EXHIBIT_A.DOCX_-_CDHSCP_Solicitation_Request_Documents_-_11-13-2026_-_71795587_-__-_150000.00.docx

DOCX document 18 KB Posted

Attached to
Sanitary Sewer Muffin Monster Replacement
Solicitation number
DQ1 IHHA 2027000189 1
Issued by
El Paso County, Colorado Springs City, Colorado

About this file

This is a Scope of Work exhibit for a State of Colorado solicitation involving the removal of existing wastewater treatment equipment and installation of a new Heavy-Duty Muffin Monster industrial sewage wastewater grinder. The project requires installation of one new 30004T-2410-DI Muffin Monster Upgrade unit equipped with an 11-tooth cam cutter, hardened alloy steel stack, and standard seals with Buna elastomers, along with a new 5 HP TEXP electric motor (460V), 29:1 NEMA reducer, PC2200 motor controller, and 10-inch pipe diameter unibody housing. All work must comply with OSHA and current life safety regulations, be performed during regular business hours (Monday through Friday, 7:00 AM to 5:00 PM), and include confined-space entry coordination, equipment removal and disposal, installation, alignment, mechanical operation verification, startup and operational testing, and staff training. The contract term includes a 12-month warranty on labor, and no change orders will be accepted for night work or utility shutdowns, though utility tie-ins may occur during off-hours at the contractor's cost.

The solicitation requires an all-encompassing bid with no product substitutions permitted, including all necessary labor, materials, electrical work, plumbing, piping, structural modifications, grounding, conduit, terminations, and power provision for 460V/3-phase/60Hz service and 120VAC control power. The contractor must be licensed and insured with experience in similar installations and must acknowledge only State of Colorado's terms and conditions. Invoicing will be accepted monthly in 30-day intervals, with equipment and materials invoiceable only upon receipt at the site. No specific contract award date, bid due date, or funding amount is stated in this scope document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT A

SCOPE OF WORK

Removal of all existing equipment and Installation of a new Heavy- Duty Muffin Monster industrial sewage wastewater grinder. The new unit will be installed in existing wastewater grinder pit. All work will need to be performed according to all OSHA and current life safety rules and regulations. Project should be bid to include all necessary labor and materials needed to complete. This will be considered an all-encompassing bid. No substitution or similar product will be considered.

Equipment and Installation:

- One (1) new 30004T-2410-DI Muffin Monster Upgrade (11T cam cutters, 1:1 stack hardened alloy STL, standard seals with Buna elastomers, cork and rubber gaskets)

- New 5 HP TEXP electric motor (460V) and new 29:1 NEMA reducer (184TC, 1.15 SF)

- New spool

- New 10" pipe diameter unibody housing

- One (1) new PC2200 motor controller for 460V service in a NEMA 4X fiberglass enclosure

- 460V/3PH/60HZ input power; designed for use with the 5 HP motor

- Includes IEC starter with over-current protection, jam-sensing current transformer, one set of spare fuses, Siemens S7-1200 PLC, and utilizes 120VAC control voltage

- All and any electrical connection and requirements needed to install equipment to manufacture recommendation.

- All removal and disposal of any obstructions will be included in bid.

All misc., plumbing and piping needed to successfully install equipment to manufacture recommendations.

Installation:

Coordinate confined-space entry into the pit, remove remaining necessary components, and install the new Muffin Monster assembly, motor, reducer, spool, unibody housing, gaskets, and seals. Equipment will be aligned, secured, and checked for proper mechanical operation.

Execute startup and operational testing once installation is complete.

Training and instructions to be included in bid.

- Electrical Work to be included: All electrical installation, connections, wiring, conduit, terminations, grounding, and power provision (460V/3PH/60HZ power and 120VAC control power) are to be included in bid along with any control tie ins.

Any Structural modifications should be included in bid.

Installation items shall comply with all current codes.

- Schedule: Work to be performed during regular business hours (M–F, 7:00 AM – 5:00 PM). All utility tie-ins could possibly need to take place off hours. This should be included in bid. No change order will be accepted for night work and utility shutdowns.

Invoicing will be accepted every 30 days. Equipment and materials cannot be invoiced until received on site.

A 12-month warranty on labor should be included.

The Contractor should be a licensed and insured.

The Contractor should have experience with similar installations.

Only the State of Colorado’s terms and conditions will be acknowledged. Contractor terms and conditions will not be considered.

File details come from the government source that posted it. Updated .