Scope of Work Summary
This Exhibit 5 Scope of Work document pertains to the Oregon Department of Transportation's (ODOT) Santiam Junction Maintenance Station Mobile Home Project. The project consists of procuring and installing one new 2-bedroom, 1-bath mobile home (700-800 square feet) at the remote Santiam Junction Maintenance Station to replace an older unit beyond repair. The scope includes delivery, complete installation in compliance with Oregon Manufactured Dwelling Installation Specialty Code standards, stairs, structural skirting, factory-provided tiedowns and anchors, a precast concrete perimeter wall panel foundation system, and all utility connections. The contractor must examine existing site conditions prior to bidding and request any clarifications in writing. Substantial completion is required no later than January 15, 2027, with final completion by January 22, 2027. Work shall be performed on weekdays between 7:00 a.m. and 5:00 p.m., excluding weekends and state holidays. The contractor must contact the ODOT Project Manager (Austin VanNette, 503-507-1394) at least ten business days before commencing work to schedule the project.
The contractor is responsible for all permits, transportation, material storage, site cleanup, and compliance with Oregon OSHA regulations and BOLI prevailing wage requirements, including submission of weekly certified payroll reports. The contractor must provide pre-bid and pre-construction submittals for approval, maintain as-built drawings with marked utility locations, provide operations and maintenance documentation, deliver equipment information and warranty details, instruct ODOT personnel on equipment operation, and furnish a one-year installation warranty on all workmanship plus applicable equipment warranties. Prior to final completion, the contractor must certify that all subcontractors and suppliers have been or will be paid in full and that all project obligations have been satisfied. ODOT will not provide disposal facilities, dumpsters, or material security, and the contractor is liable for damage caused during construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00018456_Sample_Contract.docx | DOCX document | |
| Exhibit 6_Specifications.docx | DOCX document | |
| 00018456_RFCQ.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT 5
SCOPE OF WORK
PROJECT OVERVIEW:
November 2026 Oregon Department of Transportation
Santiam Junction Maintenance Station Mobile Home Project Location:
Santiam Junction Maintenance Station Santiam Junction
Coordinates: 44.435763551694286, -121.94287084726652
ODOT Contact:
The ODOT Project Manager for this project is Austin VanNette.
· E-mail: Austin.van_nette@odot.oregon.gov
· Cell: 503-507-1394
· Address: 885 Airport Rd Se BLDG X Salem,OR 97301 The ODOT Project Manager may designate an additional ODOT contact person or engineer to support with inspections or questions in the field.
Project Background:
This is a remote maintenance station that requires staff to stay on site. ODOT is purchasing a mobile home to replace an older mobile home that was beyond repair to provide this housing.
Project Description:
This project consists of providing a new mobile home and the delivery and complete installation of that mobile home, including stairs and skirt panels as indicated in the specifications into the furthest eastern end of the building circled in the location map.
Detailed Project Specifications:
See attached specifications for details.
· One 2-bedroom 1-bath mobile home with a total floor area: 700–800 sq ft
· Stairs and structural skirting
· Outline of work:
· Provide mobile home.
· Install the home in accordance with Oregon Manufactured Dwelling Installation Specialty Code standards and Oregon state requirements.
· Install all factory‑provided or required tie‑downs, anchors, and stabilizing systems.
· Provide precast concrete perimeter wall panel system as the primary foundation enclosure.
· Transport the home to the project site in Santiam Junction, Oregon.
· Complete all utility connections.
General Construction Notes:
· The Contractor shall make a site visit and examine existing conditions prior to providing a bid. Any discrepancies shall be brought to the attention of ODOT through a request for clarification as set forth in the bid documents.
· Clarifications shall be requested in writing prior to any installation. Incorrect installations shall be corrected at no additional cost to ODOT.
· All work shown is to be by the Contractor unless specifically noted as being by ODOT or by others. All materials shown are to be provided by the Contractor unless specifically noted as existing or provided by ODOT.
· Drawings are schematic in nature, major components and equipment are shown on the drawings. The Contractor shall supply and install all minor components and materials necessary to provide a complete and functional project whether or not all such components are noted in the drawings and specifications.
· Plans and specifications may call out specific makes and models of equipment in some locations. Substitution requests shall be made during the bid process. ODOT shall at its sole discretion determine the acceptability of substitutions. No substitutions shall be installed without prior written approval from the ODOT Construction Project Manager.
· All equipment and materials shall be installed in accordance with the manufacturer’s published installation instructions and recommendations.
· Clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.
Submittals:
The Contractor shall provide pre-bid submittals as indicated in the specifications and pre-construction submittals to the ODOT Project Manager. Submittals shall be approved by the ODOT Project Manager prior to the start of on-site construction.
Scheduling of Contract:
· Substantial completion of the Work shall be no later than 1/15/27. Final completion shall be no later than 1/22/27.
· After award of contract, the Contractor shall contact the ODOT Project Manager to schedule the Work at least ten (10) business days prior to the start of any work/demolition.
· The Work shall be accomplished on weekdays between the hours of 7 a.m. and 5 p.m. Work hours shall exclude weekends and State holidays, unless specifically requested by the Contractor and approved by the ODOT Project Manager.
· Any permits required for the Work are the responsibility of the Contractor. The Contractor shall provide copies of permits to the ODOT Project Manager prior to the start of work. The Contractor shall be responsible for posting all permits on site in accordance with local jurisdiction requirements.
· The Contractor shall submit to the ODOT Project Manager a list of the contact information for the Contractor’s project manager and site superintendent, as well as a list of all Subcontractors and their key representatives.
Clean-Up/Conditions of Site:
· The Contractor shall be responsible for keeping the ODOT Project Manager informed of all activity throughout the Work.
· The Contractor shall clean up all worksite debris resulting from construction and remove all excess construction materials and scraps from the premises. The Contractor shall broom-clean their work area at the end of each workday and neatly stack materials and debris in an approved location. The Contractor shall clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.
· The Contractor shall protect materials subject to damage by temperature or other weather conditions.
· The location for storage of materials, debris, or dumpster on the premises shall be approved in advance by the ODOT Project Manager. Disposal facilities, bins, or dumpsters will not be provided by ODOT.
· The Contractor shall notify the ODOT Project Manager at least two (2) days in advance of any major deliveries.
· The Contractor shall immediately notify the ODOT Project Manager of any damage done by the Contractor to the premises, grounds, or adjacent State properties. Damage done by the Contractor to the premises or surrounding area shall be repaired by Contractor to existing conditions as found prior to the commencement of the Work.
· ODOT will not be responsible for the security of the Contractor’s materials, tools, personal belongings, or equipment on the premises.
· It is the responsibility of the Contractor to ensure the Work is performed in accordance with Oregon OSHA rules and regulations.
· The Contractor shall immediately bring to the attention of the ODOT Project Manager any conflicts or issues between existing utilities and the Work.
BOLI:
· BOLI Prevailing Wage Rates apply to this project. Provide weekly Certified Payroll Reports for Contractor and all subcontractors as a prerequisite for progress payment approval.
Close Out:
· All special inspections must be complete prior to Substantial Completion.
· Inspection of the work by the ODOT Project Manager for establishment of Substantial Completion will be made within five (5) business days after receipt of the Contractor’s email request. At this time, the ODOT Project Manager and the Contractor shall develop a punch list document of any incomplete or deficient work.
· Prior to Final Completion, the Contractor shall complete all items on the punch list.
· The Contractor shall provide final inspection reports for all permits applicable to this Contract signed by authorities having jurisdiction
· The Contractor shall maintain one set of the approved drawings for recording as-built conditions with the actual location of all underground utilities and any changes marked in red. At the time of Final Completion, the Contractor shall turn over the one marked-up set of record drawings to the ODOT Project Manager.
· Prior to Final Completion, the Contractor shall provide one (1) digital copy via email of all operations, maintenance, and warranty information to the ODOT Project Manager.
· Prior to Final Completion, the Contractor shall provide ODOT Project Manager with information for all equipment provided by the project, including but not limited to: manufacturer, model, serial number, consumables, installation date, purchase date.
· Prior to Final Completion, and as prerequisite for final payment, the Contractor shall provide ODOT Project Manager with signed certification that all subcontractors and suppliers have been paid in full or will be paid in full of the final payment and in compliance with all prompt payment requirements, all disputes with property owners have been resolved, all obligations on the project have been satisfied, all monetary claims and indebtedness have been paid and, to the best of the Contractor's knowledge, there are no claims of any kind outstanding against the project.
· Prior to Final Completion, the Contractor shall fully instruct ODOT’s operating and maintenance personnel in the operation, adjustment, and maintenance of products, equipment, and systems.
· Inspection of the work by the ODOT Project Manager for establishment of Final Completion will be made within five (5) business days after receipt of the Contractor’s email request.
Warranty:
· The Contractor shall provide a 1 year Installation warranty on all workmanship.
· The Contractor shall provide all warranties for equipment applicable to this Contract.
Revision: 5/7/24