This Statement of Work is prepared by the Oregon Department of Transportation (ODOT) for the Building A HVAC Controls Replacement Project located at 455 Airport Road SE, Salem, Oregon. The project encompasses the design and implementation of a DDC control system replacement using Automated Logic Controls to improve energy efficiency and simplify operational control of HVAC units. The scope of work includes replacement of existing controllers (SF1 and SF2 American Auto-Matrix GPC1 units, a Boiler American Auto-Matrix GPC1 with IOX2 Expansion Module, and VAV controllers serving 15 VAVs on the first floor and 21 VAVs on the second floor). The contractor must ensure that Building B operates independently of Building A upon project completion and must maintain building climate control at 70 degrees plus or minus 2.5 degrees throughout construction. Work is to be performed between 5 PM and 6 AM, with substantial completion required by January 30, 2027, and final completion by February 5, 2027. The ODOT Project Manager is Austin VanNette (503-507-1394; Austin.van_nette@odot.oregon.gov). Contractors must conduct a pre-bid site visit to examine existing conditions and submit any clarifications in writing prior to installation.
The Statement of Work requires contractors to provide all labor, materials, equipment, and services necessary for project completion, including installation, testing, design, and configuration in accordance with manufacturer specifications. Contractors must submit detailed submittals for approval prior to on-site work and contact the Project Manager at least ten business days before commencing work. Oregon prevailing wage rates apply to this project, with contractors required to submit weekly Certified Payroll Reports. The contractor is responsible for obtaining all necessary permits and coordinating all subcontractors and suppliers. Upon completion, the contractor must provide one-year installation warranty on all workmanship, manufacturer warranties for equipment, as-built marked drawings, digital copies of operations and maintenance information, equipment details including serial numbers, and full instruction to ODOT personnel on system operation and maintenance. The contractor must also provide signed certification of full payment to all subcontractors and suppliers prior to final payment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment B - Sample Contract~20.docx | DOCX document | |
| Reference Document Points.xlsx | XLSX spreadsheet | |
| Reference Document Technical Analysis Survey.pdf | ||
| Reference Document As-Builts.pdf | ||
| 00018211_RFCQ.docx | DOCX document | |
| Exhibit 3 - Specifications.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT 4
Statement of Work 7/30/26 Oregon Department of Transportation
BLDG A HVAC Controls Replacement Project Location:
Building A 455 Airport Rd SE Salem, OR 97301 ODOT Contact:
The ODOT Project Manager for this project is Austin VanNette.
· E-mail: Austin.van_nette@odot.oregon.gov
· Cell: 503-507-1394
· Address: 455 Airport Rd SE Salem OR 97301 The ODOT Project Manager may designate an additional ODOT contact person or engineer to support with inspections or questions in the field.
Project Background This project is to update the HVAC controls to improve energy efficiency and simplify operational control of the units. The Cooling units were replaced in 1997 and a Control System was installed at that time. In 2026 ODOT replaced the Cooling units with Valent VR-400-30L-0-G0 units.
Project Description:
This project includes the design and implementation of a DDC control system like for like at Building A utilizing Automated Logic Controls. The system must meet the attached specifications to ensure seamless integration and operation. This new system will be to replace the existing outdated control system. New system must be installed in a way that does not interrupt the climate control of the building, or the Contractor must provide auxiliary heating or cooling to accommodate required building temperatures. The current system is tied in with Building B. Building B must be able to work independent of Building A upon completion of the project and is also a requirement of this project. Work to be performed between the hours of 5PM and 6AM. Work to include the replacement of these listed controllers:
· SF1-American Auto-Matrix GPC1 located in RTU
· SF2-American Auto-Matrix GPC1 located in RTU
· Boiler-American Auto-Matrix GPC1 with IOX2 Expansion Module located in control compartment of boiler room on west wall
· VAV Conrollers serving SF1-American Auto-Matrix SBCVAV controllers 1 each for 15 vav’s located first and second floors above ceilings
· VAV Conrollers serving SF2-American Auto-Matrix SBCVAV controllers 1 each for 21 vav’s located first and second floors above ceilings Oregon Department of Administrative Services (DAS) HVAC Controls will provide a detailed sequence of operations that runs all of the building equipment currently for a contractor to replicate
Contractor Coordination required during Construction with DAS to remove necessary points, programs, groups and controllers out of the existing SAGE and relocate it over to Building B until that control system is replaced.
Detailed Project Specifications:
See attached drawings and specifications for details.
1. Equipment list:
· Automated Controls
· Basis of design is Automated Logic Systems.
2. Outline of work:
· Install, test, design, and configure all equipment as needed in Building A in accordance with manufacturer’s written instructions.
· Install, test, design, and configure all equipment as needed Ensure Building B has the ability to operate independently of Building A.
· Perform work in a way that does not affect building climate control or provide supplemental heating or cooling during this period to maintain 70 degrees + or – 2.5 degrees.
General Construction Notes:
· Work to be performed between the hours of 5PM and 6AM.
· The contractor shall make a site visit and examine existing conditions prior to providing a bid. Any discrepancies shall be brought to the attention of ODOT through a request for clarification as set forth in the bid documents.
· Clarifications shall be requested in writing prior to any installation. Incorrect installations shall be corrected at no additional cost to ODOT.
· All work shown is to be by the contractor unless specifically noted as being by ODOT or by others. All materials shown are to be provided by the contractor unless specifically noted as existing or provided by ODOT.
· Drawings are schematic in nature, major components and equipment are shown on the drawings. The contractor shall supply and install all minor components and materials necessary to provide a complete and functional project whether all such components are noted in the drawings and specifications.
· Plans and specifications call out specific makes and models of equipment in some locations. Substitution requests shall be made during the bid process. ODOT shall at its sole discretion determine the acceptability of substitutions. No substitutions shall be installed without prior written approval from the ODOT Construction Project Manager.
· All equipment and materials shall be installed in accordance with the manufacturer’s published installation instructions and recommendations.
· Clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.
Submittals
The Contractor shall provide the following submittals at a minimum to the ODOT Project Manager. Submittals shall be approved by the ODOT Project Manager prior to the start of on-site construction.
· As detailed in specifications and plans
Scheduling of Contract:
· Substantial completion of the Work shall be no later than 1/30/27. Final completion shall be no later than 2/05/27.
· After award of contract, the Contractor shall contact the ODOT Project Manager to schedule the Work at least ten (10) business days prior to the start of any work/demolition.
· The Work shall be accomplished on weekdays between the hours of 7 a.m. and 5 p.m. Work hours shall exclude weekends and State Holidays, unless specifically requested by the Contractor and approved by the ODOT Project Managers.
· Any permits required for the Work are the responsibility of the Contractor. The Contractor shall provide copies of permits to the ODOT Project Manager prior to the start of work. The Contractor shall be responsible for posting all permits on site in accordance with local jurisdiction requirements.
· The Contractor shall submit to the ODOT Project Managers a list of the contact information for the Contractor’s project manager and site superintendent, as well as a list of all Subcontractors and their key representatives.
· The Contractor shall coordinate the efforts of all Suppliers and Subcontractors and shall maintain orderly progress of the Work, prevent duplication of effort, and ensure proper sequence of operations.
Clean-Up/Conditions of Site:
· The Contractor shall be responsible for keeping the ODOT Project Manager informed of all activity throughout the Work.
· The Contractor shall clean up all worksite debris resulting from construction and remove all excess construction materials and scraps from the premises. The Contractor shall broom-clean their work area at the end of each workday and neatly stack materials and debris in an approved location. The contractor shall clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.
· The Contractor shall protect materials subject to damage by temperature or other weather conditions.
· The location for storage of materials, debris, or dumpster on the Premises shall be approved in advance by the ODOT Project Manager. Disposal facilities, bins, or dumpsters shall not be provided by ODOT.
· The Contractor shall notify the ODOT Project Manager at least two (2) days in advance of any major deliveries.
· Contractor shall immediately notify the ODOT Project Manager of any damage done by the Contractor to the Premises, grounds, or adjacent State properties. Damage done by the Contractor to the Premises or surrounding area shall be repaired to existing conditions as found prior to the commencement of the Work.
· ODOT shall not be responsible for the security of the Contractor’s materials, tools, personal belongings, or equipment on the Premises.
· It is the responsibility of the Contractor to ensure the Work is performed in accordance with Oregon OSHA rules and regulations.
· The Contractor shall immediately bring to the attention of the ODOT Project Manager any conflicts or issues between existing utilities and the Work.
BOLI:
· BOLI Prevailing Wage Rates apply to this project. Provide weekly Certified Payroll Reports for General Contractor and all subcontractors as a prerequisite for progress payment approval.
Close Out:
· All special inspections must be complete prior to Substantial Completion.
· Inspection of the work by the ODOT Project Manager for establishment of Substantial Completion shall be made within five (5) business days after receipt of the Contractor’s email request. At this time, the ODOT Project Manager and the Contractor shall develop a punch list document of any incomplete or deficient work.
· Prior to Final Completion, the Contractor shall complete all items on the punch list.
· The Contractor shall provide final inspection reports for all permits applicable to this Contract signed by authorities having jurisdiction
· The Contractor shall maintain one set of the approved drawings for recording as-built conditions. Mark (in red) the actual location of all underground utilities and any changes. At the time of Final Completion, the Contractor shall turn over the one marked-up set of record drawings to the ODOT Project Manager.
· Prior to Final Completion, the Contractor shall provide one (1) digital copy via email of all operations, maintenance, and warranty information to the ODOT Project Manager.
· Prior to Final Completion, provide ODOT Project Manager with information for all equipment provided by the project, including but not limited to: Manufacturer, model, serial number, consumables, installation date, purchase date.
· Prior to Final Completion, and as prerequisite for final payment, provide ODOT Project Manager with signed certification that all subcontractors and suppliers have been paid in full and in compliance with all prompt payment requirements. All disputes with property owners have been resolved, all obligations on the project have been satisfied, all monetary claims and indebtedness have been paid, and, to the best of the Contractor's knowledge, there are no claims of any kind outstanding against the project.
· Prior to Final Completion, the Contractor shall fully instruct ODOT’s operating and maintenance personnel in the operation, adjustment, and maintenance of products, equipment, and systems.
· Inspection of the work by the ODOT Project Manager for establishment of Final Completion shall be made within five (5) business days after receipt of the Contractor’s email request.
Warranty:
· Contractor shall provide a 1-year Installation warranty on all workmanship.
· Contractor shall provide all warranties for equipment applicable to this Contract Revision: 5/7/24