Exhibit 5 Specifications 2026 South Douglas D7 MIM Paving.pdf
PDF 597 KB Posted
- Solicitation number
- S-73000-00016803
- Issued by
- Douglas County, Oregon
About this file
This document is a Specifications exhibit for the Oregon Department of Transportation (ODOT) District 7 addressing the 2026 South Douglas Milling, Inlay, Mill (MIM) Paving Project. The project involves cold plane pavement removal and placement of emulsified asphalt tack coat and Level 4 dense asphalt concrete pavement along Interstate 5 between mile points 94.3 and 92.35 in Douglas County, Oregon. The work is located on the southbound B-Lane over a 6,800-foot length and 13-foot width with a 4-inch depth. The specifications are based on the 2024 Oregon Standard Specifications for Construction with modifications specific to this project. Blake Howren, ODOT District Operations Coordinator, serves as the primary contact for general project information. Traffic lane closures are permitted only during nightly hours from 6:00 p.m. to 7:00 a.m., Sunday through Friday, with work zones not exceeding one mile in length. The contractor must schedule and coordinate work zone traffic control with the ODOT Project Manager a minimum of 28 days prior to beginning work, while ODOT will provide and maintain work zone traffic control as needed throughout the project duration.
The specifications require the use of PG 70-22 ER grade asphalt cement and mandate that paved surfaces be constructed full width and length through the wearing course during the same shift before opening to traffic. Longitudinal joints must be constructed six inches from permanent lane markings or as directed. Asphalt concrete pavement quantities will be measured on a weight basis with no separate measurement or payment for asphalt cement, additives, or treatments used in the mixture. No separate or additional payment will be made for emulsified asphalt tack coat, temporary flexible pavement markers, or work related to maintaining temporary pavement markings until permanent markings can be restored by ODOT forces. The specifications explicitly state that contractor obligations not separately identified in the bid schedule are to be performed as incidental work with no separate measurement or payment required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00016803 Invitation to Bid.docx | DOCX document | |
| Exhibit 6 Standard Drawing 610.pdf | ||
| 00016803 Bid Pricing Form.xlsx | XLSX spreadsheet | |
| 00016803 Bid Results.xlsx | XLSX spreadsheet | |
| 00016803 ATT B Sample Contract.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT 5
SPECIAL PROVISONS & SPECIFICATIONS FOR
2026 SOUTH DOUGLAS (DISTRICT 7 ) MIM PAVING
SCOPE
The work to be completed under this Contract consists of the following work located along Interstate 5, between mile points 94.3 and 92.35, in Douglas County, OR:
Complete Cold Plane Pavement Removal of asphalt concrete surface, furnish and place Emulsified Asphalt Tack Coat, and furnish and place Level 4, ½” Dense Asphalt Concrete Pavement at the following locations and as directed:
Location Length Width Depth
SB: MP 94.3 - 92.35 B-Lane ** 6,800’ 13’ 4”
** SB: MP 94.3 – MP 93.8 and MP 93.1 – MP 92.35. The limits of the work areas will be marked on site. See RD610 for additional information.
Perform additional and incidental work as detailed in the Contract plans and specifications or as directed.
PROJECT INFORMATION
General information pertaining to this project may be obtained from the following:
Blake Howren, District Operations Coordinator Oregon Department of Transportation Email: Blake.W.Howren@ODOT.Oregon.gov
APPLICABLE STANDARD SPECIFICATIONS AND SPECIAL PROVISIONS
2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (Standard Specifications) include detailed technical specifications in Parts 00200 through 03000 inclusive (Technical Specifications) that apply to this ITB and the resulting Contract.
Some sections of the Technical Specifications are identified and modified herein, Specifications. Sections of the Technical Specifications not modified remain applicable to the Contract according to their original terms. Unless they are identified herein, Specifications, sections of the Standard Specifications in Part 00100 (General Conditions) are not applicable to this Contract. Bidders can also access this information at the following Internet address:
2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION
Silence of Specifications: The apparent silence of the specifications as to any detail, or the apparent omission of a detailed description concerning any point, shall be regarded as meaning that the highest value commercial practices are to prevail and that only materials and workmanship of first quality are to be used.
2026 SOUTH DOUGLAS (DISTRICT 7) MIM PAVING
Where neither the Special Provisions nor the bid schedule indicate separate payment for the work to be completed under this Contract, perform the work as incidental for which no separate measurement or payment will be made.
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the Standard Specifications modified as follows:
Construction
00210.40 Mobilization – delete the last bullet of the bullet list. Obtaining and maintaining access to Doc Express® and using Doc Express® to submit documents will not be required on this project.
Payment
00210.90 Payment – delete the last sentence in this subsection.
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
One or more Traffic Lanes may be closed on the Pacific Highway (I-5) when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):
Nightly, Sunday night through Friday morning, between 6:00 p.m. and 7:00 a.m.
Length of workzone shall not exceed 1 mile.
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
Comply with Section 00221 of the Standard Specifications modified as follows:
Description
00221.00 Scope - Replace this subsection, except for the subsection number and title, with the following:
Work zone traffic control will be installed and maintained by State forces as needed for the duration of the project. The Contractor shall schedule and coordinate work zone traffic control with the ODOT Project Manager or designated representative, a minimum of 28 days prior to beginning work.
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
Comply with Section 00222 of the Standard Specifications.
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
Comply with Section 00223 of the Standard Specifications.
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
Comply with Section 00224 of the Standard Specifications.
SECTION 00225 – TEMPORARY PAVEMENT MARKING
Comply with Section 00225 of the Standard Specifications modified as follows:
00225.90 Payment –
Delete the following Pay Item from the Pay Item list:
(b) Temporary Flexible Pavement Markers................................................ Each
No separate or additional payment will be made for Temporary Flexible Pavement Markers as they are considered incidental to the asphalt concrete paving work required under Section 00745.
The Contractor shall install and maintain temporary flexible pavement markings at no additional cost to the Agency until ODOT forces can restore any permanent pavement markings removed during paving operations.
SECTION 00620 - COLD PLANE PAVEMENT REMOVAL
Comply with Section 00620 of the Standard Specifications modified as follows:
00620.43 Maintenance Under Traffic - Replace this subsection, except for the subsection number and title, with the following:
Traffic is not allowed on the cold planed surface. Before opening the area to traffic, pave the surface according to 00745.51.
SECTION 00730 - EMULSIFIED ASPHALT TACK COAT
Comply with Section 00730 of the Standard Specifications modified as follows:
00730.90 Payment - Replace this subsection, except for the subsection number and title, with the following:
No separate or additional payment will be made for Emulsified Asphalt tack coat.
SECTION 00745 - ASPHALT CONCRETE PAVEMENT - STATISTICAL ACCEPTANCE
Comply with Section 00745 of the Standard Specifications modified as follows:
Materials
00745.11(a) Asphalt Cement – Add the following to the end of this subsection:
Provide PG 70-22 ER grade asphalt cement for this project.
00745.47(a)(2) Wearing Course - Replace this subsection, except for the subsection number and title, with the following:
Construct longitudinal joints six inches from permanent lane markings, or as shown or directed.
00745.51 Opening Sections to Traffic - Schedule Work so that, during the same shift, the surfaces being paved are paved full width and length through the wearing Course before opening to traffic.
Measurement
00745.80 Measurement - Add the following paragraph to the beginning of this subsection:
Replace the paragraph that begins "The quantities of ACP..." with the following paragraph:
The quantities of ACP will be measured on the weight basis. No separate measurement will be made for asphalt cement used in the mixture. No deduction will be made for lime or any other additives or treatments used in the mixture.
00745.90 Payment -
Add the following paragraph to the end of this subsection:
No separate or additional payment will be made for asphalt cement, additives, or treatments used in the mixture.
00745.95 Price Adjustments - Delete this subsection.