Exhibit 2 - NMWDA Contract 0964_Kane Street_Special_Provisions_July 2026.pdf

PDF 11 MB Posted

Attached to
Request for Proposals for Kane Street Sanitation Yard Renovation Construction Services
Solicitation number
BPM058404
Issued by
Baltimore City, Maryland

About this file

This is the Special Provisions document for NMWDA Contract No. 0964, a construction project managed by the Northeast Maryland Waste Disposal Authority in coordination with the City of Baltimore. The project involves the comprehensive renovation of the Kane Street Sanitation Yard facility located at 111 Kane Street, Baltimore, Maryland 21224. The scope of work includes demolition and removal of approximately 7,300 square feet of existing interior office spaces, demolition of an existing 40,000-square-foot concrete floor with installation of trench drains and placement of new reinforced concrete flooring, construction of approximately 8,900 square feet of finished office space including bathrooms and locker areas, replacement and repair of windows and doors, electrical system upgrades including EV charging infrastructure, plumbing and HVAC improvements, vehicle wash system installation, ADA-compliant ramp construction, new parking spaces, security features, landscaping, and furnishing of temporary office and locker room trailers. The contract time for completion is 365 consecutive calendar days, with specific construction schedule constraints including prohibitions on garage floor replacement between December 15 and March 15 to maintain facility operations during winter months. The contractor must coordinate with the City's Department of General Services remediation contractor regarding asbestos and lead paint removal before demolition activities begin.

The contract requires the contractor to submit a Quality Control Plan within fifteen days of Notice to Proceed and comply with strict inspection, testing, and documentation requirements for all definable features of work. Local hiring requirements under Baltimore City Code Article 5, Subtitle 27 apply to this contract, with contractors required to meet with the Mayor's Office of Employment Development within two weeks of award to complete an employment analysis and workforce plan, with at least 51 percent of new jobs to be filled by Baltimore City residents. Minority and Women's Business Enterprise (MBE/WBE) participation goals are specified for the contract in accordance with Baltimore City Code Article 5, Subtitle 28, with bidders required to submit completed Statement of Intent Forms and MBE/WBE Participation Affidavits with their proposals. The contractor must comply with prevailing wage rates established for the City of Baltimore, maintain water conservation measures throughout the project, provide pre-construction photographs and video documentation, and submit final as-built drawings sealed by a Maryland-registered Architect or Engineer. Overtime reimbursement is charged at $32.00 per inspector hour when contractors elect to work beyond normal business hours, and the contractor must obtain required permits from the Baltimore City Department of Transportation and coordinate with various city agencies regarding utilities, street lighting, and public notifications for scheduled underground utility work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NMWDA CONTRACT NO. 0964

KANE STREET SANITATION YARD RENOVATION

July 2026

I. SPECIAL PROVISIONS

I. SPECIAL PROVISIONS

A. INSTRUCTIONS TO BIDDERS

B. SPECIAL CONDITIONS

C. CONSTRUCTION DETAILS AND MATERIALS

D. STANDARD DETAILS

E. MINORITY AND WOMEN’S BUSINESS OPPORTUNITY REQUIREMENTS

F. LOCAL HIRING LAW

G. PREVAILING WAGE RATES – CITY OF BALTIMORE

EXHIBIT 2 - ISSUED FOR PROPOSALS

July 2026

SP-1 CONTRACT DOCUMENTS

The Contract Documents for this project shall consist of but not be limited to the following:

ITEM 1 - Contract Book which contains:

I. Special Provisions A. Special Conditions B. Construction Details and Materials C. Standard Details

II. Bid or Proposal and Detached Duplicate III. Agreement IV. Bonds

ITEM 2 - Contract Plans

Plans and details are provided for the preparation of a bid proposal. The Engineer will furnish, from time to time as the work progresses, such supplemental Drawings as may be necessary for further illustrating the details of the permanent work, and the Contractor will be required to abide by any modifications, and supplemental Plans and Specifications that may be furnished by the Engineer.

ITEM 3 - Standard Specifications

A. The City of Baltimore, Department of Public Works, Specifications for Material, Highways, Bridges, Utilities and Incidental Structures, Issue of 2006, or the most recent version and any and all Amendments thereto, are hereby made part of these Contract Documents and hereinafter referred to as "Standard Specifications". Any references in the Contract Documents made to an Article, Section, Paragraph or Table shall refer to the Standard Specifications, unless otherwise noted. Electronic version can be found at:

https://publicworks.baltimorecity.gov/greenbook

B. Federal Highway Administration’s Manual of Uniform Traffic Control Devices (MUTCD) and the Maryland State Highway Administration (SHA) Standard Specifications for Construction and Materials, latest revisions, as specified herein, shall be considered part of these Contract Documents.

ITEM 4 – Book of Standards

The City of Baltimore, Department of Public Works, Book of Standards, and any and all Amendments thereto, are hereby made a part of these Contract Documents and hereinafter referred to as “Book of Standards”.

Any reference in the Contract Documents made to a Standard Number, shall refer to the Book of Standards, unless otherwise noted.

https://publicworks.baltimorecity.gov/greenbook

July 2026

SP-2 WATER CONSERVATION/ RESTRICTION IMPLEMENTATIONS

The Contractor shall make every effort to conserve water on all phases of this project. All temporary bypass piping shall be maintained in an effort to minimize any leakage or failures. All failures must be addressed as soon as possible and any leakages must be kept to a minimum. Flushing shall be done to the extent necessary to achieve the required results and not as a matter of convenience. All bypass piping shall be valved in a manner to minimize the loss of water in case of a failure or a when a repair is required.

The City reserves the right to suspend and/or terminate this project for the safeguard of the public good, at its sole discretion. The City reserves the right to impose water conservation requirements on the Contractor, at his expense, when drought restrictions are implemented, in lieu of suspension of work.

In the event that a suspension and/or termination of the work is necessary, the Contractor will be required to complete any and all tasks deemed necessary to close the project down in a manner that ensures the public safety.

A. INSTRUCTIONS TO BIDDERS

IB-1 PURCHASE OF THE STANDARD SPECIFICATIONS AND BOOK OF

STANDARDS

1. The Standard Specifications is not available for print at this time. Please refer to the electronic copy located at: https://publicworks.baltimorecity.gov/greenbook

2. For the Baltimore City Departmnet of Transportation (BCDOT) Book of Standards, please refer to the webpage located at: https://www.baltimorecity.gov/book-of-standards

IB-2 SCOPE OF WORK

The work to be done under this Contract shall consist of the following principal items:

• Demolition and removal of existing interior office spaces with an area of approximately 7,300 square feet.

• Demolition and removal of an existing concrete floor with an area of approximately 40,000 square feet, installation of trench drains and associated piping, and placement of a new reinforced concrete floor.

• Construction of approximately 8,900 square feet of finished office space, including bathrooms and locker areas.

• Replacement of existing windows and installation of new windows in the existing brick masonry exterior.

• Repair of masonry veneer at damaged locations.

• Replacement of existing exterior entry doors, repair and replacement of roll-up doors

• Removal of existing electrical distribution cabinets and panels and installation of new electrical equipment, conductors, connections, lighting and controls.

• Infrastructure for future electric vehicle (EV) charging.

• Plumbing improvements.

• HVAC equipment installation.

• Installation of a vehicle wash system, including a new connection to the existing facility sewer, an oil and grease separator, a dedicated compressor, hoses and hardware.

• Installation of an ADA-compliant ramp on an existing concrete sidewalk.

• Full depth pavement for five (5) new parking spaces.

• Security gates and fencing.

• Exterior Parking area and interior Garage area painting, striping, and signage.

• Site landscaping.

• Furnish and install temporary office and locker room trailers.

The Contractor shall perform all work in accordance with the Contract Documents, including furnishing all labor, materials, tools, supplies, equipment, transportation and all other things necessary for the satisfactory prosecution and completion of all work in full compliance with the Contract requirements and all incidental work necessary to complete the Project in an acceptable manner.

The complete scope of work shall be covered by items listed in schedule of prices, as well as by “Special Provisions”.

https://publicworks.baltimorecity.gov/greenbook https://www.baltimorecity.gov/book-of-standards

IB-3 LOCATION OF WORK

Supplement Standard Specification Section 00 21 13.02, LOCATION OF WORK with the following:

The location of work shall be the Kane Street Sanitation Facility, 111 Kane Street, Baltimore, MD, 21224.

IB-4 PROJECT CONSTRUCTION SCHEDULE

There are constraints on when the work can take place at the Kane Street facility that are necessary for the continuity of facility operations. The Contractor’s construction schedule should make accommodations for the following:

1) Garage floor replacement may not occur between December 15 and March 15;

2) Temporary offices for city staff must be operational before office demolition may proceed;

3) Contractor is suggested to perform exterior work while temporary office trailers are delivered and installed;

4) Contractor is suggested to perform work in the general order as follows:

a. Loading Dock/Warehouse repairs

b. Office demolition and construction

c. Garage demolition and construction.

5) Contractor shall coordinate with the Baltimore City Department of General Services remediation contractor to schedule asbestos and lead paint remediation activities in the office, warehouse, and loading dock before demolition is conducted in those areas.

6) The Kane Street facility will need to maintain indoor operational space during the winter, December 15 to March 15, so the street sweeper vehicles can be properly stored and maintained.

IB-5 CONTRACT TIME FOR COMPLETION

Time is of the essence. The Contract Time for completion of the work described by the Contract Documents will be 365 consecutive calendar days.

IB-6 LOCAL HIRING LAW

Article 5, Subtitle 27 of the Baltimore City Code, as amended (the “Local Hiring Law”) and its rules and regulations apply to contracts and agreements executed by the City on or after the Local Hiring Law’s effective date of December 23, 2013. The requirements for the Local Hiring Law are summarized below:

A. The Local Hiring Law applies to the original term of the contract award greater than $300,000.00, in addition to any contract modification (amendment, renewal, extra work or change order). Whether a City subsidized project is subject to the Law shall be finally determined when an agreement authorizing assistance valued over $5,000,000.00 is executed by the City. Please visit www.oedworks.com for details on the requirements of the Law.

http://www.oedworks.com/

B. Within two (2) weeks of the Board of Estimate’s award of the contract or approval of the agreement, the contractor shall have a meeting, either in person or via telephone, with MOED to complete an employment analysis and review the workforce plan required for such contract or agreement. The contractor will not receive any payments under the contract or agreement, unless and until the employment analysis is performed. Contact information for MOED can be found on its website:

www.oedworks.com.

C. Should the contractor’s workforce plan indicate a need to fill new jobs, the contractor shall post the new job openings with MOED’s One Stop Career Center Network for a period of seven (7) days prior to its publicly advertising these openings. Further, the contractor shall interview qualified Baltimore City residents referred from MOED; and unless granted an exception, fill at least fifty-one percent (51%) of the new jobs required to complete the contract or project with Baltimore City residents.

D. For all contracts subject to the Local Hiring Law, the contractor shall submit an Employment Report to MOED by the fifth (5th) day of each month throughout the duration of the contract or agreement, regardless of whether MOED has granted a waiver of any of the Local Hiring Law’s requirements.

E. All reports that are sent to MOED must be sent to the City Resident Engineer/Project Manager at the same time via email. Confirmation of sent report are made at monthly construction meetings.

IB-7 UNRESPONSIVE AND UNBALANCED BIDS

Supplement Standard Specification Section 00 51 00.05, UNRESPONSIVE AND UNBALANCED BIDS, with the following:

1. All bid item prices should be reflective of the materials, labor, equipment, overhead and profit costs required to complete the bid item.

2. Bidders are advised that when the bid prices are not proportionate with the bid item work involved the bid will be considered mathematically unbalanced and may be subject to further review.

3. Bids may be rejected if the City determines that any of the bid prices are mathematically and materially unbalanced and there is reasonable doubt that the bid will result in the lowest ultimate cost to the City.

http://www.oedworks.com/

B. SPECIAL CONDITIONS

SC-1 SPECIAL CONSIDERATIONS AND/OR REQUIREMENTS 8

SC-2 OVERTIME REIMBURSEMENT 8

SC-3 WORK RESTRICTIONS 8

SC-4 CITY PROPERTY AND STREETS 8

SC-5 PAYMENT TO SUBCONTRACTORS 9

SC-6 CONSTRUCTION PHOTOGRAPHS 9

SC-7 SHOP DRAWINGS SUBMITTAL 10

SC-8 CONTRACTOR’S QUALITY CONTROL 10

SC-9 PROJECT IDENTIFICATION 12

SC-10 AS-BUILT SUBMITTAL AND WORKING DRAWINGS 13

SC-11 PUBLIC NOTIFICATION FOR SCHEDULED UNDERGROUND UTILITY

WORK 13

SC-12 STEEL PLATE POLICY 16

SC-13 SELECTED BACKFILL 16

SC-14 STREET CUT AND RESTORATION OF PAVEMENT POLICY AND PAYMENT

SC-15 TEMPORARY PAVEMENT 19

SC-16 PERMANENT PAVING RESTORATION 21

SC-17 STREET LIGHTING 21

SC-18 SUPPORT AND/OR PROTECTION OF EXISTING UTILITIES 22

SC-19 SCHEDULES AND REPORTS 22

SC-20 REVISIONS TO THE ASPHALT PAVING SPECIFICATIONS 22

SC-21 EXPERIENCE REQUIREMENTS FOR GPS USE 25

SC-22 MATERIAL TO BE SUPPLIED BY BALTIMORE CITY 25

SC-1 SPECIAL CONSIDERATIONS AND/OR REQUIREMENTS

Supplement Standard Specification Section 01 11 00 with the following:

1. There is no lump sum bid item or payment for Mobilization. The cost of mobilization shall be reflected in the Contractor’s bid for each item of work.

2. There is no lump sum bid item or payment for Erosion and Sedimentation Control. The cost of erosion and sedimentation control shall be reflected in the Contractor’s bid for each item of work.

3. No excavated material shall be stockpiled on site, without the prior approval by the Engineer;

all excavated material must be removed from the work sites immediately.

SC-2 OVERTIME REIMBURSEMENT

The Contractor shall reimburse the City for inspection and other services required when and if, the Contractor chooses to work in excess of the normal eight (8) hour workday, forty (40) hour work week, weekends, or on a City holiday as designated by the City Labor Commissioner, available at http://labor-commissioner.baltimorecity.gov/official-city-holidays. The amount due the City shall be deducted from the Contractor’s monthly pay estimate at the hourly rate of $32.00. The rate specified is per inspector on the project while the overtime work is ongoing. The Contractor should assume that, if one (1) to two (2) crew is working, one (1) inspector will be on site. If three (3) to five (5) crews are working, two (2) inspectors will be on site. If more than five (5) crews are working, three

(3) inspectors will be on site. This overtime reimbursement will not apply to overtime work done at the City’s request.

SC-3 WORK RESTRICTIONS

Supplement Standard Specification Section 01 14 00, WORK RESTRICTIONS with the following:

Unless otherwise specified or directed by the Engineer, the regular working day shall begin no earlier than 7:00 AM.

Supplement Standard Specification Section 01 14 17, NIGHT WORK with the following:

All water main shutoffs affecting a school building or similar institutions shall be initiated and completed during a period when the affected facility will be closed. In case of water service disruptions affecting commercial buildings, the same shall take place during the period when it causes least disruption of operations in consultation with the business/property owners. The proposed water main work affecting such consumers may be required to be scheduled outside of normal business hours, on nights, weekends, and/or holidays.

SC-4 CITY PROPERTY AND STREETS

Supplement 01 14 20 with the following

In order to work in the public right-of-way, the Contractor must obtain permits from the Department of Transportation. Applications for permits may be obtained at:

http://labor-commissioner.baltimorecity.gov/official-city-holidays

Department of Transportation Permit Division Harry S. Cummings Building 401 East Fayette Street, 1st Floor Baltimore, Maryland 21202

(Phone: 410-396-4508)

The Contractor shall be responsible for applying for any permits that may be required sufficiently in advance of the scheduled construction operations in order that the progress of the work is not delayed.

The obtaining of the required permits in a timely fashion shall be the Contractor’s responsibility.

Materials and equipment that cannot be stored within the Project limits shall be removed and stored at an off-site location as approved by the Engineer.

The Contractor shall protect all existing buildings, utilities, fire hydrant and other property in and adjacent to the Project site. No property may be cut, marked or defaced.

SC-5 PAYMENT TO SUBCONTRACTORS

In accordance with the Baltimore City code, Article 5, § 28-55, the payment to the subcontractors must be made within seven (7) calendar days after the prime contractor receives payment from the City. All other terms and conditions of the Baltimore City Code, and Baltimore City Standard Specifications shall apply.

SC-6 CONSTRUCTION PHOTOGRAPHS

Delete Standard Specification Section 01 32 33, CONSTRUCTION PHOTOGRAPHS in its entirety and replace with the following:

A. Photography.

1. Submit prior to beginning any Work that may cause site disturbance.

a. Digital, date-stamped, color photography provided in CD disc format.

1) Photographs:

a) Take at sufficient intervals to fully document the pre-construction conditions of the work site, not more than 100 feet apart along the street and/or right of way.

b) Progress photos in one month intervals to be submitted with the invoice and; as documentation with requests for Change Orders.

c) Include identification markers such as room names, column numbers, in each view to properly confirm location of the view for ease of identification.

d) Each photo shall be identified by a location and a compass direction.

e) Devote particular attention of existing damage to streets, curbs, sidewalks, driveways, signs, mailboxes, retaining walls, landscaping, etc.

f) Out of focus photos will not be accepted.

b. Submit Photo log along with CD disc that provides;

1) Name and number of the contract.

2) Name of Contractor.

3) Name of photographer.

4) Include for each photograph;

a) File name

b) Date taken

c) Location and direction of the view

B. Pre-Construction Video.

1. Document by video, and submit in digital format on DVD;

a. All existing site conditions adjacent to and within the limits of construction.

b. Clear and continuous view of the project alignment.

2. Submit prior to beginning Work that may cause site disturbance.

All costs associated with pre and post construction photographs and video shall be considered incidental to all bid items in this Contract and no separate payment will be made.

SC-7 SHOP DRAWINGS SUBMITTAL

Supplement Standard Specification Section 01 33 21 CONTRACT DOCUMENTS, WORKING DRAWINGS, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES, with the following:

V. The Contractor shall submit shop drawings for approval, prior to ordering the materials. All shop drawings, catalog cuts, etc. shall be submitted in electronic (PDF) format.

W. Subject to 01 33 21, Paragraph A, shop drawings and product data are required for every element of the Work. Upon written request from the City or Engineer, the Contractor shall submit any requested drawings, data sheets, catalog cuts, samples, or other shop drawing materials within seven (7) calendar days.

SC-8 CONTRACTOR’S QUALITY CONTROL

Supplement Standard Specification Section 01 45 00 with the following:

1.1 Within fifteen days after Notice to Proceed has been issued, Contractor shall submit a Quality

Control Plan to Engineer for review.

A. Contractors Quality Control Plan shall include but is not limited to:

1. Definable features of work.

2. Assigned individuals, independent testing agencies, and manufacturers who will be responsible for the Contractor’s required testing and inspections.

3. Contractor shall submit for approval independent testing agencies for all necessary testing and inspection required for the Contractor’s quality control program.

4. Resumes of individuals who are assigned to perform required inspections as part of the Contractor’s quality control program.

5. A description of how Contractor will verify and document contract and specification compliance.

6. Testing Plan: The Contractor shall prepare a testing plan and submit to the City and Engineer for review and acceptance. The testing plan shall list and describe planned testing for all definable features of the Work, the governing agency standards, and the methods Contractor will use. The testing plan shall describe testing procedures, including equipment, materials, chemicals used, points of injection, sample points, injection equipment, drain and discharge points, and point of discharge, particularly if discharge will be into the City’s sewer or storm drain system.

7. Testing logs and schedules: Logs and schedules shall include all required tests and inspections, locations of scheduled tests, date of tests, type of test, length of test for all definable features of work. Special consideration will be paid to all piping to be tested in regards to lengths of piping and appurtenances tested, testing pressures, amounts of chemicals used for disinfection, chlorine residual results, disinfection results, dates of test results, and if test was successful or a re-test is required.

i. Testing shall be shown in the project’s CPM schedule and shall be cost loaded and show expected durations.

ii. Contractor shall keep up to date and accurate documentation of all testing performed, including all testing and results from City performed tests.

iii. Contractor shall provide to the Engineer copies of all field reports and certified lab reports from all testing agencies, agents, and manufacturers.

8. Inspection plan: Contractor shall perform all required inspections for compliance on delivered materials and or equipment and document the results. If any deficient and or non-compliant materials or equipment are encountered, Contractor shall immediately inform the Engineer, and shall clearly mark the deficient/non-conforming materials or equipment as such, so these materials or equipment shall not to be used. Contractor shall remove them from site immediately.

i. Provide updated testing documents to the City for review on a monthly basis.

ii. Contractor shall provide to the Engineer Certificates of Proper Installation

(COPI) for all equipment and machinery installed. COPI shall be signed by the manufacturer, the Contractor and the City of Baltimore or their appointed representatives. Contractor shall demonstrate to the City of Baltimore that all equipment, machinery, and appurtenances installed as part of the Contract operate in accordance with the Contract requirements. City and Contractor shall both sign a certificate of acceptance. City will not accept any deliverable without a COPI and certificate of acceptance. City of Baltimore reserves the right to withhold payment until such certificates are provided to the Engineer as part of the required close out documents. This clause will be applicable only to the following appurtenances:

• HVAC System

• Fire protection System

• Vehicle Wash system

• EV Charging System

iii. Contractor shall at all times keep on site all quality control documentation for review.

B. Contractor shall be responsible for all quality control requirements of their sub-contractors.

C. Contractor shall notify City of Baltimore a minimum of 48 hours in advance, in writing, for any testing and or inspections to be performed, either by Contractor or by the City of Baltimore or their respective sub-contractors.

1.2 Testing

A. All required testing to be performed by the Contractor or approved testing agencies shall be incidental to the work being performed at no additional cost to the City.

B. Contractor shall be responsible for testing density and compaction of all backfill materials per required specifications. All testing shall be incidental to the work being performed at no additional cost to the City.

C. Contractor shall be responsible for the testing of all cast in place concrete per required specifications. All testing shall be incidental to the work being performed at no additional cost to the City.

D. The cost of any retest due the Contractors, negligence, neglect or work failing to meet the required specification shall be borne solely by the Contractor. Contractor shall not be allowed to claim for delay due to any failing tests.

1.3 Failure on the part of the City of Baltimore and or its sub-contractors and or appointed agents to implement specific testing and inspections as part of the contract testing and inspection requirements, shall not relieve the contractor of his obligations to perform the necessary testing and inspections in accordance with the contract requirements.

SC-9 PROJECT IDENTIFICATION

Supplement Standard Specification Section 01 58 00, PROJECT IDENTIFICATION, with the following:

B.

8. The signs shall be installed prior to start of work and be removed when directed by the

Engineer, and shall then become the property of the Contractor.

9. Furnishing, installing, and maintaining project information sign(s) shall not be measured, but the cost shall be considered incidental to the individual bid items.

C. The Contractor shall furnish, install, and maintain project signs on this Project, in accordance with the City Of Baltimore DPW Specifications for Materials, Highways, Bridges, Utilities, and Incidental Structures, 2006 version, using the design listed below, at locations as directed by the Engineer:

Mayor Brandon M. Scott

SC-10 AS-BUILT SUBMITTAL AND WORKING DRAWINGS

Add the following immediately after the last sentence of Standard Specification Section 01 78 39, PROJECT RECORD DOCUMENTS, paragraph C:

1. The Contractor shall furnish to the City and Engineer for review and acceptance, a complete set of final as-built drawings that include, but are not limited to, the building floor plan; the property site plan; complete drawings of mechanical, electrical, and plumbing systems; and any and all such drawings as necessary to illustrate all changes to the Contract Drawings and to document all completed work.

2. Within 14 calendar days of receiving all the as-built drawings, the City and Engineer may submit comments, additions, and corrections to the Contractor, who shall execute the changes to the as-built draings promptly, and return the corrected as-built drawings for review and acceptance.

3. Final as-built drawings shall be sealed by a Maryland-registered Architect or Engineer, as appropriate, attesting to the completeness and accuracy of the drawings.

4. The Contractor shall furnish to the City and Engineer for review and acceptance, a version of the as-built drawings in digital format, assumed to be compatible with AutoCAD version 2022, or another format mutually agreed with the City and Engineer.

SC-11 PUBLIC NOTIFICATION FOR SCHEDULED UNDERGROUND UTILITY

WORK

When underground utility work is scheduled on or adjacent to private property, the Contractor shall prepare and distribute the attached notification to those residences, institutions and businesses that will be impacted by the work. Neighbors on the fringes of the work who might have the slightest chance of being impacted should also receive a notice.

Instances requiring 72-hour or more notification:

Scheduled and unscheduled contract work, Water outages, Possible or expected discolored water, Possible or expected low water pressure, Paving disturbances – sidewalks, streets and alleys, Removal of vegetation including lawns, shrubs and trees, Street closures and detours, Barriers to vehicles and pedestrians, The erection of temporary structures or temporary mains, Loud noise - especially near institutions, e.g. schools and churches, and at night, Other circumstances where a courtesy or safety notification may be in order.

The attached notification is required, except in case of water emergencies, and must be distributed at least one week in advance, preferably two weeks in advance of the start of the work, due to the potential to disrupt activities at the Patterson High/Middle School located across the street from the area of work.

Water emergencies are generally defined as:

Unanticipated damage on a main, valve, hydrant or drain requiring immediate attention, Flooding of public or private property, Work related to immediate public safety and health considerations. (This would include sewage overflows, hydrant work where backup protection is unavailable, off-site valve repair or replacement to address a shutdown on a broken main, etc.)

Action related to providing immediate assistance to other agencies or utilities. (This would include aid to BGE, Trigen, City and County Fire Departments as emergencies warrant, such as gas and steam leaks, fires, train derailments, etc.)

It shall be the Contractor's responsibility through the Engineer, to notify in writing all consumers affected, and provide them with an emergency phone number and contact person. The Contractor may need to re-notify those consumers, once the water outage ends and just before they are returned to regular service and shall direct them to flush their in-house plumbing by running water and temporarily removing aerators, after they are returned to regular service. In addition, the Contractor shall:

1. Notify and e-mail the completed UTILITY WORK NOTIFICATION form and the temporary water plans to Chief James Wallace of the Baltimore City Fire Dept. at:

Paul.Demme@baltimorecity.gov.

2. Provide the Engineer with any information to be provided along with the notifications for prior approval by the Engineer.

3. Provide the Engineer with a list confirming the number, locations, and dates the notifications were delivered, of which the Engineer will verify.

Unless otherwise directed, the Contractor will be responsible for distributing all notices to consumers as well as other City entities for the duration of this contract, and the cost for the same shall be considered incidental to the utility bid item(s) in this Contract. If one or more shutoff valves do not work, additional valves may need to be operated to achieve the complete shutdown. In such case, the Contractor shall be required to notify any and all consumers at no extra cost to the City.

mailto:James.Wallace@baltimorecity.gov

SC-12 STEEL PLATE POLICY

A. All excavations and trenches shall be protected by steel plates at the end of each workday.

“STEEL PLATES AHEAD” warning signs shall be displayed in advance, when the steel plates are placed in streets open to public traffic.

B. Unless otherwise specified or directed, all Steel Plates shall be installed in accordance with

Baltimore City Standard Detail BC 576.17-1, or the latest revision thereto. All Steel Plates or temporary paving patches shall be clearly marked so that ownership is easily discernible.

C. Steel plates shall not be used in lieu of temporary paving. No steel plates shall be kept in place for an extended period of time, unless authorized by the Engineer in writing. Those steel plates that need to be in place for an extended period of time shall be recessed such that the top of the plate is flush with the existing pavement, as per Baltimore City Standard Detail BC 576.17-2.

SC-13 SELECTED BACKFILL

Supplement Standard Specification Section 31 23 23.13, SELECTED BACKFILL, with the following:

For excavation in roadways, the Contractor shall not use the material excavated from utility trenches as backfill material, unless directed otherwise by the Engineer. All other requirements of Specification Section 31 23 33, TRENCHING AND BACKFILLING, POINT EXCAVATION AND BACKFILL, shall apply to utility trenches.

PART 3 EXECUTION:

The use of No. 57 stone shall be limited to the water main related work within the Contract, unless directed otherwise by the Engineer:

For all new water mains related work in this Contract, the Contractor shall use No. 57 stone as a pipe bedding material for 6 inches below the pipe and up to 12-inches above the top of pipe, under valves in roadway boxes, and any appurtenances. From 12-inches above the top of pipe to sub-grade, Crusher Run Aggregate CR-6 shall be used, and placed and compacted in accordance with the Baltimore City Standard Specifications and Details. The Contractor shall follow the Baltimore City Standard Details for use of No. 57 stone for all fire hydrant installations.

All open trenches behind the curb shall be backfilled with existing excavated materials and compacted in place. The backfill shall not contain any rocks larger than six (6) inches in size.

PART 4 MEASUREMENT AND PAYMENT:

Selected Backfill using No. 57 Stone or using Crusher Run Aggregate CR-6, for work performed in accordance with this Special Condition and within the limit of proposed water main work shall not be measured, but will be considered incidental to the appropriate utility bid item in this Contract, and will include all labor, tools, material, equipment, compaction, and incidentals necessary to complete the Work.

SC-14 STREET CUT AND RESTORATION OF PAVEMENT POLICY AND

PAYMENT

Supplement Standard Specification Section 32 01 30.10, PATCH EXISTING PAVEMENT AND RESET UTILITY SERVICES with the following:

For permanent pavement restoration due to utility trench excavation, the Contractor shall not use the surface course restoration section for an Overall Condition Index (OCI) of 3, 4, or 5, unless directed otherwise by the Engineer. All roadways within the City shall be considered to have an Overall Condition Index (OCI) of 1 or 2, or a “Revised” paving status. All other requirements of Baltimore City Standard Specification Section 32 01 30.10 shall apply.

A. PERMANENT PAVEMENT RESTORATION

Permanent restoration of pavement cuts in flexible (HMA) pavement and flexible surface for pavement with rigid base ( composite pavement), shall be in accordance with the Standard Details BC 576.19-1 – BC 576.19-2 and BC 576.20-1 - BC 576.20-2 as modified herein.

For all streets with flexible pavement surfaces, additional milling and resurfacing shall be required to extend the limits of the new HMA surface course beyond the limits of the full depth patch repair, in accordance with Standard Detail BC 576.19-2.

All permanent restoration of rigid pavement, including bus stopping pads, shall be in accordance with the Standard Details BC 500.13 and BC 576.18 – BC 576.18-2 included herein.

Permanent restoration/replacement of rigid pavement in alleys and driveways shall be in accordance with the Standard Details BC 500.01, BC 500.11 and BC 500.12 included herein.

Replaced paving materials and their thickness shall match existing.

Guidelines for Hot Mix Asphalt (HMA) Pavement Sections:

1) Neighborhood Streets - No truck traffic (typical section):

2” HMA Superpave 9.5 mm PG 64-22 for Surface Level 2 (Surface Course) 5” HMA Superpave 19.0 mm PG 64-22 for base Level 2 (Base Course) – (2 lifts of 2.5”)

6” CR-6*

2) Major Routes with truck traffic (typical section):

2” HMA Superpave 12.5 mm PG 64-22 for Surface Level 2 (Surface Course) 7” HMA Superpave 19.0 mm PG 64-22 for base Level 2 (Base Course) – (2 lifts of 3.5”) 12” CR-6 (2 lifts of 6”)*

3) Industrial Area (typical section):

2” HMA Superpave 12.5 mm PG 64-22 for Surface Level 2 (Surface Course) 7” HMA Superpave 25.0 mm PG 64-22 for base Level 2 (Base Course) – (2 lifts of 3.5”) 12” CR-6 (2 lifts of 6”)*

* For pavement outside the planned utility trench, as directed by the Engineer.

Wedge and level if required. Use HMA Superpave 9.5 mm for wedge and level.

NOTE 1: HMA Superpave 19.0 mm PG 64-22 for base Level 2 (base) can be compacted a minimum of 2.0” to a maximum of 4.0” lift thickness (desired lift thickness is 3”).

NOTE 2: Neighborhood Streets and Major Routes shall be as identified in the Contract Drawings, or as directed by the Engineer. Per City DOT, roads classified as primary and/or secondary are considered “major routes”; tertiary roads are considered “Neighborhood Streets”.

NOTE 3: Any pavement cut 5’x5’ or less in size shall be considered as “Intermittent Utility Cuts”.

The Contractor shall follow the appropriate pavement restoration for “Trench Repair” and “Intermittent Utility Cuts”.

B. MEASUREMENT AND PAYMENT

For all permanent pavement restoration for installation of water supply services (WSS), ductile iron pipe and fittings, including 6” hydrant leads, the measurement shall not exceed the “Trench Width for WSS and Ductile Iron Pipe and Fittings” as specified below, plus the appropriate cut backs as specified in the Standard Detail BC 576.19-1 and BC 576.20-1.

TRENCH WIDTH FOR WSS &

DUCTILE IRON PIPE AND FITTINGS

Nominal Pipe Size

(in.)

Maximum Trench

Pay Width (in.)

½ to 2 24

4 28 6 30 8 32 10 34 12 36 16 40 20 44 24 48 30 54 36 60

1) All temporary pavement restorations for any water main work in this Contract shall not be measured but shall be considered incidental to all utility bid items.

C. SPECIAL REQUIREMENTS FOR PAVEMENT RESTORATION

Supplement Standard Specification Sections 32 01 29.64, 32 01 30.10, 32 12 16.13, and 32 13

13.33 with the following:

1. Upon completion of the permanent patch or resurfacing, the surface shall be thoroughly compacted, smooth, and free from ruts, humps, depressions, or irregularities and shall not separate from existing adjacent pavement.

2. The Contractor shall have available, at all times, a ten feet (10') straightedge approved by the Engineer. After final compaction of each course, the surface of each pavement course shall be true to the established line and grade and shall be sufficiently smooth so that when tested with a ten feet (10') straightedge placed upon the surface parallel with the center line, the surface shall not deviate more than one-eighth inch (1/8"). The transverse slope of the finished surface of each course when tested with a ten feet (10') straightedge placed perpendicular to the centerline, the surface shall not deviate more than three sixteenths inch (3/16").

3. Transverse joints on each course shall be checked with a ten feet (10') straightedge immediately after the initial rolling. If the surface of each course varies more than one eighth inch (1/8") from true, the Contractor shall make immediate corrections acceptable to the Engineer so that the finished joint surface shall comply.

4. Patches and other resurfacing work shall have a cross (transverse) slope consistent with the design of the existing roadway. Positive drainage shall be maintained to existing condition or better along all directions of the roadway to the intended curb line or drainage structure. Paving over existing gutter pan shall not alter the drainage pattern along the curb line, cover any existing drainage or underdrain outlets and/or result in overtopping of the curb.

5. For all curb to curb paving in this Contract, the Contractor shall perform pre and post- construction topographic survey of top of curb, edge of pavement and centerline of the roadway as necessary and as directed by the Engineer. All costs shall be considered incidental to the appropriate paving bid item in this Contract.

6. Repair due to unacceptable and rejected patching and resurfacing of the roadway by the Contractor shall be remedied by the Contractor at no extra cost to the City.

SC-15 TEMPORARY PAVEMENT

The Contractor shall maintain temporary pavement at any disturbed areas for no longer than 45 days following completion of construction activities.

Supplement Section 32 12 16.15, HOT MIX ASPHALT (HMA) FOR MAINTENANCE OF TRAFFIC, with the following:

PART 2 PRODUCTS

When Hot Mix Asphalt (HMA) is not available, the Contractor shall use high performance cold mix asphalt, approved by the Engineer. The Contractor to provide shop drawing/catalog cut sheet for approval by the Engineer.

High Performance Cold Mix Asphalt:

Composed of approved suitable aggregate, plant mixed with approved asphaltic liquid blend following blend manufacturer’s specifications.

a. Final mix:

1) Stripping resistance of retained coating minimum 75% when testing to ASTM-D-1664, latest revision.

2) Remain flexible and cohesive to minus fifteen degrees F (-26 degrees C).

3) Homogeneous, free of lumps.

4) Retain its adhesive qualities in wet applications.

b. Acceptable aggregate: Consist of 10% crushed stone or laboratory approved equivalent under

ASTM C-136.

Recommended Gradation:

PART 3 EXECUTION

3.17 TEMPORARY PAVEMENT

A. Place temporary pavement as specified herein unless directed otherwise by the Engineer:

1) The Contractor shall backfill the utility cut or trench using approved backfill materials as specified in this contract specifications, up to temporary paving sub-base.

2) From sub-base to the finished grade, place and compact Hot Mix Asphalt (HMA), or Engineer approved high performance Cold Mix Asphalt, in one 3” lift, to match the existing grade.

a. Stockpiling of high performance cold mix asphalt will be permitted provided it is stored in manner to prevent infiltration of deleterious material and not longer than one (1) month from date of mixing.

b. Compact high performance cold mix asphalt using uniform tamping equipment.

c. If permanent pavement replacement is not completed before December 1, replace all cold mix with hot mix asphalt bituminous concrete mix.

3) Provide hot mix asphalt for temporary curb and gutter, walks, and driveways.

4) Mark temporary pavement repairs in all roads with blue paint for water or water and sewer, and green paint for sewer in 4 inch high letters with the Contractor’s name.

5) Maintain temporary pavement in condition acceptable to Engineer until permanent pavement is placed, which shall be accomplished within 45 days of all utility work completion on any street. The only exception will be for weather related issues for which prior approval of the Resident Engineer is required.

6) If temporary pavement becomes defective and creates an emergency, commence repair to rectify situation within one (1) hour after notification by the Engineer or Engineer may arrange to have Work performed by others and deduct costs of corrective measures from monies owed by the Contractor.

Sieve Size

Percent Passing by Weight

3/8” 90-100% #4 20-55% #8 5-30% #16 0-10% #50 0-5% #200 0-2%

PART 4 MEASUREMENT AND PAYMENT

Temporary pavement using hot mix asphalt (HMA) or high performance cold mix asphalt shall not be measured, but will be considered incidental to all appropriate utility bid items in this Contract.

SC-16 PERMANENT PAVING RESTORATION

Permanent pavement installation and pavement repair shall be completed in accordance with the Contract Drawings and Standard Details. The Contractor shall maintain temporary patches or plates as indicated below for no longer than 45 days following completion of construction activities.

All temporary patches of pavement and sidewalk cuts shall be promptly stenciled, which shall include the Contractor’s name and patch installation date, and shall be kept properly identified until permanent restoration is performed. Temporary patches must be maintained at grade, in a condition acceptable to the Resident Engineer. If steel plates are utilized, they must be installed in accordance with Baltimore City Revised Standard BC-576.17.

Failure to comply with DOT’s street/sidewalk restoration policies may result in violation notices issued by DOT, along with the imposition of fines. Any fines assessed must be paid in a timely manner and all cost shall be borne solely by the Contractor. Unpaid fines may be withheld from pay requests and monthly estimates.

DPW reserves the right to perform and complete permanent paving restoration on its own should the Contractor fail to complete pavement and/or sidewalk restorations in a timely and efficient manner as determined by DPW. Any costs incurred by DPW to complete pavement and/or sidewalk restorations may be withheld and/or recovered from the Contractor’s approved monthly estimates upon formal notification from DPW.

SC-17 STREET LIGHTING

In the event a street light must be removed for construction purposes, the Contractor shall notify the Street Lighting Maintenance Section of the Baltimore City Department of Transportation, the Transportation Engineering and Construction Division, at 410-396-4446, to schedule and complete that item of work.

The Contractor shall provide at least fourteen (14) days notice. The Contractor must provide temporary lighting prior to the removal of the street lights. The Contractor will be responsible for the installation, maintenance and removal of the temporary lights and related equipment. The Contractor must provide power for any temporary lights installed. All temporary lights must be in service prior to the removal of the street lights and remain in service until the street lights are reinstalled and operating.

The Contractor shall be responsible for maintaining the street light cable during construction. If any crossings are removed or damaged, the Contractor must replace the crossing per current City standards at no cost to the City. If a street lighting duct or cable is hit, the Contractor shall immediately notify Street Lighting Maintenance, at 410-396-4446 and Mr. Eric Barger of Baltimore Gas and Electric Company (BGE), at 410-859-9466. If a street light pole base or pole is damaged during construction, it must be replaced per current City standards at no cost to the City.

All street lighting related work must be done in coordination with the Street Lighting Maintenance Section of the Baltimore City Department of Transportation, the Transportation Engineering and Construction Division, and the Baltimore Gas and Electric Company.

SC-18 SUPPORT AND/OR PROTECTION OF EXISTING UTILITIES

The Contractor shall support street light poles adjacent to the excavation and all existing utilities within the limits of excavation. Should any utility and/or utility structure, in the opinion of the Contractor and verified by the Engineer, be impacted by the Contractor’s work, the utility shall be supported, protected and/or temporarily relocated as needed to maintain service and accommodate the Contractors work without cost to the City. Refer to Standard Specification Sections 01 76 04, UTILITIES, 01 76 05, REMOVAL OF OBSTRUCTIONS, and 01 76 06, PROTECTION, SHIFTING, OR REMOVAL OF STRUCTURES BY OWNERS OF SAME for additional requirements.

Fourteen (14) working days prior to starting excavation, the Contractor shall submit to the Engineer the proposed method of utility support for review and acceptance.

No separate payment will be made for the cost of temporary or permanent support and/or protection of existing utilities over, under or adjacent to the excavations for proposed work. All work, materials, labor, or other costs associated with temporary or permanent support and/or protection of existing utilities will be considered incidental to the work required under this Contract.

Bracing of utilities or utility poles (other than BGE poles) shall be designed by a Maryland Registered Professional Engineer, and the bracing plan submitted to the Engineer for review and acceptance.

Bracing of utility poles will not be measured fro payment and shall be considered incidental to the work.

The Contractor must notify BGE at least 4 weeks in advance to support BGE poles affected by his work. BGE will brace the poles at no cost to the Contractor. Contact Shaahin Bahmani at 410-470- 7868 or 410-672-0232.

SC-19 SCHEDULES AND REPORTS

Specification Section 01 32 16 of the Standard Specifications concerning the provision and periodic updating of progress schedules, and coordination with the approved schedule of values applies to this project.

SC-20 REVISIONS TO THE ASPHALT PAVING SPECIFICATIONS

Supplement Standard Specification Section 32 12 16.13 of the Standard Specifications with the following:

2.1 MATERIALS

References to the following draft or provisional standards shall be substituted as follows:

AASHTO MP1 shall be M320 Binder ETG draft shall be PP42 AASHTO MP2 shall be M323 AASHTO PP28 shall be R35 AASHTO TP4 shall be AASHTO T 312

Reference of RAP less than 15 percent should read less than 20 percent.

3.11 SAMPLING AND TESTING FOR DENSITY

Delete in its entirety and replace with the following:

3.11 SAMPLING AND TESTING FOR DENSITY AND MIXTURE

Mixture sampling shall be performed before the material is compacted. Density testing shall be performed before allowing traffic or construction equipment on the placed mat and before the placement of the next lift. All sampling will be done by the Contractor. Quality Control testing will be performed by the Contractor. Acceptance testing will be performed by the City. All tests shall be performed by Certified Technicians and Testers in accordance with MSMT 731.

A. Mixture Sampling

An HMA mixture lot size is approximately equal to 6000 tons of a mix per project. A mix lot ends on the day when 6000 tons is reached. A mixture sublot size shall not exceed 1000 tons. A sublot size up to 200 tons can be combined with the previous 1000 ton sublot placed on the same day. A mix lot constitutes all sublots of a mix created during the production of required tonnage for a lot as defined herein. A new lot number for a mix will be given when there is a change in the approved job mix formula. Samples shall be obtained from the mat behind the paver in accordance with MSMT 457, Sampling HMA Prior to Compaction, as witnessed by the Engineer.

A minimum of two samples per mixture sublot, shall be obtained. The Contractor shall retain half of the mixture samples for Quality Control testing and the Engineer will take possession of the remaining mixture samples for acceptance testing.

1. Quality Control Testing

The Contractor shall test a minimum of one mix sample per sublot in conformance with MSMT 735 for asphalt content and gradation after each days paving operation and make the results available to the Engineer within five (5) working days.

2. Acceptance Testing

The Engineer will test mixture samples in conformance with MSMT 735 for asphalt content, gradation, and volumetrics. The Engineer may accept quality control test data without comparing them with acceptance data based on the Contractor’s past quality control and performance history.

Acceptance testing of these mixture samples will be in conformance with MSMT 735, Table 2. Mixture acceptance will be based on a composite percent within Specification limits (CMPWSL) of the lot based on asphalt content, voids total mix (VTM), percent passing No 4, No. 8, and No. 200 sieve material for dense mixes and gap-graded mixes.

B. Compaction Testing

An HMA compaction lot size shall equal one paving day’s production per mix. A lot shall be divided into a minimum of five equal sublots. A sublot shall not be greater than 500 tons.

When a paving day’s production per mix is greater than 2500 tons, then each sublot size shall be 500 tons or fraction thereof. Core locations shall be selected by the Engineer in conformance with MSMT 459 and taken by the Contractor in conformance with MSMT 458, as witnessed by the Engineer. The diameter of the cores shall be 6 in. except that a 4 in. core may be used for mixes smaller than 25 mm. Additional core locations for acceptance testing can be selected by the Engineer outside of the standard paving width.

A minimum of two cores per sublot shall be taken. The Contractor shall retain half of the cores for Quality Control testing and the Engineer will take possession of the remaining cores for acceptance testing.

1. Quality Control Testing

The Contractor shall test at a minimum one core per lift, per mix design, per daily occurrence, in accordance with MSMT 452. The Contractor shall make quality control test data available to the Engineer no later than the beginning of the next paving…