Exhibit 6 Price and Services Schedule (P1).docx

DOCX document 23 KB Posted

Attached to
Edith Green Wendell Wyatt (EGWW) Federal Building - Aquatherm Domestic Hot Water Service (DHWS) Pipe Replacement (Project 1)
Solicitation number
EQ10PCPA2-20-0026
Issued by

About this file

This document contains a price and services schedule for a federal solicitation seeking replacement of domestic hot water system piping at the Edith Green-Wendell Wyatt Federal Building in Portland, Oregon. The schedule outlines pricing and period of performance for design, construction, bonds and insurance, and security clearances. It requests fixed pricing for design services from September 2020 through August 2021, construction services over the same period, bonds and insurance, and a not-to-exceed amount for security adjudications. Accompanying details in the federal contract opportunity description specify that the scope of work includes removing polypropylene piping and replacing domestic hot water and zone piping with copper, along with associated mechanical, plumbing, architectural, and commissioning services. The solicitation number is EQ10PCPA2-20-0026 and was issued on July 23, 2020 by the General Services Administration for the Edith Green-Wendell Wyatt Federal Building.

View the file

Other files

File Type Posted
EGWW Aquatherm DHWS Replacement (Project 1) - Solicitation 8.26.20 (Amd 02).docx DOCX document
EGWW Aquatherm DHWS Replacement (Project 1) - Agreement 8.26.20 (Amd 02).docx DOCX document
Exhibit 7 Wage Determination Gen Decision OR20200029 Mod 8 08.21.2020 (Amd 02).pdf PDF
Exhibit 11 - EGWW Aquatherm Pre-Proposal RFI Log 8.26.20 (Amd 02).docx DOCX document
Amd 02 SF30.pdf PDF
Exhibit 7 Wage Determination Gen Decision OR20200029 Mod 7 08.14.2020.pdf PDF
EGWW Aquatherm DHWS Replacement (Project 1) - Agreement 8.18.20 (Amd 01).docx DOCX document
Amd 01 SF30.pdf PDF
Exhibit 11 - EGWW Aquatherm Pre-Proposal RFI Log 8.18.20.docx DOCX document
EGWW Aquatherm DHWS Replacement (Project 1) - Solicitation 8.18.20 (Amd 01).docx DOCX document
EGWW Aquatherm DHWS Replacement (Project 1) - Solicitation 7.23.20.docx DOCX document
Exhibit 00 Pre-Proposal Conference Job Walk.docx DOCX document
EGWW Aquatherm DHWS Replacement (Project 1) - Agreement 7.23.20.docx DOCX document
Exhibit 10 Project Experience.docx DOCX document
Exhibit 9 Key Personnel Resume Format.docx DOCX document
Exhibit 2 SF1442 (P1).pdf PDF
Exhibit 5 GACA - GSA Affiliated Customer Accounts May 2014.docx DOCX document
Exhibit 7 Wage Determination Gen Decision OR20200029 Mod 6 07.17.2020.pdf PDF
Exhibit 3 EGWW DHWS Design Build SOW (P1).docx DOCX document
Exhibit 8 GC Reps and Certs May 2020 508 (P1).docx DOCX document
Exhibit 0 SBU Document.docx DOCX document
Exhibit 4 Performance Evaluation Survey - Commercial Client.docx DOCX document
EGWW Aquatherm DHWS Replacement (Project 1) - Solicitation 7.23.20.docx DOCX document
Exhibit 1 Schedule (P1).pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SERVICES AND PRICE SCHEDULE

ITEM NO

SUPPLIES/SERVICES

PRICE

EGWW Aquatherm DHWS Replacement (Project 1) - DESIGN STAGE

Period of Performance: 9/7/2020 – 8/6/2021 (240 Calendar Days)

The Contractor shall provide all labor, equipment, materials, services and incidentals necessary and perform all work required to provide services throughout performance of all DESIGN STAGE phases of the contract.

This CLIN shall include all costs necessary for performance of DESIGN (Concept, DD and CD) PHASES as identified in the Statement of Work. It shall also include all costs for those tasks and services under PROJECT MANAGEMENT, as identified in the Statement of Work, associated with design aspects prior to commencement of the CONSTRUCTION PHASE.

Work shall be performed IAW this Statement of Work and the Contractor’s resulting contract.

EGWW Aquatherm DHWS Replacement (Project 1) - CONSTRUCTION STAGE

Period of Performance: 9/7/2020 – 8/6/2021 (240 Calendar Days)

The Contractor shall provide all labor, equipment, materials, services and incidentals necessary and perform all work required to provide services throughout performance of all CONSTRUCTION STAGE phases of the contract.

This CLIN shall include all costs necessary for performance of the PROJECT MANAGEMENT, CONSTRUCTION and CLOSEOUT PHASES as identified in the Statement of Work. Costs included under this CLIN for PROJECT MANAGEMENT as identified in the Statement of Work, shall cover those tasks and services associated with those PHASES during the CONSTRUCTION and CLOSEOUT PHASES of the project.

Work shall be performed IAW the Statement of Work and the Contractor’s resulting contract.

BONDS / INSURANCE

Cost for providing payment and performance bond premiums and insurance coverage as required under FAR 52.228-5, Insurance - Work on a Government Installation, also shown in Section III.F. Insurance Requirements within The Agreement.

HSPD-12 ADJUDICATIONS ALLOWANCE

This CLIN is established as a Not to Exceed (NTE) Allowance line item to reimburse cost(s) incurred in order for their personnel to comply with GSA’s Office of Mission Assurance (OMA) security related clearance and adjudication functions in support of this project.

Work shall be performed IAW the Statement of Work and the Contractor’s BPA Contract.

Note: Allowance CLINs will not count in the overall price evaluation as they are not designed as firm fixed price amounts. They are designed as an allowance (or contingency) for allocable costs that are not easily predicted at the time of award. All actual costs must be validated by the GSA project team prior to being allowed.

NTE

TOTAL PROPOSED PRICE: $_____________________

Period of Performance offered: _______________Days

Future Modification Mark-up Rate offered: _______________%

Government Caused Delay Rate offered: $______________/Day

Solicitation No. EQ10PCPA2-20-0026, 7.23.20 Page 1

File details come from the government source that posted it. Updated .