Exhibit 6_Specifications.docx
DOCX document 24 KB Posted
- Attached to
- Santiam Junction Maintenance Station Mobile Home
- Solicitation number
- S-73000-00018456
- Issued by
- Lake County, Oregon
About this file
This is a Specifications exhibit document that outlines technical and operational requirements for a state and local contract opportunity. The document establishes detailed specifications for products or services to be procured, including performance standards, quality requirements, and compliance criteria that potential bidders must meet to qualify for consideration. The specifications define the minimum acceptable standards and functional requirements that govern how the contracted work must be performed or how delivered products must operate, ensuring consistency and measurable outcomes across all submissions received.
The specifications document serves as a binding technical reference that contractors must adhere to throughout contract performance. All bidders are required to demonstrate their ability to meet or exceed these stated requirements in their proposals, with non-compliance potentially resulting in bid rejection. The document may include detailed performance metrics, material standards, testing protocols, and operational procedures that will be used to evaluate bid responses and monitor ongoing contract compliance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00018456_Sample_Contract.docx | DOCX document | |
| Exhibit 5_Scope of Work.doc | DOC document | |
| 00018456_RFCQ.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit 6 - Specifications Santiam Junction Maintenance Station Mobile Home
1. Section- Home
1.0 Home Size and Layout
The manufactured home must meet all of the following dimensional and layout requirements:
· Style- Single wide
· Exterior walls 2x6 framing 16” on center.
· Wall insulation minimum R21, roof insulation minimum R40, and floor insulation minimum R33.
· Total floor area: 700–800 sq ft
· Bedrooms: Two bedrooms, each at least 50 sq ft
· Bathroom: One full bathroom
· Living area: Minimum 150 sq ft
· Home classification: home built on a permanent chassis
· Maximum width with overhangs is 14’
· Maximum overall height: No more than 11 feet, measured from the top of finished floor to the highest point of the roof
· Height limit applies as delivered from the factory, prior to installation on piers, skirting, or other site‑built supports.
The Contractor must provide manufacturer documentation verifying factory‑built height.
1.1 Structural and Construction Standards
· Home must comply with Oregon Manufactured Dwelling Installation Specialty Code and Safety Standards (24 CFR Part 3280).
· Roof load, wind load, and thermal zone ratings must meet Oregon requirements.
· Factory‑built height must not exceed 11 feet. No post‑delivery modifications may increase the height.
· All rooftop equipment (vents, caps, exhausts, etc.) must be included within the 11‑foot maximum height.
1.2 Transportation and Delivery Requirements
· Contractor is responsible for transporting the home to the project site in Santiam Junction, Oregon.
· Transported unit must comply with Oregon oversize‑load regulations, including height limits.
· The home must arrive at or below 11 feet in total height, eliminating the need for oversize‑height permits.
· Contractor must confirm transport route feasibility based on verified factory height.
2. Section- Installation
2.0 Installation Requirements
· The Contractor must provide complete installation of the manufactured home unit, including all labor, equipment, stairs, and materials necessary to place the home in its final, code‑compliant position on the project site. Requirements include:
· Installation of the home on the approved foundation, piers, and perimeter wall panels support systems in accordance with Oregon Manufactured Dwelling Installation Specialty Code standards and Oregon state requirements.
· Alignment, leveling, and securing of the home to meet manufacturer specifications.
· Connection of all required structural components, including mating walls, roof joints, and mechanical chases (if applicable).
· Installation of all factory‑provided or required tie‑downs, anchors, and stabilizing systems.
· Completion of all utility connections by the appropriate trades.
· Installation work must not increase the overall height of the home beyond the 11‑foot maximum specified in Section 1.0.
3. Section- Precast Wall panels
3.0 Precast Wall Panel Foundation System
· Provide precast concrete perimeter wall panel system as the primary foundation enclosure.
· Panels shall be factory‑produced reinforced concrete meeting structural requirements.
· Panels should include crawl space venting per code requirements.
· Include all connectors, bearing pads, leveling shims, and anchorage hardware.
· Install per manufacturer instructions and engineered details.
· Any deviation from standard installation requires engineer certification.
4. Section- Submittals and Documentation
4.0 Submittals and Documentation
The Contractor must provide the following with the bid package:
· Manufacturer’s certified drawings showing overall dimensions, including height and width.
· A height‑verification document confirming the unit is 11 feet or less as constructed.
· A width‑verification document confirming the unit is 14 feet or less as constructed.
· Confirmation that no add‑ons, rooftop accessories, or installation components will exceed the height limit.
File details come from the government source that posted it. Updated .