer (FRP) for boardwalks and footbridges, specifically from Wagners Composite Fiber Technologies or an approved equal. The project has a 240-day completion timeline from the notice to proceed, which includes permitting time, with SJRWMD and Army Corps permits already issued.
The project requires the contractor to maintain public access throughout construction, provide proper safety signage and barriers, comply with Florida Building Codes and national construction standards, and restore all affected areas to preconstruction conditions. The estimated project cost is $1,949,041.29, with bid documents available on the Seminole County website. The solicitation (CC-5767-24/HSM) encourages M/WBE participation, and prospective bidders are instructed to obtain documents through the county's procurement portal. Additional specifications include using FDOT-approved materials, installing turbidity barriers before construction, and coordinating pavilion color selection with the county's project manager.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Spring Hammock Preserve
Scope of Services
Description Seminole County Leisure Services Department is seeking a contractor to provide labor, materials and equipment necessary to complete improvements needed for the Spring Hammock Preserve located at 2985 Osprey Trail. The project shall include, but is not limited to paving Osprey Trail, installing ADA parking stalls, a new pavilion, replacing footbridges at multiple locations and construction of a new elevated boardwalk that terminates at the edge of Lake Jesup.
Note: Leisure Services is requesting an alternate bid for the boardwalk and foot bridges to be constructed with a Fiber Reinforced Polymer (FRP) product. The product manufacturer shall be Wagners Composite Fiber Technologies or an approved equal. The manufactures product must be FDOT approved. Separate specifications attached.
Requirements
1. This project shall be completed within 240 days from notice to proceed, this includes time for permitting. SJRWMD and Army Corps permits have already been issued. It shall be the contractor’s responsibility to obtain all other permitting required to complete this project.
2. It shall be the contractor’s responsibility to provide and maintain all the bonds, insurances and licenses required to complete this project.
3. The property will remain open to the public through the duration of the project. It shall be the contractor’s responsibility to provide proper signage and construction barriers to ensure public safety.
4. All materials, equipment and methods of installation shall comply with National Design Specifications for Wood Construction and Supplement 1986 Edition, National Forest Products Association codes and standards.
5. Any turbidity barriers required shall be installed before commencing any construction such as brush/tree removal, grubbing, digging, dredging, jetting, etc.
6. Contractor shall comply with all Florida Building Codes (latest Edition) and plan specification/notes provided by engineer.
7. All areas affected by work performed shall be returned to preconstruction conditions.
This includes but is not limited to asphalt, concrete, curbing, grading, sod, etc.
8. Colors for pavilion will be selected by the County’s project manager closer to construction.